MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE
Content CDR content Update on the transport strategy 2 CLIC module Working Group Keith Kershaw 27 Sept 2010
CDR content – 6.5Transport and installation – 6.5.1Overview and challenges – 6.5.2Surface and shafts – 6.5.3Underground – 6.5.4Cost Considerations 3 CLIC module Working Group Keith Kershaw 27 Sept 2010
Items to be transported Modules and their supports Magnets Vacuum pipes, Beam dumps Racks Cooling and ventilation equipment Electrical cables and cable trays Others? 4 CLIC module Working Group Keith Kershaw 27 Sept 2010
Module data 5 CLIC module Working Group Keith Kershaw 27 Sept 2010
Concept vehicle 6 CLIC module Working Group Keith Kershaw 27 Sept 2010
Tunnel cross section 7 CLIC module Working Group Keith Kershaw 27 Sept 2010
Shaft cross section 8 CLIC module Working Group Keith Kershaw 27 Sept 2010
UTRC cavern – transport arrangements 9 CLIC module Working Group Keith Kershaw 27 Sept 2010
Magnets 10 CLIC module Working Group Keith Kershaw 27 Sept 2010
Update on module transport strategy A reminder 11 CLIC module Working Group Keith Kershaw 27 Sept 2010
Some Conclusions from Nov 2009 Ensure clear interconnection plane and clearance in order to allow installation and removal of one module between two others Decide if main beam quadrupoles transported and installed separately Consider whole installation sequence covering supports, alignment equipment and interfaces between girders and their supports Module mock ups should be used to test installation issues (this will increase focus on installation problems during design). 12 CLIC module Working Group Keith Kershaw 27 Sept 2010
Module integration Sept CLIC module Working Group Keith Kershaw 27 Sept 2010
Conceptual drawing 14 R. Leuxe CLIC module Working Group Keith Kershaw 27 Sept 2010
Module mock –ups (Nov 2009 slide) 15 CLIC module Working Group Keith Kershaw Install and remove central module with outer modules in position. For example by using overhead crane 27 Sept 2010
Test module – installation plane + sequence? 16 CLIC module Working Group Keith Kershaw 27 Sept 2010
Conclusions (basically as Nov 2009) Ensure clear interconnection plane and clearance Consider how main beam quadrupoles transported and installed Don’t forget lifting points, support points and transport restraints Consider whole installation sequence covering supports, alignment equipment and interfaces between girders and their supports (Full sequence starts with assembly) Test modules should be used to (design for + ) test installation issues e.g. with overhead crane or hoist Installation of other items in tunnel still to be considered. 23 Nov CLIC module Working Group Keith Kershaw