The MICE Target Lara Howlett University of Sheffield.

Slides:



Advertisements
Similar presentations
1 MICE Target Status Chris Booth 3 rd March 2004.
Advertisements

MICE Magnetic Investigation of T2 MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
Target Operations A summary of Target Operation to Date Paul Hodgson The University of Sheffield.
MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
MICE Target Report Chris Booth (for target team) Sheffield 23 rd April 2009.
Progress on Target Design Chris Booth Sheffield 2 nd August 2004.
MICE TARGET OPERATION C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England.
Target Status Report Lara Howlett University of Sheffield.
MICE MICE Target Status P J Smith CM 25 Wed 4 th November 2009.
MINIATURE ENGINEERING SYSTEMS GROUP MINIATURE CENTRIFUGAL COMPRESSOR TESTING Presented by Dipjyoti Acharya.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
ISIS Related Issues for MICE Adam Dobbs Proton Accelerator Development Meeting, RAL 24 th March /03/20111A. Dobbs.
MICE Target Development Chris Booth Sheffield 8 th June 2006.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICO Alain Blondel 17 March MICO Alain Blondel 17 March MICE target test-run March 2008 Friday 14/03/2008 6:00-> 18:00 Saturday 15/03/2008.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Progress on Target Design Chris Booth Sheffield 14 th July 2004.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
P J SmithUniversity of Sheffield1 MICE Target Electronics Paul J Smith University of Sheffield Fermilab 10 th June 2006.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
Target Test Report Given permission for a maximum of 5000 actuations. Performed 3679 actuations, 3654 with the gate valve open. Ran target at 0.4 Hz to.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
Target Specifications & History (to avoid reinventing a broken wheel!) 2 nd December 2009 Chris Booth The University of Sheffield.
Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
MICE Target Review Chris Booth Sheffield 12 th June 2006.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
MOM - M.ApollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Summary of MICE operations – 14/15 March 2008 AIMS - establish MICE beamline in ISIS synchrotron.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
14/1/20097 January 2009MICE CM23 - Harbin - Beamline Session1 MICE Beamloss Data Adam Dobbs.

DESIGN AND OPERATIONAL EXPERIENCE OF THE MICE TARGET Target Drive The linear electromagnetic drive that has been designed to meet these requirements consists.
MICE Target Report Video Conference 05/07/07 Chris Booth Sheffield 5 th July 2007.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Target Mechanism P J Smith University of Sheffield MICE CM 18 RAL June 2007.
Chris BoothMICE-UK I.C. 16th January Useful meeting held at RAL last Thursday. Representatives of MICE, ISIS & others with Sheffield electronic &
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
MICE Target – Design Update and Test Plans Chris Booth Sheffield 22 nd October 2005.
1 MICE TARGET STATUS 23 rd February 2007 CM17 - CERN Paul J Smith University of Sheffield.
MICE MICE Target Mechanism Control Electronics Upgrade P J Smith – University of Sheffield James Leaver – Imperial College 2 nd March 2009.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
MICE Target - Risk Lara Howlett University of Sheffield.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
MICE Target Development Lara Howlett University of Sheffield.
Status of Target Design Chris Booth Sheffield 28 th October 2004.
MICE TARGET OPERATION C. Booth, P. Hodgson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 – The MICE Experiment2 - The.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Jason Tarrant / November 2008 MICE Target Mechanical Design l Jason Tarrant – STFC l Introduction »Investigations into target shaft failure »Current suspicions.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Chris BoothUniversity of Sheffield 1 Target Status & Progress 1 st February 2006 Disappointingly slow progress over last 2 months. However, progress is.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
Target Status 27 th August 2009 Chris Booth The University of Sheffield.
The Target Drive For The MICE Experiment Control and Infrastructure Optical Readout and Drive Electronics Target Drive A linear electromagnetic drive has.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Chris Booth Sheffield 29th March 2006
Stator Plan & Schedule Chris Booth 2nd March 2009
Target Installation Plan
P. J. Smith on behalf of the MICE target team.
MICE Target Report Video Conference 29/11/07
Status of Target Design
BGC Collaboration Meeting –
Presentation transcript:

The MICE Target Lara Howlett University of Sheffield

Overview Improvement to components Current performance of target Assembly tests at RAL Plans for November tests

Overview of components

Flanges All flanges have been redesigned to give improved indium seals These seals have been tested under vacuum twice and have held vacuum first time on both occasions Robust – an assembled target setup has been transported from Sheffield to RAL without any problems in the vacuum seals

Optics A new optics system has been built Flat windows – meaning laser beams can all be parallel Arm to hold collimators machined from one piece means only minimal adjustment is required for alignment Robust – transported from Sheffield to RAL with no need for realignment

Shaft New cross shape shaft Machined from a single piece of titanium Only magnets and optics comb need to be attached

Stator Water cooling jacket has been redesigned bringing it much closer to the coils The stator can now be run at 1Hz and remain at a temperature of 25 degrees with cooling and 35 degrees with rt water

Control Electronics Significant improvements have been made to electronics –Optical isolation between control and power electronics –Optical isolation between racks These give greatly improved stability Development of electronics for November tests –Digital to analogue converter of position information –Board to allow selected delay of ISIS signal

Full Power Electronics Full power electronics is being produced at Daresbury This was brought to Sheffield during September and tested with the actuator There are some problems with the current control which need to be fixed before this can be used

Target Performance High stability of electronics has been achieved Over 50,000 pulses have been achieved without failure Target achieves acceleration of 16g with 10A

Closer look at a pulse

Target Performance Dip depths between 10mm and 45mm have been achieved Time for pulses 25ms to 65ms Adjustments of order 0.6mm are currently possible

Fit to data Assuming flat acceleration in each section it is possible to fit the pulse shape to 3 quadratics It is then possible to look at velocities and accelerations

Velocity and Acceleration

Error on dip depth Dip depths remains very stable RMS 0.07mm Granularity of readout 0.15mm

Error on time of lowest point Time stability is currently hard to ascertain due to problems with readout RMS for time error on ½ a pulse order of 50 micro seconds

RAL Tests Tests took place at RAL during September All mechanical and electronic equipment was transported from Sheffield to RAL All equipment worked without any adjustments being required –All mechanics –All optics –All electronics

RAL Tests Good vacuum achieved 2.6x10 -8 mbar Over 10,000 pulses achieved under vacuum (1Hz 15mm) No changes to vacuum observed during operation Measurements taken to define absolute position

RAL tests

RAL Tests

Plans for November Tests We are currently all systems go for November tests Detectors and readout Bill Murray and Kenny Walaron Run plan discussed and agreed Target to be installed during shutdown 16 th Oct-27 th Oct 1 or 2 shifts in machine startup 28 th Oct- 2 nd Nov

What we believe we can achieve

Conclusions New mechanical designs have solved –Problems with optics –Problems with indium seals –Problems with cooling Successful tests carried out at RAL in September Due to go in for target tests in November This should give as input for further optimisation of design