CERN, Geneve 14 Jun WPSS-PHASE 2 WPSS PH-2 Scheduling
CERN, Geneve 14 Jun General Presentation of Tasks: –Helmet Attachment –Handheld Camera –Software –Integration –Deployment *Provisional dates (under discussion, review and agreement)
CERN, Geneve 14 Jun Task: Helmet Att. 30 Jun: Completion of conceptual design for Helmet attachment 20 Aug: First implementation of Helmet attachment –CERN -> Casing –PRISMA -> Electronics 30 Sep: Final implementation of Helmet attachment –As above
CERN, Geneve 14 Jun Task: Handheld C. 20 Jul: Completion of conceptual design for Handheld Camera 10 Sep: First implementation of Handheld Camera –CERN -> Casing –PRISMA -> Electronics 20 Oct: Final implementation of Handheld Camera –As above
CERN, Geneve 14 Jun Task: Software 30 Jun: Final specifications (after review) 15 Aug: SW completion (PTU-Helmet Camera side) 31 Oct: SW completion (Server side)
CERN, Geneve 14 Jun Tasks: Integration 31 Aug: PTU-Helmet Attachment SW system (with prototype PTU + prototype Helmet attachment) 15 Nov: 5x PTU-Helmet Attachment- Handheld Camera Systems Quality- Control Completed (in Lab conditions)* *Assumption on PTU availability
CERN, Geneve 14 Jun Task: Deployment 1-15 Nov(T): Christos come to CERN (approx. 1 month before opening for operations) T+15: Setup/resolution of CERN WiFi- WPSS system T+30: 5x Fully tested and fine-tuned PTU-Helmet Attachment-Handheld Camera Systems (CERN) T+45: Completion of deployment (daily routine state: )
CERN, Geneve 14 Jun Timeline
CERN, Geneve 14 Jun Gantt
CERN, Geneve 14 Jun Conclusion Best Effort Estimates! Critical assumption: PTU/HW availability on time! THANK YOU