LBNF Test Cryostat Requirements David Montanari / Jack Fowler Jan 29, 2015 Rev. 11.

Slides:



Advertisements
Similar presentations
Design of the T962 Cryostat L. Bartoszek BARTOSZEK ENGINEERING 5/10/07.
Advertisements

TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
LBNE 35 ton prototype Phase 1 summary Terry Tope Fermi National Accelerator Laboratory All Experimenters’ Meeting – Fermilab – May 19, 2014.
Cryogenic discussion and update 30 October 2014Neutrino platform.
LAr1-ND Conceptual Design Review of Status June 25 Craig Thorn.
LAr1-ND David Montanari Fermi National Accelerator Laboratory CERN – Feb 16, 2014.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
CERN LBNE Test Experiment. Plan view of Bat
LBNE Reconfiguration Workshop – April 2012 FD Assumptions and Cost Estimate 1 Bruce Baller.
LAr1-ND Cryogenics Concept David Montanari Neutrino Cryogenics Requirements Meeting 24 September 2014.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
ICARUS Cold Vessels Thermal insulation Project progress report.
ILC / ILD TPC Requirements of the support mechanics Volker Prahl ILD Workshop 2013 Cracow
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
LAr1-ND Cryostat proposal David Montanari Neutrino Cryogenics Requirements Meeting 24 September 2014.
Single Phase Test at CERN Cryostat/Cryogenics Update
FLARE Constructing the detector First FLARE Workshop November 4-6, 2004 Rafael Silva Fermilab / PPD / MD Fermilab Liquid Argon Experiments.
WA104 Cryogenics Design Status David Montanari / Johan Bremer May 21, 2015 Rev. 1.
TPC Design Concept: From MicroBooNE to LAr20
Some naïf ideas on cryostats , BNL-LBNF meeting D.Mladenov, M.Nessi.
Grounding Guidelines Developed for LBNE
LAr1 Plans at FNAL Bruce Baller - Fermilab. Outline LAGUNA Meeting - Mar  LBNE LAr detector overview  Prototyping plan  1 kton prototype.
Single Phase Test at CERN David Montanari / Johan Bremer / Jack Fowler / Dimitar Mladenov Apr 2, 2015 Rev. 2.
Neutrino Cryogenics Requirements Meeting 25/09/2014 Day 1 review.
Concept Design for LBNF Far detector (LAr single phase)
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Installation of the T600 at Fermilab CSN2, September 22,
Cryogenics Fabrication Plans & Constraints David Montanari (on behalf of the CERN Neutrino Cryogenic Group) ProtoDUNEs Meeting Feb 23, 2016.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
Wire and Cathode Planes - Current Concept (work in progress) PPD Internal Review – 2 nd Part April 19 th, 2005 Rafael Silva FLARE Fermilab Liquid Argon.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Single phase ProtoDUNE detector installation Plans and Constraints Jack Fowler Duke University 23-Feb-2016.
Laser Calibration of a Liquid Argon TPC G. Sinnis J. Danielson W. Sondheim.
Single-Phase ProtoDUNE Construction Planning Jim Stewart LBNC January 11, 2016.
The ModuLAr Project LoI discussion INFN-LNL 21/11/2007 Legnaro (PD)
35 Ton LAr Impurity Distribution Measurements and CFD simulation Erik Voirin – Fermilab – Thermal and Fluids Engineering Group / Engineering.
Value Engineering proposal: Putting APA’s on outside or put short drift cell on outside April 21, 2014, Post meeting rev. April 25, 2014 Russ Rucinski.
DUNE Single Phase Prototype Cryostat overview David Montanari / Jack Fowler / Dimitar Mladenov Apr 17, 2015 Rev. 15.
Recent Changes to the FD TPC Design Bo Yu Oct. 20, 2015.
Installation of the T600 at Fermilab Fermilab, February 15,
Neutrino Platform Proximity Cryogenics Functional Design M.Chalifour 14/04/2016 M. Chalifour - TE/CRG-CI 2.
ProtoDUNEs Interface documents (NP-02, NP-04) David Montanari (on behalf of Redouan A, Mark A, Johan B, Michel C, Joaquim C, Aurelien D, Kevin H) Apr 14,
WA105 6x6x6 Cryogenics David Montanari / Johan Bremer Sep 21, 2015 Rev. 1.
TPC Support Installation 26 Apr 2016Dan Wenman Mechanical Engineer1 Overview Installation of the support rails Details of the rail from the SAS to the.
ProtoDUNE Single Phase (NP-04) P&ID David Montanari (on behalf of Mark A, Johan B, Michel C, Joaquim C, Kevin H) CERN Neutrino Platform General Meeting.
SBND Cryostat Requirements David Montanari, Michael Geynisman, Dimitar Mladenov, Joe Howell 14 October 2015.
European cryogenic days Membrane cryostats for large volume neutrino detectors June 9 th, GENEVA.
Warm Vessel Leveling Islands (Piers)
The LBNF cryostats Marzio Nessi, CERN 16 March 2017.
Installation of the T600 at Fermilab
Overview of the Long-Baseline Neutrino Facility Cryogenic System
David Montanari / Johan Bremer / Jack Fowler / Dimitar Mladenov
ProtoDUNE – DSS Installation, Alignment and QA
SBN Far Detector Installation & Integration
IT-4189 Supply and installation of a cryogenic distribution system
Proximity Cryogenics P&IDs Meeting
Product Presentation January 2010.
HFM Test Station Main Cryostat
Proximity Cryogenics P&IDs meeting
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
INSTALLATION SEQUENCE
First tests on the roll-formed field cage.
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LARP Vertical Test Facility
Warm structure requirements :
Pressure vs height (solid CPA plane)
TPC Support and Constraint TPC Support
Test box for ProtoDUNE SP – Integration Test
LIFT,ESCALATOR AND MOVING WALKS
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

LBNF Test Cryostat Requirements David Montanari / Jack Fowler Jan 29, 2015 Rev. 11

Outline Intro Beam Cryostat requirements Cryostat top requirements Cryogenic system requirements Summary 2

Intro The goal of this prototype is to study, characterize and validate the design of the full scale detector components for a future far detector of a neutrino long baseline, which aims to study neutrino oscillations, search for CP violation in the lepton sector and perform other physics measurements. To test beam data for at least one additional beam direction at a relative large angle with respect to the drift direction would be a valuable cross-check of reconstructing modeling. This could be a second phase for the prototype. The general idea is to build a flexible facility that can host other detectors in the future. In order to achieve 100% containment, the active detector volume would have to be at least 5 m in longitudinal direction and ~4-5 m in the transverse direction (with respect to the beam). 3

Beam The H4ext beam line in EHN1 at CERN can provide electron, muon, pion and proton beams. The charged particle momentum is selectable and covers range from 200 MeV to ~10 GeV. The nominal configuration is to steer the beam horizontally into the cryostat with the option of bending the beam up to +/- 10 degrees to study angular dependence. 4

Assumptions for TPC configuration APA: three (3) wide and one (1) high. 6,000 mm x 2,300 mm APA dimensions. Equates to ~ 6,884 mm total height. Also assumes the frame will be produced with 4” x 3” structural tubing. – Note: the cryostat height will be based on a 6,600 mm APAs even though we plan to use 6,000 mm APAs to allow flexibility for future testing. CPA: to cover APA area CPA-APA-CPA, with the possibility to do APA-CPA-APA. Drift distance: 2,500 mm for each side of APA. Orientation: parallel to the walls of the cryostat. Clearances: – 300 mm from floor to CPA to prevent HV discharge. – 1,000 mm on 3 sides to allow for access and egress around the outside of the TPC. – 300 mm of liquid above the CPA to prevent HV discharge. – 1,200 mm on hatch end of TPC for cryogenic piping and instrumentation. Ullage: 900 mm (based on the far detector design). 5CERN test Cryo size discussion 16-Jan-2015

ParameterValue Type of structureMembrane cryostat Membrane material SS 304/304L, 316/316L or equivalent. Other materials upon approval. FluidLiquid Argon (LAr) Outside reinforcement (Support structure) Self standing concrete/steel enclosure with frost prevention (Floor + Sides) TPC size Length: 3 x 2.30 = 6.90 m Width: 2 x 2.50 = 5.00 m Total Height: 6.9 m Minimum inner dimensions (flat plate to flat plate) Physics requirements + Installation. Assumes 0.9 m ullage (LBNF value) 7.3 m (W) x 9.5 m (L) x 8.4 m (H) Maximum static heat leak10 W/m^2 Operating gas pressurePositive pressure. Nominally 1.0 psig (~70 mbar). Design Pressure (Discussion in progress)5.0 psig (~350 mbar) + LAr head Design Temperature77 K (liquid Nitrogen temperature for flexibility) All surfaces in the ullage during operations< 100K Max noise/vibration/microphonics inside cryostatLAr pump outside the cryostat Beam window (Work in progress)In the center of the active volume Accessibility after operationsCapability to empty the cryostat in 30 days and access it in 60 days Lifetime / Thermal cycles Consistent with the LAr program TBD Cryostat Requirements – 1 6

ParameterValue LAr Loading on the floor of the cryostat15 psi Total force on the floor of the cryostat (LAr mbarg GAr) 782 ton (at the point of action) Total force on the sides of the cryostat (LAr mbarg GAr) 346 ton (short side), 450 (long side) at the point of action Max noise/vibration/microphonics inside cryostatLAr pump outside the cryostat Beam window (Work in progress)At the center of the active volume Accessibility after operationsCapability to empty the cryostat in 30 days and access it in 60 days Lifetime / Thermal cycles Consistent with the LAr program TBD Cryostat Requirements – 2 7

EHN1 CERN test Cryo size discussion 16-Jan CERN cryostat Pit B Bridge Crane LBNE cryostat

Plan view – EHN1 CERN test Cryo size discussion 16-Jan CERN cryostat Pit B LBNE cryostat Bridge Crane

Side view TPC in Cryostat CERN test Cryo size discussion 16-Jan Top cap Containment vessel Liquid level APAs Insulation Membrane

End view TPC in Cryostat CERN test Cryo size discussion 16-Jan ,142 mm

Crane clearance above TPC/Cryo CERN test Cryo size discussion 16-Jan Hook height 9.9 m above gallery floor Current hook height above cryostat as modeled 7,709 mm top cap thickness included Pit B depth 9.0 m

Cryostat Top

ParameterValue ConfigurationRemovable metal plate reinforced with trusses anchored to the membrane cryostat support structure. Contains multiple penetrations of various sizes and a manhole. Number, location and size of the penetrations TBD. Provisions shall be made to allow for removal and re-welding six (6) times. Plate/Trusses non-wet materialSteel if room temperature. SS 304/304L or equivalent if at cryogenic temperature. Wet materialSS 304/304L, 316/316L or equivalent. Other materials upon approval. FluidLiquid Argon (LAr) Design Pressure (Discussion on-going)5.0 psig (~350 mbar) Design Temperature77 K (liquid Nitrogen temperature for flexibility) Inner dimensionsTo match the cryostat Maximum allowable roof deflection0.024 m Maximum static heat leak15 W/m^2 (Greater than sides/bottom to allow for the penetrations) All surfaces in the ullage during operations< 100K Additional design loads-Top self-weight -TPC (~3,000 kg on each anchor) -TPC anchors (TBD) -Live load (488 kg/m^2) -Electronics racks (400 kg in the vicinity of the feedthroughs) -Services (150 kg on every feed through) TPC anchorsCapacity: 3,000 kg each anchor. Number and location TBD (Minimum 6). Cryostat Top Requirements – 1 14

ParameterValue Hatch opening for TPC installation3,550 mm x 2,000 mm Grounding plate1.6 mm thick copper sheet brazed to the bottom of the top plate. Lifting fixturesAppropriate for positioning the top and the different parts that constitute it. Cold penetrationsMinimum 4. Location and design TBD. Lifetime / Thermal cycles Consistent with the LAr program TBD. Cryostat Top Requirements – 2 15

Infrastructures

Assumptions for external cryostat dimensions Outer support structure thickness: 500 mm. Insulation thickness: 800 mm (might be 900 mm??). Top cap thickness: 1,500 mm. Cryostat external dimensions: 11,191 mm (H) x 12,122 mm (L) x 9,882 mm (W). Hook height above floor of pit B: 18,900 mm. Hook clearance over top cap: 7,709 mm. APA height: 6,289 mm. Clearance between height of APA and hook over cryostat: 1,420 mm. 17CERN test Cryo size discussion 16-Jan-2015

ParameterValue Cryostat footprint (estimate)12,122 mm (L) x 9,882 mm (W) Work area around the top of the cryostat (platform type)2.0 m around the whole perimeter Lay down spaceWill be defined in MOU Crane coverageOver the cryostat and the lay down space Crane capacity for TPC (Not including top cryostat)5 ton Minimum hook height above the cryostat for TPC installation4.5 m Clean Room space??? Do we need it ??? Cryostat Infrastructures Requirements 18

ParameterValue Isolation1)The cryostat membrane and any supporting structure, whether it is a steel structure or a concrete and rebar pour, shall be isolated from any building metal or building rebar with a DC impedance greater than 300 kohm. 2)All conductive piping penetrations through the cryostat shall have dielectric breaks prior to entering the cryostat and the top plate. Grounding1)The cryostat, or “detector” ground, shall be separated from the “building” ground. 2)A safety ground network consisting of saturated inductors shall be used between detector ground and building ground. 3)Parameters TBD. Top plate grounding 1)If the cryostat is contained within a concrete pour, the top plate shall be electrically connected to any rebar used in that pour, and the rebar shall be conductively tied at regular intervals. Parameters TBD. 2)The top grounding plate shall be electrically connected to the cryostat membrane by means of copper braid connections. a)Each connection shall be at least 1.6 mm thick and 63.5 mm wide. b)The length of each connection is required to be as short as possible. c)The distance between one connection and the next one shall be no more than 1.25 m. d)The layout can follow the profile of several pieces of insulation, but it shall be continuous. e)The DC impedance of the membrane to the top plate shall be less than 1 ohm. Cryostat Grounding/Isolation Requirements 19 Note: The layout of the top plate grounding is outlined in the next slide.

Top plate grounding layout 20

Cryogenic System

ParameterValue LocationPreferably not in front of the cryostat (on the beam) LAr purity in cryostat10 ms electron lifetime (30 ppt O2 equivalent) GAr Piston purge rate of rise 1.2 m/hr Membrane cool-down rate From manufacturer TPCs cool-down rate < 40 K/hr < 10K/m (vertically) Mechanical load on TPC The LAr or the gas jet pressure shall not apply a mechanical load to the TPC greater than 200 Pascal. Nominal LAr purification flow rate (filling/ops) 5.5 day/volume change All surfaces in the ullage during operations< 100K GAr purge within insulation 1 volume change/day of the open space between insulation panels Lifetime of the cryogenic system Consistent with the LAr program TBD Cryogenic System Requirements 22

Summary 8.4 m (H) x 9.5 m (L) x 7.3 m (W) is the internal size required by the TPC elements. Using the assumptions listed (800 mm insulation, 500 mm outer structure, 1,500 mm top cap), the external dimensions are: 11.2 m (H) x 12.1 m (L) x 9.9 m (W). The goal is to be able to run the detector before the long shut-down. The design should start as soon as practical with GTT. The specifications should be formalized in a format that can be used to issue a contract. 23CERN test Cryo size discussion 16-Jan-2015

Backup

Cryostat sizing Length APA width 2300 mm (x 3) mm of edge boards on each side of the center joint (x 4). 50 mm from the SS APA (active area boundary) frame to field cage (x 2) mm diameter of CPA tube (x 2) mm clearance to membrane for access and egress mm clearance for piping and instrumentation. 60 mm depth of corrugations (x 2) mm total length of cryostat. 25CERN test Cryo size discussion 16-Jan cm

Cryostat sizing Width 76.2 mm - APA thickness 3” mm height of wire layers on each side (x 2) mm drift distance (x 2) mm – Half the diameter of 3” CPA frame (x 2) mm to membrane for access and egress (x 2). 60 mm depth of corrugations (x 2) mm total width of cryostat. 26CERN test Cryo size discussion 16-Jan-2015

Cryostat sizing Height for 6.6 m APA 6,638.7 mm - APA side tube length mm - Distance from top of the cross tube down to the beginning of active volume mm – Diameter of CPA tubing above active volume. 300 mm of liquid above CPA tube. 16 mm boards at bottom of frame mm – Diameter of CPA tubing below APA bottom boards. 300 mm of liquid below CPA tube. 100 mm of space reserved for piping at bottom of cryostat. 7,491 mm is liquid level height. 900 mm ullage based on far detector design. 60 mm depth of corrugations (x 2) Total height from floor to underside of top cap = 8,391 mm. Total inner volume 582 m 3. 27CERN test Cryo size discussion 16-Jan-2015 Floor of Cryostat Space for piping CPA APA APA active volume Liquid Volume Bottom boards of APA

Cryostat Height sizing (6.0 m APA) 6,060.1 mm - APA side tube length 76.2 mm - Distance from top of the cross tube down to the beginning of active volume mm – Diameter of CPA tubing above active volume. 300 mm of liquid above CPA tube. 16 mm boards at bottom of frame mm – Diameter of CPA tubing below APA bottom boards. 300 mm of liquid below CPA tube. 100 mm of space reserved for piping at bottom of cryostat. 6,912 mm is liquid level height. 900 mm ullage based on far detector design. 60 mm depth of corrugations (x 2) Total height from floor to underside of top cap = 7,812 mm. Total inner volume 542 m 3. 28CERN test Cryo size discussion 16-Jan-2015 Floor of Cryostat Space for piping CPA APA APA active volume Liquid Volume Bottom boards of APA

Conclusions 8.4 m H x 9.5 m L x 7.3 m W is the internal size required by the TPC elements. Using the assumptions listed, this yields these external dimensions – 11.2 m H x 12.1 m L x 9.9 m W. How this fits into the overall plan and layout for pit B needs to be evaluated. There are some opportunities to reduce the size if necessary. – Design cryostat height for 6.0 m APAs. – Reduce the access and egress around the TPC. – Reduce the ullage. – Move cryogenic equipment outside of cryostat. – Reduce number of APAs. 29CERN test Cryo size discussion 16-Jan-2015

Current cryostat schedule Preliminary Design: Fen-Jun Design Review: Jul-Sep Final Design/Procurement: Oct 2015-Sep Construction: Oct 2016-Jul CERN test Cryo size discussion 16-Jan-2015