MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.

Slides:



Advertisements
Similar presentations
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
Advertisements

MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
Paul drumm; 3rd December 2004; AFC MM 1 Why? Goal: Ultimate (CCLRC defined) Safety & Design Review –How do we get there? We need a Process –What is needed?
1 Infrastructure at RAL Iouri Ivaniouchenkov, RAL MICE Collaboration CERN, 29 March 2003.
MICE Installation and Commissioning meeting RAL, 12 June 2007 Diffuser Oxford University.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
1 MICE Hall Layout MICE Collaboration Meeting, LBNL, February 12, 2005 Paul Drumm for Yury & the RAL team.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
Iouri Ivaniouchenkov RAL Safety considerations at RAL July 9, RAL MICE Collaboration Meeting 1.
Integration GlueX Detector Integration Mission: To ensure systems meet or exceed physics driven goals To ensure that detectors are designed in a sensible.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
(1/15) 08/05/13 – RadWG meeting J. Mekki M. Brugger PS East Area Update Outline Layout updates of the facility Conveyer options Mock-up preparation and.
Project manager report paul drumm CM16 October 2006.
MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Layout and Installation MICE Collaboration Meeting, RAL, October 27-29, 2004 Elwyn Baynham, Tom Bradshaw, Paul Drumm, Matthew Hills, Yury Ivanyushenkov,
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
1 MICE Mtg Oct 2002 Elwyn Baynham RAL Implementation of MICE at RAL Work done in Engineering and ISIS Departments Rutherford Appleton Laboratory Contributors.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE Radiation Shielding MICE Phone Conference, 28 January 2004 Yury Ivanyushenkov Engineering Department, RAL.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
Hall clearance completed Revisiting Water & Cryo Plant Prepare for shutdown ’04 –beam tube –Contract hole cutting Negotiating with DF to help target work.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
DCal-ALICE integration and installation plan and status A. Tauro.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Update on PANDA solenoid design
MICE Partial Return Yoke Mechanical Design
Step IV PRY Preparation - Contents
MICE CM31 Schedule summary
SNS PPU Cryomodule Space Frame
Presentation transcript:

MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006

2 My Profile Recently joined project… …..But picking it up quickly! Professional Mechanical Engineer in CCLRC Technology –20 years RAL Worked in all major Engineering areas; –ISIS :MARI spectrometer, experience of beamline design –Space Science :Thermal & Structural Analysis, Project management Particle physics : ATLAS Detector, Project Management, procurement of high stability CF cylindrical structure

3 Contents My responsibilities Current hall tasks: Stairs/shield/platform Trench strengthening Imminent hall tasks: Wall holes Magnetic modelling Fire Safety Approval Decay Solenoid transport Central Drawing database Conclusions

4 Responsibilities My MICE job Responsible for Hall Infrastructure –Mechanical/Civil work + Associated underlying work e.g. Magnetic analysis –Health & Safety e.g. Fire Safety Approval –Provision of Services – water, electric, ventilation Responsible for Setting up and monitoring central drawing database at RAL Part of Target engineering team (design & test) Technical Board Secretary

5 Current Hall tasks 1) Modifying (Linac side) stairs to reduce width –Drgs out for pricing 2) Re-Engineering (control room side) stairs/shield/platform –New set design drgs – awaiting magnetic performance confirmation

6 Current Hall tasks Linac side stairs –Drgs out

7 Current Hall tasks Shield Wall (Currently 25mm steel/100mm gap/25mm steel) Awaiting magnetic confirmation

8 Current Hall tasks Trench strengthening –Drgs being prepared –Non-magnetic Al used (supports + covers) near tracker along to access covers. –Decision to strengthen whole trench since layout still subject to change About to tackle: –Wall holes for cables to MICE LCR –Wall holes for hydrogen area ventilation –Ceiling holes for emergency H2 ventilation

9 Magnetic Modelling New magnetic model produced –More user-friendly, Easier to quickly iterate if reqd. –Need to prove shield designs will be effective –Requirements –Shield ISIS control room –Reduce to safe personnel levels (pacemakers) Currently making predictions

10 Magnetic Modelling cont.

11 Magnetic Modelling cont.

12 Magnetic Modelling cont.

13 Fire safety Fire safety: Discussions started towards getting approval. –Fire exits defined, checking correct door types –Access routes being checked (minimum width, hazards)

14 Fire safety 2 Gap between magnets to be used as emergency access route – signs Small/hidden areas of hall to be fenced off Trench – blocked off with access cover and fixed steel ladder

15 Decay Solenoid transport Current situation: Solenoid on PSI trolley (~14.6 tonnes)

16 Decay Solenoid transport Solenoid assy in R55 & very unmanagable Need to test solenoid in MICE hall Need to work on trolley (wheels etc.) –Temporary Transport frame designed and almost ready to go out for manufacture. –Mass < 10 tonnes incl lifting frame –Can therefore be moved within MICE hall with a tandem lift (15 tonnes SWL)

17 Decay Solenoid :Temporary transport frame

18 Decay Solenoid: Disassembly and transport In-situ disassembly and transport procedure 1) Tighten centralising cold-mass supports x6 2) Grind off tack welds, remove end supports 3) Lead shielding assy off nose 4) Fit yellow cradles 5) Fit orange beams 6) Connect blue lifting beam 7) Unbolt feet (keep shims) 8) Lift onto green frame, bolt down re-using shims 9) Refit lead shield onto nose 10) Refit modified end supports (bolt holes) 11) lift onto transport trailer 12) Take to MICE Hall

19 Drawing database –Initial discussions started, established some parameters –Need to maintain central database of RAL (local to experiment) –Vital to maintain latest set of drawings (drawing control) –Need for Read access by institutes e.g. Oxford group, Imperial, etc. –Proprietary database e.g Intralink probably not suitable –I’m likely to use FTP site

20 Conclusions Mechanical/Civil items moving forward - Need to maintain momentum A good scheme for disassembly/transport of decay solenoid Early steps towards a Central drawing database