RSRDC UNIT- II, AJMER
ORGANISATION CHART OF RSRDC UNIT-II, AJMER Sh.--------- RE Sh. --------- Accountant Sh. -------- ARE P.K.Arora Vacant (Addl. Charge to Sh. Sunil jain ARE Sh. Lokesh Gupte Sh. Lalit Sharma 3. Sh. Ashish Sharma 4. Sh. Harsh Rai
Financial Work Load in Unit Rs. In Lacs S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – I Sh. Lokesh Gupta 1 Construction of ROB with approaches (Excluding railway portion) on Dholpur-Rajakhera road Km-3 on SH-2 PWD 1000.00 579.43 420.57 2 Construction of ROB with approaches at LC No. 472 (1305/6-8 Mania-Marena road) Jhansi-Agra Section. 0.03 999.97 ARE – II Sh. Lalit Sharma Construction of 2 lane ROB with approaches (excluding Railway portion) at MDR 37-A on Nagour-Basni Road in lieu of LC No. 63-C (On NH-89) 1300.00 ARE – II 600.00 191.45 408.55 ARE - IV 700.00 197.41 502.59
ARE – III Sh. Ashish Sharma 1 S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – III Sh. Ashish Sharma 1 Construction of ROB & approaches on Bhilwara -Chittorgarh BG Track at Bhilwara. (UIT Work) UIT Bhilwara 2086.00 1327.31 + 385.00 (Rly.) 373.69 ARE – IV Sh. Harsh Rai Construction of ROB & approaches on Phalodi-Mandal-Bhilwara road in lieu of LC No. 63-C PWD 1000.00 870.32 129.68 2 Construction of ROB on Manglana - Makrana road in lieu of LC No. 36 Kuchaman city Makrana section SH-2B 305.16 694.84 ARE – V Sh. Brijesh Mathur of Unit-I,Ajmer Construction of ROB in Km. 70 of Kishangarh -Roopangarh road SH-07 in lieu of LC No. 28 NWR. 843.67 156.33 Construction of ROB (excluding Railway portion) and approaches on Ajmer-Beawer road in lieu of LC No. 5A/2E 783.28 216.72
Regional Pollution Control Board office, Bhilwara Important Works Completed during last 5 years Regional Pollution Control Board office, Bhilwara Completion Cost – Rs. 23.97 lacs
Construction of ROB at Kishangarh, Ajmer Total Cost : Rs. 10.00 Crores Location : Kishangarh, Ajmer Date of Start : 18.03.2007 Stipulated Date of Completion : 17.01.2008 Expenditure till Date : Rs. 843.96 Lacs Likely Completion date : 30.6.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.
Construction of ROB at Saradhna, Ajmer Total Cost : Rs. 10.00 Crores Location : Beawar road, Ajmer Date of Start : 17.07.2007 Stipulated Date of Completion : 16.06.2008 Expenditure till Date : Rs. 783.56 Lacs Likely Completion date : 31.12.2010 (Depends on Railway work) Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work Status of railway work : Lay out & shifting of cable work in progress.
Construction of ROB at Bhilwara(UIT Work) Total Cost : Rs. 20.86 Crores Location : Bhilwara Date of Start : 18.03.2007 Stipulated Date of Completion : 17.11.2007 Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.) Likely Completion date : 31.05.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Super structure work in progress.
Construction of ROB at Mandal (Bhilwara) Total Cost : Rs. 10.00 Crores Location : Mandal, Bhilwara Date of Start : 19.07.2007 Stipulated Date of Completion : 18.06.2008 Expenditure till Date : Rs. 870.46 Lacs Likely Completion date : 30.06.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work in progress.
Construction of ROB at Makrana Distt. - Nagour) Total Cost : Rs. 10.00 Crores Location : Makrana, (Distt.-Nagour) Date of Start : 23.08.2008 Stipulated Date of Completion : 22.07.2009 Expenditure till Date : Rs. 390.67 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : Shifting of electric lines & encroachments. Status of railway work : Work order placed. Work yet not started.
Construction of ROB at Nagour Total Cost : Rs. 13.00 Crores Location : Nagour Date of Start : 21.08.2008 Stipulated Date of Completion : 20.07.2009 Expenditure till Date : Rs. 405.45 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Dholpur Total Cost : Rs. 10.00 Crores Location : Dholpur Date of Start : 17.11.2007 Stipulated Date of Completion : 16.10.2008 Expenditure till Date : Rs. 609.36 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Mania-Marena Road Total Cost : Rs. 10.00 Crores Location : Mania, Dholpur Date of Start : - Stipulated Date of Completion : - Expenditure till Date : Rs. 0.03 lacs. Likely Completion date : Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’
Proposed New Works S. No. Name of Work Client Deptt. Mode Estimated Cost 1 Construction of Academic block at MLV Textile & Engineering College, Bhilwara MLVT, Bhilwara Actual plus Rs. 350.00 lacs 2 Construction of Urban Co Operative bank at Shastri Nagar Bhilwara BUCB Bhilwara Rs. 50.00 Lacs