Wildlife Considerations in Financing Wind Power Albuquerque, New Mexico July 2007 Penny Jennings Eckert, Ph.D.

Slides:



Advertisements
Similar presentations
Laws & Regulations pertaining to Endangered Species in Wisconsin.
Advertisements

1 Wind Energy Services Environmental Permitting for Wind Energy Facilities Anntonette Alberti, JD Tetra Tech, Inc.
The three most important considerations for development of wind farms are: LAND with good to excellent wind resource CONTRACT to sell electricity produced.
Endangered Species Conservation Banking
Chris Dandurand, P.Eng Kiewit Infrastructure Group Large Hydro Perspective on the Permitting Process & Environmental Approvals.
Environmental Scoping Guidance Jerry Vogt Region Environmental Coordinator ODOT – Region 3.
National Environmental Policy Act of Establishes protection of the environment as a national priority Mandates that environmental impacts be considered.
Environmental Compliance Negotiating our way through the process…
WETLAND REGULATORY PROGRAM Role of the U.S. Fish and Wildlife Service.
Major Federal & State Approvals Environmental Business Council of New England Land-Based Wind Energy May 29, 2008 Ruth H. Silman, Esq.
John F. Corbett, III Bio.335-Wildlife and Fisheries Biology Keystone College January 21, 2010.
Proposed Amendments for Terrestrial Wind Regulation in the New Jersey Coastal Zone Kevin Hassell Coastal Management Office NJDEP.
Wind Energy Development Wildlife Issues and Concerns Wind and Prairie Task Force February 27, 2004 Edward A. Martinko State Biologist and Director Kansas.
Wind Power in Western North Carolina Potential Avian Impacts Source: avian.php.
Legal Issues Affecting Wind Energy Federal Nexus: Public Lands. On public land, Federal funding, Federal permit, Federal power grid. On public land, Federal.
What is an In Lieu Fee Program ? Clean Water Act - Section 404 : “no overall net loss” of wetland acreage and functions. One mechanism for providing Compensatory.
Clean Water Act Section 404: An O&G Perspective Andrew D. Smith SWCA Environmental Consultants.
Environmental Consultants BMI Environmental Services, LLC AN OVERVIEW OF THE WETLANDS REGULATORY PROCESS AS IT RELATES TO THE PROPOSED OCEAN SPRINGS HIGH.
Natural Resource Reviews Threatened or Endangered Species Natural AreasWetlands.
Northeast Corridor Greenway Acquisition – Mitigation Feasibility Study Results City Council Workshop June 24, 2014.
1 Wetland Regulatory Programs Department of Natural Resources Legislative Audit Bureau July 2007.
Clean Water Act Section 404 Basics Clean Water Act Section 404  Regulates discharges of dredged or fill material into waters of the U.S., including.
US Army Corps of Engineers BUILDING STRONG ® Coordinating U.S. Army Corps of Engineers Regulatory Permits with Species Conservation Plans November 16,
GIS Study of the Kelsey-Whisky Logging Plan Jared Chapiewsky Matthew Bloch U of Wisconsin, Madison.
Endangered Species Act
WETLANDS and ODOT Environmental Services Oregon Department of Transportation.
Biological Reviews JOELLE L. GEHRING, Ph.D. Federal Communications Commission.
Assessing Project Related Impacts to Migratory Birds.
WETLANDS and LOCAL PROGRAMS Environmental Services Oregon Department of Transportation.
Our mission ead and execute environmental programs and provide expertise that enables Army training, operations, acquisition and sustainable military communities.
HABITAT CONSERVATION PLANNING Charles J. Randel, 1 III, Howard O. Clark, Jr., 2 Darren P. Newman, 2 and Thomas P. Dixon 3 1 Randel Wildlife Consulting,
West Texas Legislative Summit ENVIRONMENTAL ISSUES Environmental Regulations Affecting Transportation Carlos Swonke Director, Environmental Affairs Division.
BUILDING STRONG ® 1 Regional General Permit (RGP) 31 Interagency Meeting June 11, 2015.
Marine Corps Air Station Miramar
Wind Energy Developed and presented by Ed Shoener To Wilkes University FYF 101J 19 November 2007.
Implementing Conservation Measures to Reduce Impacts to Migratory Birds.
East Link Extension Migratory Bird Treaty Act Compliance.
ENVIRONMENTAL OPPORTUNITIES AND CONSTRAINTS ARCHAEOLOGICAL - HISTORICAL INVESTIGATIONS PERMITTING FOR UNAVOIDABLE ENVIRONMENTAL IMPACT AREA ENDANGERED.
Photos by Peter LaTourrette and PRBO The California Avian Data Center (CADC) User Survey: Results and Trends The CADC Development Team, PRBO July 30, 2008.
Number of Copies Agency Submissions & Comments. Coordination ESRs are reviewed by OES and coordinated with resource agencies as part of the NEPA review.
U.S. Army Corps of Engineers Decision Authority l All permit decisions, scope of analysis, 404(b)(1), mitigation, alternatives, jurisdiction -- Corps.
Transmission Siting Considerations, Best Practices, and Lessons Learned Gary Graham, Ph.D. Transmission Project Director.
Wetlands and Waterways Permits Ken Franklin Statewide Permits Program Coordinator Geo-Environmental, ODOT.
Recreational Trails Program Federal Requirements.
1 Implementing the Concepts Environment Pre-Conference Workshop TRB MPOs Present and Future Conference August 27, 2006 Michael Culp FHWA Office of Project.
ODFW Habitat Mitigation Policy and Energy Facility Siting.
Defenders of Wildlife Species we are helping to protect.
GREEN INFRASTRUCTURE FUNCTIONAL MASTER PLAN Prince George’s County MNCPP-C Draft: December, 2004.
SAFETEA-LU: Environmental Provisions for Transportation Planning Michael Culp FHWA Office of Project Development and Environmental Review
Environmental Commitments/Tracking. Environmental Commitments Federal Agencies Shall –Use all practicable means consistent with the requirements of.
Emerging T&E Issues L. Peter Boice Conservation Team Leader 23 March 2003.
California Department of Fish and Wildlife’s Role in Timber Harvest Review.
Guide to Permitting Electric Transmission Lines in Wyoming Wyoming Renewable Energy Coordination Committee Presented to Western Governors Association October,
FCC’s NEPA Process Overview of NEPA Overview of NEPA Overview of FCC’s NEPA rules and procedures Overview of FCC’s NEPA rules and procedures Nuts and bolts.
Environmental Issues Update - Endangered Species 1.
NAVFAC PACIFIC March st North American Wildlife and Natural Resources Conference National Military Fish and Wildlife Association Marine Conservation.
Overview of Everything You Need to Know About Mitigation.
Barriers and Challenges to Developing Renewable Energy Projects
Non-government Environmental Organization
Range Management in the Face of Climate Change
2017 EBA Annual Meeting & Conference
Endangered Species Conservation Banking
Michigan Dept. of Environmental Quality Water Resources Division
DG Environment, Nature Protection Unit (D3)
Endangered Species.
Environment Safeguards
The National Environmental Policy Act (NEPA)
Environmental Reports
NATURAL RESOURCE ISSUES
Presentation transcript:

Wildlife Considerations in Financing Wind Power Albuquerque, New Mexico July 2007 Penny Jennings Eckert, Ph.D.

Tetra Tech Experience Actively permitting projects in any state the wind is blowing! Many permitting and engineering projects in the West (including California), the Midwest, and the East (including New York). Also active in project construction (EPC)

Why Wildlife Issues at all? Collisions with turbines kill birds and bats Collisions with transmission lines kill birds Collision numbers vary geographically Wildlife may avoid windfarms, further reducing habitat available Installation of wind turbines and access roads can reduce or divide habitat Regulating agencies worry

Putting Avian Mortality in Perspective With Other Causes

But the agencies still worry!

Birds, Bats, and Bankers: Important questions:  Is permitting this project feasible?  How long will permitting take?  How much will permitting cost?  What role do wildlife issues play in permitting feasibility?  Will there be wildlife problems during operations?

It Depends!

Depends on….  Is there a Federal nexus?  What are the State permitting rules?  Who else is watching (stakeholder groups)?  Who’s in the neighborhood (resident wildlife)?  Who passes through and when (migratory birds and bats)?

Common Sources of Federal Nexus Federally managed land? (BLM, National Forest, Military, Indian Reservation) Substantial wetland or waterbody impact, either with project or with access and transmission? If yes then Army Corps of Engineers permit required. Cross an Interstate with a transmission line? If yes then FHWA involvement

Federal Nexus Brings…. NEPA compliance Consultation with USFWS on threatened and endangered species USFWS active in protection of eagles and migratory birds, involved in NEPA USFWS recommends THREE years of avian surveys prior to permitting Section 7 consultation on T&E has a timeline of around 6 months

State Permitting Varies drastically from state to state Federal-like rules in many states (e.g. CA, NY) NO state permitting in some states (e.g. TX) Intermediate permitting structures in most other states

State Permitting Brings…. Quasi-NEPA compliance Involvement of state wildlife agencies Often USFWS-like pre-permitting survey requirements If serious concerns for T&E species, may require a Section 10 consultation with USFWS, which has no set timeline and can take 1-2 years to issue a “take” permit

Stakeholder involvement brings… More attention to –preconstruction surveys – analysis –Mitigation Longer public involvement, possibly decision drag in agencies

Who’s in the neighborhood, and who’s passing through?

Wildlife Studies Site-specific baseline studies + geographically similar case histories = predicted impacts Impacts vary by location, location, and location

Wildlife Studies Pre-construction/siting –Initial “fatal flaw” analysis –Preconstruction surveys During Construction –Compliance, micrositing, habitat avoidance Post-construction –Fatality monitoring –Displacement studies

Wildlife Baseline Studies Preconstruction Surveys –Avian use surveys—resident, migrant—at least 1 year –Raptor nesting surveys –Habitat inventory and mapping –Bat habitat inventory and/or risk analysis –State Natural Heritage database/USFWS T&E species inquiries Studies vary by state and geographic setting

Additional Baseline Studies Radar study of night migrants Focused T&E species surveys where necessary USFWS requests a MINIMUM of two full years of avian studies prior to permitting (USFWS 2003)

Ideally…. Preconstruction Surveys Permit Permit Conditions, including mitigation Construction!

Impact Mitigation Avoidance Minimization Compensation

Avoidance Site turbines, roads, or transmission lines “somewhere else” Setbacks Have biologist on site to assist with micrositing Do not construct while animals are present Operational limitations (last resort)

Minimization Reduce footprint Reduce need for very wide roads by assembling cranes near installation site Reduce working hours during critical periods

Compensation Expenditures on studies sometimes count –Post-construction mortality studies –Pre- and Post-construction habitat use and species presence/success studies Contribution to other programs involved in habitat restoration Conduct onsite restoration Purchase of mitigation bank credits, where available Purchase of offsite habitat for preservation Management of offsite habitat “in perpetuity”

Conclusions Cost and schedule impact of wildlife studies varies by federal nexus presence, state rules, geography Studies are conducted to determine risk Risk can be mitigated (at a price) USFWS and state wildlife agencies generally continue to work with wind proponents in non-enforcement roles

Questions?