9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Chapter 7 Project Management
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Developing the Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Developing a Project Plan
Chapter 9 Project Scheduling: PERT/CPM
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Developing a Project Plan
8-1 Scheduling Scheduling Defined Gantt Charts Network Techniques: PERT and CPM Determining Task Durations Probability and Simulation Some Examples.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 University of Wales Bachelor of Science (Industrial Engineering and Management) Year 3 Copyright © 2012 MDIS. All rights reserved.Section
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
ELC 347 project management
Project Development Scheduling and Probability of Completion.
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Scheduling: Networks, Duration estimation, and Critical Path
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall8-1 Cost Estimation and Budgeting.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –Part 4 Due –Part 5 Due Nov 24 (page 342) –Any of the first five sections can be resubmitted.
Project Management MGT 30725
Project Management -- Developing the Project Plan
Project Scheduling KULIAH 10 Magister Sistem Informasi
Project Planning & Scheduling
Project Scheduling KULIAH 10 Magister Manajemen
Time Planning and Control Activity on Node Network (AON)
Project Planning & Scheduling
Chapter 6: Project Time Management
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
PROJECT SCOPE, SCHEDULE, AND RESOURCE MANAGEMENT
Time Planning and Control Precedence Diagram
ENM448-Project Planning and Management
Project Scheduling: Lagging, Crashing and Activity Networks
Time Planning and Control Activity on Node Network (AON)
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Slides Prepared by JOHN LOUCKS
Project Time Management
Presentation transcript:

9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education

9-2 Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities E D C B A F Merge activities Burst activities Node Path Critical Path

9-3 Network Diagrams Show interdependence Facilitate communication Help schedule resources Identify critical activities Determine project completion Show start & finish dates

9-4 AOA Vs. AON The same mini-project is shown with activities on arc… C E D B F E C D B F …and activities on node.

9-5 Node Labels Early Start Activity Float Activity Descriptor Late Start ID Number Activity Duration Late Finish Early Finish

9-6 Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution –Most likely (m) –Most pessimistic (b) –Most optimistic (a)

9-7 TaskPredecessorabc Z YZ XZ WY, X VW1413 TW61014 ST, V Sketch the network described in the table. 2.Determine the expected duration and variance of each activity.

9-8 Constructing the Critical Path Forward pass – an additive move through the network from start to finish Backward pass – a subtractive move through the network from finish to start Critical path – the longest path from end to end which determines the shortest project length

9-9 Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) –ES + Duration = EF –EF of predecessor = ES of successor –Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) –LF – Duration = LS –LS of successor = LF of predecessor –Smallest succeeding LS at a burst point becomes LF for predecessor

9-10 TaskPredecessorTime A--4 BA9 CA11 DB5 EB3 FC7 GD, F3 HE, G2 KH1 1.Sketch the network described in the table. 2.Determine the ES, LS, EF, LF, and slack of each activity

9-11 Laddering Activities Project ABC can be completed more efficiently if subtasks are used A(3)B(6)C(9) ABC=18 days Laddered ABC=12 days A 1 (1)A 2 (1)A 3 (1) B 1 (2)B 2 (2)B 3 (2) C 1 (3)C 2 (3)C 3 (3)

9-12 Hammock Activities Used as summaries for subsets of activities 0 A B C Hammock Useful with a complex project or one that has a shared budget

9-13 Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten –early tasks –longest tasks –easiest tasks –tasks that cost the least to speed up