Project Scheduling: Networks, Duration estimation, and Critical Path
Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities E D C B A F
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-3 Project Scheduling Terms E D C B A F Merge activities Burst activities Node Path Critical Path
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-4 Network Diagrams Show interdependence Facilitate communication Help schedule resources Identify critical activities Determine project completion Show start & finish dates
AOA vs. AON The same mini-project is shown with activities on arrow… C E D B F E C D B F …and activities on node.
Node Labels Early Start Activity Float Activity Descriptor Late Start ID Number Activity Duration Late Finish Early Finish
Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution –Most likely (m) –Most pessimistic (b) –Most optimistic (a)
TaskPredecessoramb A BA CA DB, C ED1413 FD61014 GF, E Sketch the network described in the table. 2.Determine the expected duration and variance of each activity.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-9 Constructing the Critical Path Forward pass – an additive move through the network from start to finish Backward pass – a subtractive move through the network from finish to start Critical path – the longest path from end to end which determines the shortest project length
Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) –ES + Duration = EF –EF of predecessor = ES of successor –Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) –LF – Duration = LS –LS of successor = LF of predecessor –Smallest succeeding LS at a burst point becomes LF for predecessor
TaskPredecessorTime A--4 BA9 CA11 DB5 EB3 FC7 GD, F3 HE, G2 KH1 1.Sketch the network described in the table. 2.Determine the ES, LS, EF, LF, and slack of each activity
Laddering Activities Project ABC can be completed more efficiently if subtasks are used A(3)B(6)C(9) ABC=18 days Laddered ABC=12 days A 1 (1)A 2 (1)A 3 (1) B 1 (2)B 2 (2)B 3 (2) C 1 (3)C 2 (3)C 3 (3)
Hammock Activities Used as summaries for subsets of activities 0 A B C Hammock Useful with a complex project or one that has a shared budget
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-14 Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten –early tasks –longest tasks –easiest tasks –tasks that cost the least to speed up
Chapter 10 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-15
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Lags in Precedence Relationships The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks 1.Finish to Start 2.Finish to Finish 3.Start to Start 4.Start to Finish
Finish to Start Lag Most common type of sequencing Shown on the line joining the modes –Added during forward pass –Subtracted during backward pass 0 A 6 Spec Design 6 6 B 11 Design Check 5 15 C 22 Blueprinting 7 Lag 4 This lag is not the same as activity slack
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Finish to Finish Lag Two activities share a similar completion point –The mechanical inspection cannot happen until wiring, plumbing, and HVAC installation are complete 10 B 16 Plumbing 6 16 C 24 HVAC 5 24 D 25 Inspection 1 15 A 21 Wiring 6 Lag 3
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Start to Start Lag Logic must be maintained by both forward and backward pass 31 B 32 Plumbing 1 33 C 36 HVAC 5 36 D 37 Inspection 1 30 A 36 Wiring 6 Lag 3
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Start to Finish Lag Least common type of lag relationship Successor’s finish dependent on predecessor’s start 22 B 28 Plumbing 6 28 C 33 HVAC 5 33 D 34 Inspection 1 30 A 36 Wiring 6 Lag 3
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Gantt Charts Establish a time-phased network Can be used as a tracking tool Benefits of Gantt charts 1.Easy to create and comprehend 2.Identify the schedule baseline network 3.Allow for updating and control 4.Identify resource needs
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Create a Gantt chart based on the activities listed in the table. TaskTimePred A8-- B5A C8A D4B,CB,C E5D
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Crashing The process of accelerating a project Principal methods for crashing Improving existing resources’ productivity Changing work methods Increasing the quantity of resources
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Managerial Considerations Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path Cease crashing when –the target completion time is reached –the crashing cost exceeds the penalty cost
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall What is the lowest cost to complete this project in 52 weeks? Times are in weeks and costs in dollars. Plot the AON & AOA networks and the GANTT chart. ActivityPredNormal Time Min Time Normal Cost Crash Cost A BA CA DB, C ED FD GE, F HG
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Activity on Arrow Networks Activities represented by arrows Widely used in construction Event nodes easy to flag Forward and backward pass logic similar to AON Two activities may not begin and end at common nodes Dummy activities may be required
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Use AOA to sketch the network that represents the project as described in the table. 2.Calculate early and late event times for all activities. ActivityTimePredActivityTimePred A4--F15E B2AG4E C10AH7D,F,G D3BI11H E15B,C
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Activity on Arrow Network AH F D E C B I G
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Controversies in the Use of Networks Networks can be too complex Poor network construction creates problems Networks may be used inappropriately When employing subcontractors –The master network must be available to them –All sub-networks must use common methods Positive bias exists in PERT networks