2. Phase: 2. Phase: PLAN THE PROJECT What? How? Work Breakdown Structure Estimation of resources Definition of dependencies between project activities Development of PERT diagram Assignment of responsibilities
Work Breakdown Structure (WBS) Project - Hierarchical system (tree): Goal Objectives Workpackages... Tasks Decomposition „upside- down“
Task S.M.A.R.T. Criterion: Specific Measurable (costs, work, time) Assignable (responsibility) Realistic Time-related
TASK DESCRIPTION Task ID, title, description Input (outcomes of other tasks) Title, type, description of a deliverable Start and end time Effort (e.g. in person-months) Costs Responsibility
Example: Conference planning 1.Conference programme 1.1 Define programme of conference 1.2 Obtain speakers 1.3 Prepare conference materials Obtain presentations from speakers Prepare and print conference materials
Example: Conference planning (2) 2.Set the conference site & date 2.1 Set the conference date 2.2 Select & commit conference site 2.3 Confirm arrangements
Example: Conference planning (3) 3. Develop marketing plan 3.1 Develop and print conference brochure 3.2 Obtain Label Sets for Direct mailing 3.3 Mail brochures 3.4 Receive & acknowledge registrations
Duration of a Task Task duration = Effort / No of persons Random character Average time of activity duration: TA = (O + 4.M + P) / 6 O - optimistic completion time P - pesimistic M – most likely completion time
COSTS CATEGORIES Personnel costs Equipment Travel and subsistence Consumables Other direct costs Subcontracting Indirect Costs (overheads)
SEQUENCING THE PROJECT ACTIVITIES Logical / time dependencies Types of dependencies: Finish Start („Immediate predecessor“) Finish Finish Start Start Start Finish
ActivityTitleImm. Pred. A (2.1)Date- B (1.1)Programme- C (2.2)SiteA D (1.2)SpeakersB E (3.1)Conf.broch.C, D F (3.2)Database C, D Example: Conference planning
ActivityPlaceImm.Pred. G (3.3)MailingE, F H (1.3.1)ObtainD I (3.4)ProcessG J (2.3)FinishH, I K (1.3.2)PrintJ Example: Conference planning(2) Example: Conference planning (2)
PERT DIAGRAM (Project Evaluation & Review Technique) PERT DIAGRAM (Project Evaluation & Review Technique) NODE: ID - activity identifier ES - earliest possible start EF - earliest possible finish LS -latest possible start LF -latest possible finish AD - activity duration TS - time slack
NODE PERT
Example: Conference Planning A BD end KJ H IG F EC start
USE OF PERT Locating the Critical Path (CP) Earliest possible time of finishing the project Determination of paralelly executable tasks View from „bird perspective”
CRITICAL PATH Critical path: The longest path in PERT Delay of activity delay on critical path prolongation of the project duration
CALCULATION OF THE CRITICAL PATH ES k = max {EF i, i all imm. predecessors of the node k} EF k = ES k + AD k LF k = min {LS i, i all nodes for which the node k is a predecessor} LS k = LF k - AD k Activities on CP have zero Time slack
Example: Conference Planning 02 A C E F G I H D B K J start end
APPLICATION OF PERT APPLICATION OF PERT Planning – activity scheduling, assigment team members to tasks Implementation – realocation of resources Control – Comparision of plan and current status quo
Project Proposal Problem definition, Aim of the project, approach taken, expected benefits Detailed description of project activities (Workplan) - dates, resources, deliverables,... Budget, management structure,... Depends on the type of the project
PURPOSE OF THE PROJECT PROPOSAL Detailed project description (Request for Grant) Dynamic tool for project manager for decision making Reference document for project control Becoming familiar with the project
TEAM ASSIGNMENT 2 Develop a Project Proposal for the „ACRU Continuind Education“ Project addressing the following items: WBS with brief description of each activity PERT diagram Budget
2nd Phase: 2nd Phase: PROJECT PLAN Summary Work break down structure (Tasks - S.M.A.R.T.) Estimation of time and costs (duration, effort, costs) Sequencing of activities PERT diagram Determination of the critical path Project Proposal