Project Management Introduces Pert/CPM as a tool for planning, scheduling, and controlling projects Applied Management Science for Decision Making, 2e.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Finding the Critical Path
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Chapter 13 Project Scheduling: PERT/CPM
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
PROJECT MANAGEMENT. Outline What is a “project”? Project Management Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time.
Project Scheduling Basic Approach. projectA project is a collection of tasks that must be completed in minimum time or at minimal cost. activitiesIt is.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Project Scheduling Basic Approach. projectA project is a collection of tasks that must be completed in minimum time or at minimal cost. activitiesIt is.
MGMT 483 Week 8 Scheduling.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Management Chapter 13
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Management Techniques.
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Operations Management Project Management
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT /
3 - 1© 2011 Pearson Education 3 3 Managing Projects PowerPoint presentation to accompany Heizer and Render Operations Management, 10e, Global Edition Principles.
1 Project Management Seminar Project Scheduling. 2 Importance of Project Management Three Components of Project Management Project Evaluation and Review.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management (專案管理)
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
To accompany Quantitative Analysis for Management, 7e by Render/Stair 13-1 © 2000 by Prentice Hall, Inc., Upper Saddle River, N.J Quantitative Analysis.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
Welcome to MM305 Unit 7 Seminar Dr. Bob Project Management.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Welcome to MM305 Unit 7 Seminar Dr. Bill Wood Project Management.
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Project Planning & Scheduling
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Project Scheduling Network Optimization can be used as an aid in the scheduling of large complex projects that consist of many activities A project is.
Project Planning and Budgeting
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Project Time Management
Project Time Management
General Foundry Example of PERT/CPM
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Project Time Management
Project Time Management
Presentation transcript:

Project Management Introduces Pert/CPM as a tool for planning, scheduling, and controlling projects Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions Philip A. Vaccaro, PhD MGMT E-5050

Project Management Overview History and ImportanceHistory and Importance The Two Pert / CPM ConventionsThe Two Pert / CPM Conventions Pert / CPM Building BlocksPert / CPM Building Blocks ES, EF, LS, LF, and SES, EF, LS, LF, and S Task Times Task Times Probabilistic PERTProbabilistic PERT

Project Examples  New Product Development & Manufacture  New Product Promotion Campaign  Broadway Shows  Television Programs  Corporate Restructure  Software Conversion  Weapons System  Skyscraper  Bridges & Highways Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions

 Lost revenues and profits  Contract penalties  Loss of clientele  Higher costs due to overruns  Reputation damage  Resource waste Missed Deadline Consequences

Project Prerequisites  Tasks with clear start/finish points  Tasks with alternate execution sequences  Tasks with several possible time estimates  Tasks that run parallel to each other THESE PREREQUISITES STRENGTHEN MANAGEMENT ACCOUNTABILITY AND PROVIDE FLEXIBILITY IN THE FACE OF FUNDING CHANGES, STAFFING, & TECHNICAL PROBLEMS

Project Prerequisites  Tasks with clear start/finish points Laying the foundation of a new home starts when the excavation crew and equipment arrive on the site and ends when the foundation has been poured. Framing starts when the carpenters arrive on site and ends when the frame has been built.

Project Prerequisites  Tasks with alternate execution sequences Tasks that can be reordered might result in overall shorter overall execution times and less cost.

Project Prerequisites  Tasks with several possible time estimates Identifying best case, worst case, and most likely time estimates for each project task allows us to better adopt to changes in funding, deadlines, and unforeseen technical problems. Flexibility

Project Prerequisites  Tasks that run parallel to each other It is vital that several tasks be scheduled at the same time, so that, if one of them is in danger of falling behind, the others will stand ready to assist with extra funds, personnel, equipment, and other resources. This will, in turn, save the entire project from falling behind schedule!

PERT / CPM History  The Critical Path Method (CPM) was developed in 1957 by J.E. Kelly of Remington Rand and M.R. Walker of DuPont.  Originally, CPM was used to assist in building chemical plants, reducing completion time from 7 to 4 years. CPM requires only one time estimate for each project task

PERT / CPM History  Program Evaluation and Review Technique was developed in 1958 by the United States Navy Special Projects Office.  Originally used to plan and control the Polaris submarine program, reducing completion time from 7 to 4 years !  In 1960, PERT and CPM were combined, hence the term PERT/CPM. PERT requires 3 time estimates for each project task

U.S. Navy Special Projects Office Grace Murray Hopper  Ph.D, Yale University, 1934  Professor, Vassar College,  Developed the COBOL programming language and the compiler  Worked on the Mark I & II computers at Harvard University  Developed international standards for computer languages  Lecturer, consultant, engineer, operations researcher  Received 47 honorary degrees  Naval reservist  First women admiral, U.S. Navy (1984) Famous Staff Member

Grace Murray Hopper Anecdote While she was working on the Mark II computer at Harvard University, her associates discovered a moth stuck on a relay, thereby impeding operation. Whereupon she remarked that they were “debugging” the system. The remains of the moth can be found at the Smithsonian Museum of American History in Washington, D.C.

PERT / CPM PERT / CPM The Two Conventions Activity-on-Node Activity-on-Arc TASKS ARE SHOWN AS ARROWS ( ARCS ) NODES REPRESENT TASK START AND FINISH Activity-on-Node TASKS ARE SHOWN AS SQUARES ( NODES ) ARROWS REPRESENT TASK PREDECESSOR RELATIONSHIPS

Activity-on-Node Convention  The network is cleaner and uncluttered  It is natural to view nodes as tasks  It is easier to use than the activity-on-arc convention  U.S. Government switched over to the AON convention in 2001 ADVANTAGES

Activity-on-Node Building Blocks  Nodes represent the tasks/activities  Small nodes represent the start and finish of the project  Arcs/arrows show the predecessor relationships among the tasks start 1 st Task 2 nd Task 3 rd Task end Here, the 2 nd task cannot begin until the 1 st task has been completed. The 3 rd task cannot begin until the 2 nd task has been completed.

GENERAL FOUNDRY INC. GENERAL FOUNDRY INC. PROJECT TASKS TASK A TASK A – Build Internal Component TASK B TASK B – Modify Roof and Floor TASK C TASK C – Construct Collection Stack TASK D TASK D – Pour Concrete TASK E TASK E – Build Burner TASK F TASK F – Install Control System TASK G TASK G – Install Pollution Device TASK H TASK H – Inspect & Test EXAMPLE

General Foundry Inc. THE PERT/CPM NETWORK STARTFINISH A B C D E F G H TIME in WEEKS Time can be expressed in days, weeks, or months

Task Interpretation EXAMPLE 2 A ES = 0EF = 2 TASK “A” EXPECTED DURATION TIME IS 2 WEEKS EARLIEST TIME TASK “A” CAN START IS AT THE END OF WEEK “0” THAT IS, THE START OF WEEK “1” EARLIEST TIME TASK “A” CAN FINISH IS AT THE END OF WEEK “2” THAT IS, THE START OF WEEK “3”

Expected Task or Activity Time te = [ 1a + 4m + 1b ] 6 optimistic time estimate most likely time estimate pessimistic time estimate 67% Weights Sum of the Weights A WEIGHTED AVERAGE TIME FORMULA 17% Expected times are usually used for each task in the project

Expected Task or Activity Time GIVEN: a = 1 week, b = 3 weeks, m = 2 weeks [ 1a + 4m + 1b ] [ 1(1) + 4(2) + 1(3) ] = te = 2 weeks 6 == OPTIMISTIC TIME PESSIMISTIC TIME MOST LIKELY TIME EXAMPLE

The BETA Distribution ( a skewed distribution) m tete a b Optimistic time Most likely time (mode) Pessimistic time Expected time TASK TIME IS NOT ASSUMED TO BE NORMALLY DISTRIBUTED The probability distribution commonly used to describe the inherent variability in task time estimates

The BETA DISTRIBUTION  Symmetrical, right, or left-skewed based on the nature of a particular task  Unimodal with a high concentration of probability surrounding the most likely time estimate (m)  No strong empirical reason for using the BETA distribution  Attractive however, because the mean (μ) and the variance ( ) can be easily obtained from the three time estimates “a”, “m”, and “b” CHARACTERISTICS & COMMENTS

The Critical Path ( CP )  The chain of tasks from project start to end that consumes the longest amount of time.  Any delay in one or more of those tasks will delay the entire project.  The critical path is equal to the project’s expected or mean completion time. start AB C end DE

Critical Path Characteristics Several critical paths may exist within the project network at any given time. These critical paths may change or disappear entirely at any given time as the project progresses Management must monitor all critical paths closely.

General Foundry Inc. THE NETWORK STARTFINISH A B C D E F G H TIME in WEEKS

General Foundry Inc. 1st Critical Path Candidate STARTFINISH A B C D E F G H A-C-F-H Nine (9) Weeks

General Foundry Inc. 2nd Critical Path Candidate STARTFINISH A B C D E F G H A-C-E-G-H Fifteen (15) weeks

General Foundry Inc. 3rd Critical Path Candidate STARTFINISH A B C D E F G H B-D-G-H Fourteen (14) weeks

The Critical Path A-C-F-H9 weeks A-C-E-G-H15 weeks B-D-G-H14 weeks The expected, mean, or average project completion time is 15 weeks

General Foundry Inc. THE CRITICAL PATH STARTFINISH A B C D E F G H Fifteen (15) Weeks

E EE Expected, Mean, or Average Project Completion Time μ Here, 15 Weeks 50% CHANCE OF COMPLETION BEFORE μ (15 weeks) 50% CHANCE OF COMPLETION AFTER μ (15 weeks) THE CRITICAL PATH EQUALS MEAN PROJECT COMPLETION TIME

EARLY START TIME ( ES ) The technique is called FORWARD PASS  The earliest time that each task can begin.  Computed from left to right, that is, from the network’s begin- ning node to the net- work’s finish node.

EARLY START TIME FORMULA PREDECESSOR TASK ES PREDECESSOR TASK te FOLLOWER TASK ES =+ IF THERE ARE SEVERAL CANDIDATES FOR THE FOLLOWER TASK ES, THE LONGEST ES IS SELECTED THE VERY FIRST TASK IN A PROJECT HAS AN EARLY START TIME OF ZERO As we progress through the project, follower tasks will eventually become predecessor tasks themselves !

General Foundry Inc. EARLY START TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES = 0 ES = 2 ES = 3 ES = 4 ES = 8 ES = 13

EARLY START TIME SELECTED CALCULATIONS PREDECESSOR TASK ES A ( 0 ) PREDECESSOR TASK te A ( 2 ) FOLLOWER TASK ES C ( 2 ) =+ IF THERE ARE SEVERAL CANDIDATES FOR THE FOLLOWER TASK ES, THE LONGEST ES IS SELECTED THE VERY FIRST TASK IN A PROJECT HAS AN EARLY START TIME OF ZERO

General Foundry Inc. EARLY START TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES = 0 ES = 2 ES = 3 ES = 4 ES = 8 ES = 13

EARLY START TIME SELECTED CALCULATIONS PREDECESSOR TASK ES B ( 0 ) PREDECESSOR TASK te B ( 3 ) FOLLOWER TASK ES D ( 3 ) =+ IF THERE ARE SEVERAL CANDIDATES FOR THE FOLLOWER TASK ES, THE LONGEST ES IS SELECTED THE VERY FIRST TASK IN A PROJECT HAS AN EARLY START TIME OF ZERO

General Foundry Inc. EARLY START TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES = 0 ES = 2 ES = 3 ES = 4 ES = 8 ES = 13

ES Candidate Selection 4 E 4 D G 5 ES=4 ES=3 ES=8 COMING IN FROM TASK “E” EARLY START TIME FOR TASK “G” WOULD BE “8” ( = 8 ) COMING IN FROM TASK “D” EARLY START TIME FOR TASK “G” WOULD BE “7” ( = 7 ) THEHIGHER EARLY START CONTROLS

General Foundry Inc. EARLY START TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES = 0 ES = 2 ES = 3 ES = 4 ES = 8 ES = 13

ES Candidate Selection 3 F 5 G H 2 ES=4 ES=8 ES=13 COMING IN FROM TASK “F” EARLY START TIME FOR TASK “H” WOULD BE “7” ( = 7 ) COMING IN FROM TASK “G” EARLY START TIME FOR TASK “H” WOULD BE “13” ( = 13 ) THEHIGHER EARLY START CONTROLS

EARLY FINISH TIME ( EF ) This technique is also called FORWARD PASS The earliest time that each task can finish. Computed from left to right, that is, from the network’s beginning node to the network’s finish node.

EARLY FINISH TIME FORMULA TASK EARLY START TIME ES TASK EXPECTED TIME te TASK EARLY FINISH TIME EF =+ NEEDLESS TO SAY, EARLY FINISH TIMES CANNOT BE COMPUTED UNTIL EARLY START TIMES ARE IDENTIFIED

General Foundry Inc. EARLY FINISH TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES=0EF=2 ES=0EF=3 ES=2EF=4 ES=3EF=7 ES=4EF=7 ES=4EF=8 ES= 8 EF=13 ES=13EF=15

EARLY FINISH TIME SELECTED CALCULATIONS TASK EARLY START TIME ES = 0 A TASK EXPECTED TIME te = 2 A TASK EARLY FINISH TIME EF = 2 A =+ NEEDLESS TO SAY, EARLY FINISH TIMES CANNOT BE COMPUTED UNTIL EARLY START TIMES ARE IDENTIFIED

General Foundry Inc. EARLY FINISH TIMES STARTFINISH A B C D E F G H TIME in WEEKS ES=0EF=2 ES=0EF=3 ES=2EF=4 ES=3EF=7 ES=4EF=7 ES=4EF=8 ES= 8 EF=13 ES=13EF=15

EARLY FINISH TIME SELECTED CALCULATIONS TASK EARLY START TIME ES = 2 C TASK EXPECTED TIME te = 2 C TASK EARLY FINISH TIME EF = 4 C =+ NEEDLESS TO SAY, EARLY FINISH TIMES CANNOT BE COMPUTED UNTIL EARLY START TIMES ARE IDENTIFIED

General Foundry Inc. EARLY FINISH TIMES STARTFINISH A B C D E F G H TIME in WEEKS EF=2 EF=3 EF=4 EF=7 EF=7 EF=8 EF=13 EF=15

LATE FINISH TIME ( LF ) This technique is called BACKWARD PASS The latest time that each task can finish without jeopardizing the project’s expected completion time. Computed from right to left, that is, from the network’s finish node to the network’s start node.

LATE FINISH TIME FORMULA FOLLOWER TASK LATE FINISH TIME (LF) FOLLOWER TASK EXPECTED TIME (te) PREDECESSOR TASK LATE FINISH TIME (LF) = - IF THERE ARE SEVERAL CANDIDATES FOR THE PREDECESSOR TASK LF, SELECT THE SHORTEST LF

General Foundry Inc. LATE FINISH TIMES STARTFINISH A B C D E F G H TIME in WEEKS LF = 2 LF = 4 LF = 8 LF = 13 LF = 8 LF = 13 LF = 15

LATE FINISH TIME SELECTED CALCULATIONS FOLLOWER TASK LATE FINISH TIME (LF = 15) H FOLLOWER TASK EXPECTED TIME (te = 2) H PREDECESSOR TASK LATE FINISH TIME (LF = 13) F = - IF THERE ARE SEVERAL CANDIDATES FOR THE PREDECESSOR TASK LF, SELECT THE SHORTEST LF

General Foundry Inc. LATE FINISH TIMES STARTFINISH A B C D E F G H TIME in WEEKS LF = 2 LF = 4 LF = 8 LF = 13 LF = 8 LF = 13 LF = 15

LF Candidate Selection 2 C 4 E F 3 LF=4 LF=8 LF=13 COMING IN FROM TASK “F”. THE LATE FINISH TIME FOR TASK “C” IS “10” (13-3=10) COMING IN FROM TASK “E”, THE LATE FINISH TIME FOR TASK “C” IS “4” (8-4=4) THE SMALLER LATE FINISH TIMECONTROLS

LATE START TIME ( LS ) This technique is also called BACKWARD PASS  The latest possible time that each task can start without jeopardizing the project’s expected completion time.  Computed from right to left, that is, from the network’s finish node to the network’s start node.

LATE START TIME FORMULA TASK LATE FINISH TIME (LF) TASK EXPECTED TIME (te) TASK LATE START TIME (LS) = - NEEDLESS TO SAY, TASK LATE START TIMES CANNOT BE COMPUTED UNTIL TASK LATE FINISH TIMES ARE IDENTIFIED

General Foundry Inc. LATE START TIMES STARTFINISH A B C D E F G H TIME in WEEKS LS=0LF=2 LS=1LF=4 LS=2LF=4 LS=4LF=8 LS=10LF=13 LS=4LF=8 LS= 8 LF=13 LS=13LF=15

LATE START TIME SELECTED CALCULATIONS TASK LATE FINISH TIME (LF = 15) H TASK EXPECTED TIME (te = 2) H TASK LATE START TIME (LS = 13) H = - NEEDLESS TO SAY, TASK LATE START TIMES CANNOT BE COMPUTED UNTIL TASK LATE FINISH TIMES ARE IDENTIFIED

General Foundry Inc. LATE START TIMES STARTFINISH A B C D E F G H TIME in WEEKS LS=0LF=2 LS=1LF=4 LS=2LF=4 LS=4LF=8 LS=10LF=13 LS=4LF=8 LS= 8 LF=13 LS=13LF=15

LATE START TIME LATE START TIME SELECTED CALCULATIONS TASK LATE FINISH TIME (LF = 4) B TASK EXPECTED TIME (te = 3) B TASK LATE START TIME (LS = 1) B = - NEEDLESS TO SAY, TASK LATE START TIMES CANNOT BE COMPUTED UNTIL TASK LATE FINISH TIMES ARE IDENTIFIED

General Foundry Inc. LATE START TIMES STARTFINISH A B C D E F G H TIME in WEEKS LS=0 LS=1 LS=2 LS=4 LS=10 LS=4 LS=8 LS=13

SLACK TIME ( S )  The time each task may be postponed without jeopardizing the project’s expected completion time. The chain of zero slack tasks in the network will also identify the critical path. ALSO KNOWN AS PRIMARY SLACK

SLACK TIME FORMULAE TWO VERSIONS S = Task LS – Task ES S = Task LF – Task EF

General Foundry Inc. ALL SLACK TIME CALCULATIONS STARTFINISH A B C D E F G H ES=0 EF=3 LS=1 LF=4 S=1 S=1 ES=2 EF=4 LS=2 LF=4 S=0 S=0 ES=3 EF=7 LS=4 LF=8 S=1 S=1 ES= 4 EF= 7 LS=10 LF=13 S=6 S=6 ES=4 EF=8 LS=4 LF=8 S=0 S=0 ES=8 EF=13 LS=8 LF=13 S=0 S=0 ES=13 EF=15 LS=13 LF=15 S=0 S=0 ES = 0 EF = 2 LS = 0 LF = 2 S = 0

General Foundry Inc. PRIMARY SLACK TIMES FOR ALL TASKS STARTFINISH A B C D E F G H TIME in WEEKS S=0 S=1 S=0 S=1 S=6 S=0 S=0 S=0

General Foundry Inc. CRITICAL PATH VIA ZERO SLACK TIME TASKS STARTFINISH A B C D E F G H A-C-E-G-H S=0 S=1 S=0 S=1 S=6 S=0 S=0 S=0

Probabilistic PERT 1.Critical path time ( CP or μ ) 2. CP tasks’ optimistic times ( a ) 3. CP tasks’ pessimistic times ( b ) 4. CP tasks’ time variances ( ) REQUIRES 4 STATISTICS Generates probabilities for completing a project before and after its expected completion date.

Task Time Variance Formula OF THE BETA DISTRIBUTION 2 where: a = optimistic time b = pessimistic time 6 = constant ( k ) MUCH EASIER FORMULA THAN THE ONE FOR THE NORMAL PROBABILITY DISTRIBUTION ! = b - a 6

EXAMPLE EXAMPLE ALL NEW - VARIANCES FABRICATED  Assume the critical path is days ( CP = μ )  Assume the tasks along the critical path are: C,D,E,F,H,K  Assume that the critical path task time variances ( σ ) in days are: C =.11 C =.11 D =.11 D =.11 E =.44 E =.44 F = 1.78 F = 1.78 H = 1.00 H = 1.00 K = 1.78 K =

Requirements I.What are the chances of finishing the project in 30 days or less? In other words, P ( t =< 30 ) = ? II.What are the chances of finishing the project in 40 days or less? In other words, P ( t =< 40 ) = ?

Solution Project Variance = ∑ CP Task Variances ( σ ) days = Project 5.22 Std Dev = √5.22 = 2.28 days ( σ ) 2

Solution μ = days σ = 2.28 days X = 30 days Project completion time is normally distributed. Therefore, a normal curve can be drawn with a μ and σ. Z = X – μ = – = Z = X – μ = – = σ 2.28 σ 2.28 The no. of standard deviates between the mean ( μ ) and the value of interest ( X ) Z The percentage of the normal curve covered to a point that is “2.78” standard deviates to the left of the mean = % z

Solution  Therefore, the probability of finishing the project in 30 days or less is: = P( t =< 30 ) ≈ 0%  Conversely, the probability of finishing the project in more than 30 days is: P( t > 30 ) ≈ 100%

Solution μ = days σ = 2.28 days X = 40 days Project completion time is normally distributed. Therefore, a normal curve can be drawn with a μ and σ. Z = X – μ = – = Z = X – μ = – = σ 2.28 σ 2.28 The no. of standard deviates between the mean (μ) and the value of interest (X) Z The percentage of the normal curve covered to a point that is “1.61” standard deviates to the right of the mean = % Z

Solution  Therefore, the probability of finishing the project in 40 days or less is: P( t=<40 ) ≈ 95%  Conversely, the probability of finishing the project in more than 40 days is:.0537 P( t>40 ) ≈ 5%

PERT / CPM with QM for WINDOWS

We scroll to PROJECT MANAGEMENT ( PERT / CPM ) Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions

We have only one time estimate for each task in this project We select the SINGLE TIME ESTIMATE program

There are 8 tasks in the project “Precedence List” is another term for Activity-on-Node Convention The tasks are labeled A, B, C, D, etc.

The Data Input Table  “Prec” is an abbreviation for “Predecessor Task”.  Here, the program provides for listing as many as 7 predecessor tasks for each task.

Project Estimated Completion Time ( Critical Path ) Zero Slack Time Tasks Are Highlighted In Red

The 2 nd Solution Is “CHARTS” Four Different Charts Can Be Brought Up By Clicking Their Titles Early Start Early Finish Late Start Late Finish Critical Path Tasks

Here, the program displays a precedence relationship diagram based on what we entered in the “predecessor” columns The Critical Path Tasks Are Shown In Red

Template and Sample Data

Template and Sample Data

Project Management