ATN 2001, London - 18 Sep 01 1 PETAL II and II Extension Maastricht Multi-stack Implementation Lessons Learnt Prepared by Gustaaf Janssens/Konrad Koebe.

Slides:



Advertisements
Similar presentations
ATN-2000 AOC Migration Strategy Presented by Frank OConnor.
Advertisements

© 2010 The MITRE Corporation. All rights reserved. AERONAUTICAL COMMUNICATIONS PANEL (ACP) THIRTEENTH MEETING OF THE WORKING GROUP I Bangkok, Thailand.
Overview of the interoperability Regulation
Air / Ground Communications in Europe
1 C ENTRE D'ETUDES DE LA NAVIGATION AERIENNE PHARE Aeronautical Telecommunication Network: PATN By Gérard Mittaux-Biron PATN Project Leader CENA.
The EMERALD RTD Plan and the ASAS Validation Framework R P (Bill) Booth 10 October 2002.
ATN99 International ConferencePage September 1999 London ATN99 INTERNATIONAL CONFERENCE September 1999 London Paul Hennig, United Airlines.
ATN 99 Service Technique de la Navigation Aérienne 1 ATN Activities & Plans ATN in FRANCE FOR SAFETY REASONS MAIN FUTURE DATA/LINK ATSC WILL BE ATN.
Rob Mead PETAL-II Trials Manager Eurocontrol, DIS/ATD
ACI/GM/3011/1.0 ACI's Portable ATN Software Products & Services Technology for next-generation aviation data communication… Presented by Forrest Colliver.
The Future of PETAL Technology
PETAL A major step Towards Cooperative Air Traffic Services Patrice BEHIER Manager of the Air/ground Co operative ATS Programme Directorate Infrastructure,
Page 1STNApresentation of data-link activities DATA-LINK IMPLEMENTATION IN FRANCE Initial data-link services with ACARS - Departure Clearance, ATIS - CPDLC.
VHF Digital Link Mode 2 Deployment Strategy Vic Nagowski
International Civil Aviation Organization Aviation System Block Upgrades Module N° B0-86/PIA-3 Improved Access to Optimum Flight Levels through Climb/Descent.
Workshop on preparations for ANConf/12 − ASBU methodology
ATN ‘99, London, 23 September 1999 David Russell ATS Market Manager, SITA AIRCOM SITA AIRCOM Data Link Service.
Data-link Elements and Role of Stakeholders – Reflections of an ANSP
Air-Ground Data Link - DFS Strategy
B1 Backwards Compatibility CSG October 2012, Long Beach, CA, USA F. Picard, EGIS AVIA.
International Civil Aviation Organization Aviation System Block Upgrades Module N° B0-40/PIA-4 Improved Safety and Efficiency through the initial application.
FAA Presentation to CAR/SAM ATN/GNSS Seminar, Varadero, Cuba, May 2002 Current Status of FAA Controller-Pilot Data Link Communication (CPDLC) - Build 1,
18-19 September 2001ATN2001 (London)1 A Commitment to ATN Implementing Aeronautical Data Link Today Presented by Kevin Wohlers ACI Program Manager.
24 Sept '02Page 1 FANS-1/A Accommodation in an ATN Environment.
Integrated information and telecommunications solutions AIRCOM Implementation VHF Digital Link Presented by Philip Clinch to ATN 2001 Conference 19 September.
FAA Controller Pilot Data Link Communications Program ATN ‘99 London, England James H. Williams September 22, 1999.
The ATN Avionics Vendors View. ATN2001 Sept 2001; p.2 PETAL-II Avionics.
ATN/VDL Mode 2 Implementation Status
ATN 2001, London - 18 Sep 01 1 PETAL II Extension Architecture, Integration and Testing Prepared by Martin Adnams/Isabelle Herail.
International Civil Aviation Organization Aviation System Block Upgrades Module N° B0-25/PIA-2 Increased Interoperability, Efficiency and Capacity through.
How the PETAL Trial Relates to the FAA’s CPLDC Program ATN 2001 Focus on the Reality of Data Link IEE London, England 18 September 2001 Gregg Anderson.
ATN Subnetwork Implementation:
ARINC PETAL IIe VDL Mode 2, ATN …and beyond
Next Generation Air/Ground Communications (NEXCOM) Presented to ATN 2002 London, England 25 September 2002 James H. Williams Communications Integrated.
ATN 2002, London - 24 Sep 02 1 OPERATIONAL DATA LINK AT MAASTRICHT UAC P2L PETAL TO LINK Gustaaf Janssens Maastricht UAC Project Manager P2L.
EEC-ATI (V2) 1 ATN2002 CONFERENCE LINK2000+ ATN2002 CONFERENCE LINK2000+ LINK2000+ European ATS Provider Benefits Real-time Simulation Results ATN2002.
IPv6 integration with the ATN Tony Whyman Helios Information Services Ltd.
Data Link Communications
FANS-1/A and ATN Data Link: An Avionics Perspective Bob Kerr
CRISTAL ITP European Organisation for the Safety of Air Navigation CRISTAL ITP ASAS-TN, Paris Johan Martensson CASCADE CRISTAL ITPJohan Martensson ASAS-TN.
Episode 3 EP3 WP6 - Excom - December 15th, Brussels 1 WP6 - Technology EP3 Final Report Technology results December 2009.
NORTH ATLANTIC ADS WAYPOINT REPORTING TRIALS. John Coulson NATS Infrastructure Services.
OOI CI LCA REVIEW August 2010 Ocean Observatories Initiative OOI Cyberinfrastructure Architecture Overview Michael Meisinger Life Cycle Architecture Review.
Rob Mead PETAL-II Trials & Project Manager Eurocontrol, DIS/ATD
Presented by Philip Clinch on 27 September 2000 at ATN 2000 Aeronautical Telecommunications Services.
Direction générale de l’Aviation civile centre d’Études de la navigation aérienne First ASAS thematic network workshop The user’s expectations and concerns.
CARE/ASAS Activity 2 Follow-up: Validation Framework Dissemination Forum Isdefe Ingeniería de Sistemas CARE/ASAS ACTIVITY 2 FOLLOW-UP: VALIDATION.
Malmö 5 September. 27 th 2005 NUP ITP TT Reykjavik “NUP -- ITP”
Federal Aviation Administration Data Communications Program FAA Prototype & Validation Activities Presented to:Data Comm Implementation Team By:Craig Morris.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
4 th Workshop, Amsterdam, 23 rd -25 th April 2007 ASAS-SEP Applications Airborne Implementation Overall Architectural Considerations.
Page 1 July 28, 2003 Richmond Facility ATN 2003 IEE London Raytheon Integrated Data Link–RIDL
Service Enhancement AMHS Implementation Workshop Chennai, India 15 th – 17 th December 2008.
LINK EEC Test Facility - ATN 2003 London 1 LINK Test Facility Overview Located at EEC Bretigny - France In support to LINK EATMP project.
Workshop on preparations for ANConf/12 − ASBU methodology
Workshop on preparations for ANConf/12 − ASBU methodology
Presented by Thales Avionics ATN 2003 London, UK September 2003
Workshop on preparations for ANConf/12 − ASBU methodology
ATN London - 23 September 2003 Alex Wandels
The Air Ground Datalink Server (AGDS)
6th May 2002 Current Status of FAA Controller-Pilot Data Link Communication (CPDLC) - Build 1, 1A, and Beyond M J A Asbury Presentation ATN3.3 The development.
Ground System implication for ASAS implementation
Presented at ICAO ACP WG-I By Robin Hughes
15-19 Nov 2010 Rockville, MD – Lockheed Martin
Workshop on preparations for ANConf/12 − ASBU methodology
ICAO WGN New Orleans Nov 2004
DATA LINK IMPLEMENTATION IN EUROPE
ATN Subnetwork Implementation:
FAA Data Communications Program System Engineering
ICAO ACP WG-N meeting Use of IP in ARTAS
Presentation transcript:

ATN 2001, London - 18 Sep 01 1 PETAL II and II Extension Maastricht Multi-stack Implementation Lessons Learnt Prepared by Gustaaf Janssens/Konrad Koebe Maastricht UAC

ATN 2001, London - 18 Sep 01 2 TOPICS n What Do We Mean by Multi-Stack? n Why Multi-Stack ? n What Are Multi-Stack Design Considerations ? n MUAC Ground Architecture n MUAC Schedule Achievements n How Do We Test ? n What Are Our Lessons Learnt ? n Next Steps n Conclusions

ATN 2001, London - 18 Sep 01 3 What Do We Mean by Multi-Stack ? n Accommodating Existing Specifications for AGDL uNEAN Extension (Prototype VDL4) uFANS-1/A uATN SARPs n Aim uCommunicate With Any Avionics Equipment Using One Of The Specifications

ATN 2001, London - 18 Sep 01 4 Why Multi-Stack ? n PETAL-II Project Needs for MUAC uOperations - Hide AGDL Technology for User F Operational Requirements Validation Independent From AGDL Technology uQuick Implementation F Project Has to Compete With Daily Life Activities at an Operational Centre uTake Advantage of Existing Operational Avionics Equipment uEncourage ATN SARPs based Air and Ground Implementations

ATN 2001, London - 18 Sep 01 5 Design Constraints (1) n Fit In MUAC Existing Ground Structure uHMI, FDPS, Gateways F Add Functionality in HMI and FDPS, Add AGDL Gateway uHMI F Add to Normal Controller Presentation and Interface uFDPS F Based on ATN SARPs Ground End User Applications Definitions u AGDL Gateway F Single Access Point for FDPS F Access Points for Underlying AGDL Technologies

ATN 2001, London - 18 Sep 01 6 Design Constraints (2) n Evolutionary Development uNext Step Building on Results of Predecessor

ATN 2001, London - 18 Sep 01 7 Maastricht Multi-stack GROUND End System (1) Controller HMI Controller HMI Controller HMI Controller HMI Flight Data Processing System ATM Services NEAN GWY NEAN 9705 BER P2GW (PETAL 2 GATEWAY) FANS-1/A GWY SITA ProATN ES 9705 PER VDL2-ATN ProATN ROUTER

ATN 2001, London - 18 Sep 01 8 Maastricht Multi-stack GROUND End System (2) Controller HMI Controller HMI Controller HMI Controller HMI Flight Data Processing System - Flight plan / address association - ATN SARPs (ICAO 9705) CM, ADS, CPDLC - All datalink service logic and dialogue control P2FEP NFEP - Aircraft address/state - ASE emulation CM, CPDLC, ADS - Conv. to NEAN specs. FAFEP - Aircraft address/state - ASE emulation CM, CPDLC, ADS - Conv. To FANS specs ALLA- P2PI - Aircraft address/state - BER-PER Conversion. ProATN - ASEs: CM, CPDLC, ADS - ATN Router FANS-1/A Gateway NEAN Server 9705 BER 9705 PER P2GW

ATN 2001, London - 18 Sep 01 9 Design Constraints (3) n P2GW uHolds and Manages Addressing Data uBuffers FDPS from Unexpected communications uMADAP Msg= { Msg ID, Infra ID+24bits+FID+Reg.Mark+9705-BER-Msg} uHides Communication and Network Specifics from FDPS

ATN 2001, London - 18 Sep Design Constraints (4) n AGDL Applications implemented u CM, ADS, CPDLC n FDPS AGDL Services Using these Applications uCM: DLIC Acceptance uADS: ADS demand (FLIPCY), ADS periodic (CAP) uCPDLC: (ACL, ACM, AMC) n FDPS Functionality Used for AGDL u Manages Flight plan Operational Status F DLIC acceptance and ADS, CPDLC requests F Terminates CPDLC, ADS

ATN 2001, London - 18 Sep Design Constraints (5) uController Authorisation F Only Controlling Sector handles CPDLC  FDP Controls Sequence Extraction  Next internal or external sector (NDA) identities  Controls Automatic Flight Plan Action F CMContact at OLDI ABI event  CPDLC (NDA) at OLDI ACT event  Extracts Information for Controller HMI  radar picture and tabular display uProvides Authorised Input Sequences and Guidance on Controller HMI

ATN 2001, London - 18 Sep 01 12

ATN 2001, London - 18 Sep MUAC Schedule Achievements (1) n NEAN IN 4/98 n FANS 1/A 2/99 n P2GW - BAC1/11 using ATIF/SATCOM, P-II message set. 5/00 n MC-P2GW-BAC1/11 Flight using ATIF/SATCOM, P-IIe message set. 9/00 n Application Testing: FDPS-Avionics11/00 n FDPS, P2GW Ready 3/01

ATN 2001, London - 18 Sep MUAC Schedule Achievements (2) n FANS1/A ONLINE: P-IIe Message set 4/01 n NEAN OUT 4/01 n CERTification Testing Support 5/01 n Non Revenue Flights 6/01 n MUAC-RUAC Shadow Flight 7/01 n Revenue Flight 8/01

ATN 2001, London - 18 Sep MUAC Technical Achievements (1) n ICAO 9705 Compliant FDPS Implementation n Usage of ATN, FANS1/A and Prototype VDL4 n First Fully Certified ATN avionics n CPDLC Flights May1998-June2001 = 8455 (FANS/NEAN) n Test Infrastructure n Test Methodology

ATN 2001, London - 18 Sep How Do We Test (1) ? n Test Approach uLocal Tests F HMI, FDPS, P2GW uEnd-to-End Application Tests: F FDPS- Other ATC Centre - Avionics grounded avionics airborne avionics F Operational Observation n Overview of Our Test Configurations

ATN 2001, London - 18 Sep P2GW EMUL FAME AGDG-FANS FDPS EMUL AFAME PSF AGDG ATN NON REV

ATN 2001, London - 18 Sep PIIe Operational Observation VDL M2 B767 P2GW MAASTRICHT UAC Control Centre PROATN R PROATN End System FDPS LAN CPDLC Services VIA ATN/VDL Mode 2

ATN 2001, London - 18 Sep What Are Our Lessons Learnt (1) ? n Step by Step Implementation uNEAN F Validation of Technical Concept and Architecture uFANS 1/A F Validation of ‘Multi Stack’ Concept HMI, FDPS Independent From AGDL Technology uATN SARPs F Validation of SARPs Compliant Implementation F Additional Operational Messages and Stack Functions uLessons F More Testing Effort due to Regression Testing ?

ATN 2001, London - 18 Sep What Are Our Lessons Learnt (2) ? n ATN SARPs Implementation Tests u Early Feedback = Early Application Error Detection and Correction F BAC1-11 Test Flights F ATIF-ground Testing F End-to-End Application testing uNo Application Errors Detected During CERT, Non- Revenue and Revenue Flights

ATN 2001, London - 18 Sep What Are Our Lessons Learnt (3) ? n Local Tests as Much as Possible u Avionics Emulators uTest Automation u Protocol Test facilities n External Testing is Expensive uTest Setup uTest Execution uTime Consuming n Good Test Objectives and Strategies

ATN 2001, London - 18 Sep What Are Our Lessons Learnt (4) ? n Future Requirements for Test Tools and Strategies uReference Test Tools Required F Available For All Implementers F Common Development F A lot of Tools exist. Usable to further develop ? uReference Test Objectives and Strategies n Separate Test Network Required uConnect Test Systems uIntra Centre Test uAvionics Tests

ATN 2001, London - 18 Sep Next Steps (1) n Complete PETAL-IIe uSystem Safety Assessment uDocument Lessons Learned uConsolidate Documentation uEvaluate Test Automation (GEODE) n New Project (P2L = PETAL To LINK2000+) (in approval and initiation phase)

ATN 2001, London - 18 Sep Next Steps (2) n P2L Objectives uMaintain a State of the Art Implementation of the Existing AGDL Implementation. uEnsure Safety of all Operational Systems uIncrease the Number of aircraft applying AGDL Services (FANS, ATN) uSupport the LINK Project F Enabler for aircraft to equip. F Enabler for other Centres F Enabler for COMS F Enabler for Test and Validation tools - Common Development and Support.

ATN 2001, London - 18 Sep CONCLUSION n MULTI STACK CONCEPT WORKS ! n SERVE MORE AIRCRAFT n CONNECT TO NEIGHBOUR ATC CENTRES THANK YOU PARTNERS FOR THE COOPERATION !