F INANCIAL R ISK M ANAGEMENT A FFECTING B UILDING P ROJECTS IN WB, C ONTRACTOR ’ S P ERSPECTIVE Prepared by: Alaa Al-Araj Ahmad Freehat Hazza’a Ammori.

Slides:



Advertisements
Similar presentations
Public Private Partnership Investment and Construction Armando R. Araujo Cairo 2003.
Advertisements

Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.
Cash Flow Sewon Kim Kevin Tran Mary. Index Introduction Clients cash flow Contractors cash flow Cash flow forecasting Improving cash flow Example References.
NEC - Engineering and Construction Contract (ECC)
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Construction Cost Estimating Class #2: Bidding Process Prof. Ralph V. Locurcio, PE.
Financial Management F OR A S MALL B USINESS. FINANCIAL MANAGEMENT 2 Welcome 1. Agenda 2. Ground Rules 3. Introductions.
4/13/2017 1:54 PM.
Bootstrapping and Financing the closely held company
J. K. Dietrich - FBE Fall, 2005 Interest Rates: Basic Determinants Week 5 – September 28, 2005.
Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. Statement of Cash Flows Revisited 21.
VII-Financing of Constructed Facilities The Financing Problem Institutional Arrangement for Facility Financing Avaluation of Alternative Financing Plans.
Module five: Session Two M5S21. Training objective To review the various financing options available to road contractors M5S22.
Lesson 8. 1.Estimate the amount of debt needed to achieve the firm’s goals. 2.Understanding the balance sheet and operating statements. 3.Make the needed.
3.1 Sources of Finance Chapter 18 Part 1.
UNIT 4 – TEST REVIEW PLANNING FOR YOUR FUTURE SAVINGS AND INVESTING
Obtaining Surety Credit An Introduction to the Surety Process for Contractors and Subcontractors.
Surety Bonds The Sensible Choice For Managing Risk.
Syed M. Ahmed, Ph.D. Department of Construction Management Risk Management in Construction Syed M. Ahmed, Ph.D. Department of Construction Management Florida.
Chapter 2 Project Financing Dr. Nabil I El Sawalhi Associate Professor of Construction Management AEPM 21.
Cash flow planning Unit 8.
 Buying on credit = buy goods and services now and pay for them later (usually with interest)  Having credit depends on the suppliers’ confidence in.
Surety Bonds 101 The Basics of Bonding. Surety Bonds Vs. Traditional Insurance Surety BondsInsurance 3-party2-party Risk transfer Duty to obligeeDuty.
Introduction Time Quality Cost Project Constraints Success Introduction.
IB Business and Management
Construction Contracts and Project Delivery Methods
Copyright 2001 November 2001 Venture 2002 – introduction to the financial planning model.
Joint Venture in construction company in West Bank.
Delay In Construction Project In West Bank. Outline:  Background.  Research objective & methods.  Important factors that cause time and cost overrun.
IB Business and Management
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Specification & Quantities Estimating
Financial Analysis Ag Management Chapter 3. Objectives Know the three kinds of financial analysis Be able to calculate liquidity, solvency, and equity.
1 18 International Payments and Related Issues. Summary: 18.1 Payment Currency Clauses Mobilization and Progress Payments Insurance Issues.
CONSTRUCTION CONTRACTS DOCUEMENTS
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Cash Flow Analysis Part 2 King Saud UniversityCE511- Construction Planning & Control 1.
* WHAT’S FINANCE? The Role of Finance and Financial Managers * LG1
Project Cash Flow.  In order to make a workable project plan, the resources needed for the project and their availability must be checked.  Money is.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
International Business 9e By Charles W.L. Hill McGraw-Hill/Irwin Copyright © 2013 by The McGraw-Hill Companies, Inc. All rights reserved.
T HE I NTERPRETATION OF FINANCIAL STATEMENTS Profitability, liquidity, efficiency, gearing ratios.
RISK MANAGEMENT YULVI. Introduction Time Quality Cost Project Constraints Success Introduction.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
Measurement and Payment
TOPIC-7- PROJECT CASH FLOW
Final Accounts. Accounts Submissions Last Bill for Contracted Works ( excluding Retention) Presented at Practical Completion Practical Definition dependant.
Army Directorate of Public Works Support Contractor of the Year Building a government contractor for the 21 st century By Carlos Garcia Owner and CEO KIRA.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Unit 3.5 Final Accounts. Financial Statements ▫Profit and Loss account ▫Balance sheet ▫Cash Flow statement Financial Accounting Management Accounting.
Topic 3: Finance and Accounts
Marcumllp.com CASH FLOW AND THE RELATED BUSINESS IMPACTS marcumllp.com Presented by: Greg Alford, CPA.
Construction Tender Process Tender steps between Client, Contractor and Subcontractor Dr A Kimmance.
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
((Organizing relationship between the Owner and Contractor involved in construction project at Palestine)) By: Maw`ed Abu Shamleh Malaak Hamaydi Supervisor:
Causes of Contractors’ Failure “ North West Bank” Graduation Project
Costs and Economics of Construction
An-Najah National University
Under supervision of: Eng. Reema Nassar
TOPIC-7- PROJECT CASH FLOW
TOPIC-7- PROJECT CASH FLOW
An - Najah national university Civil engineering department
ARCH 435 PROJECT MANAGEMENT
Supervisor: Eng. Mohammad abu neama
Factors Affecting Bid/No Bid Decision Making IN The West Bank
CHAPTER TWO: CASH FLOW CALCULATIONS
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

F INANCIAL R ISK M ANAGEMENT A FFECTING B UILDING P ROJECTS IN WB, C ONTRACTOR ’ S P ERSPECTIVE Prepared by: Alaa Al-Araj Ahmad Freehat Hazza’a Ammori Supervised by: Eng. Reema Bdair

R ESEARCH M ETHODOLOGY 1. Problem definition, Research aim and Research objectives 2. Theoretical Background & Literature Review 3. Determination of R-Strategy 4. Questionnaire building and sample size determination. 5. Questionnaire analysis 6. Recommendations.

M ETHODOLOGY – R ESEARCH S TRATEGY Research strategies are usually divided into two main types: 1- Quantitative research 2- Qualitative research This research mixes both of them but depends mainly on conducting questionnaire survey.

Q UESTIONNAIRE F INAL F ORM It consists of two parts : The first one asks about general questions related to the company and the questionnaire filler. ( 6 Questions ) The second one measures the degree of severity and controllability of 24 widespread and well- known financial risk factors.

Q UESTIONNAIRE A NALYSIS

The severest ten main factors in term of the degree of severity were: 1. Bankruptcy of the owner or financier. 2. Delays in payments: 3. Contractor's debts before the start of the project (Existing debt). 4. Monopolization of materials and equipment as a result of Israeli closures and unforeseen political conditions. 5. Foreign currency fluctuation and Exchange rate fluctuation. 6. Error in the previous estimate for the project and its related costs account (Unsound pre-estimation of the project cost.) 7. Inflation 8. Labor strikes 9. Contractor's bankruptcy 10. Inadequate terms and conditions in tender documents.

Q UESTIONNAIRE A NALYSIS The top ten factors in terms of the degree of being out of control where: 1. Monopolizing of materials due to closure and other unexpected political conditions. 2. Bankruptcy of the funder or the owner 3. Take-up of shares 4. Financial failure of the contractor (insufficient funding/ Contractor’s bankruptcy) 5. Foreign currency fluctuation and Exchange rate fluctuation 6. Inflation 7. Source of loan 8. delay in payments 9. labor strikes 10. Delay in the first payment.

Risky FactorSeverityControllability 1 Delay in Payments Very SevereModerate 2 Delay in the first payment specially Moderatecontrollable 3 Foreign currency fluctuation and Exchange rate fluctuation severe Moderate 4 InflationsevereModerate 5 Inadequate terms and conditions in tender documents.severecontrollable 6 Having to break up partnerships between companies, in a project or both Moderate controllable 7 Labor strikesseverecontrollable 8 Unsound pre-estimation of the project cost.severecontrollable 9 Financial failure of the contractor (insufficient funding/ Contractor’s bankruptcy)severeModerate 10 Bankruptcy of the funder or the owner Very severe Moderate 11 Lack of financial liquidity management during the projectsevere controllable 12 Monopolizing of materials due to closure and other unexpected political conditions. Very severe Moderate 13 Fraudseverecontrollable 14 Performance bond requirementsModeratecontrollable 15 Interest Type (Fixed, Floating, or capped)Moderatecontrollable 16 Changes in interest rateModeratecontrollable 17 Availability of loanModeratecontrollable 18 Loan periodModeratecontrollable 19 Source of loanModerate 20 Existing debtVery severecontrollable 21 InsuranceModeratecontrollable 22 Taxes severe controllable 23 Time and amounts of dividend payments Moderate controllable 24 Take-up of shares MildModerate

R ECOMMENDATIONS 1- Bankruptcy of the financier or the owner: 1. If the contractor feels that the case here will occur, he shall try to get a bank guarantee which ensures that the owner or the funder has the ability to pay. 2. Avoiding taking projects which are funded by the Palestinian financial ministry.

2- Delay in payments (1) Asking for advanced or mobilization payment (2) Loading of rates (3) Adjustment of work schedule to late start timing.. (4) Reduction of delays in receiving revenues. (5) Achievement of maximum production in the field to increase the monthly payments. (6) Reducing the retention. (7) Adjust the timing of delivery of large material orders to be with the submittal of the monthly invoice. (8) Delay in paying labor wages, equipment rentals, material suppliers and subcontractors. (9) Billing ahead of schedule.

3- Owed debts on the contractor before starting the project : 1. Asking for sufficient advanced payment or mobilization payment. 2. Loading of rates by increasing the prices of the earlier items which guarantee more income at the early stages and help in debts repayment. 3. Delay in some duties as much as possible such as: labor wages, material suppliers, equipment rentals and/or subcontractors. 4- Israeli Closure of the West Bank 1. Seeking for local alternatives and alternative materials. 2. Prolonging the duration of the project as a safety margin. 3. Increasing the value of the bid (the price). 4. Risk allocation (sharing risk between the key parties). 5. Avoiding far projects or projects at risky areas.

5- Foreign currency fluctuation and Exchange rate fluctuation This is one of the most frequent problems in Palestine since projects aren’t usually locally funded. This problem can be solved or avoided by inserting clear statements in the contract which fix and set the exchange rate.

6- Unsound pre-estimation of the project cost (faulty estimation) 1. To avoid this, estimations and calculations should be done by specialized ones in the company. 2. Taking into account both of the history of material prices fluctuation and future expectations (during the life of the project). 3. Using of modern technologies and methods as much as possible in finding out quantities and cost estimation. 4. An in-depth study of the contract is needed to avoid any ambiguity which may lead to wrong evaluation and estimation.

7- Inflation: 1. If the life time of the project is too long, the contractor can increase the price to avoid the case of inflation. 2. If the preceding choice leads to unsound value and his financial ability is unstable, then the contractor may avoid this kind of projects. 3. If possible, linking the value of the project in the contract with a fixed-kind value.

8- Labor strikes 9- Financial failure of the contractor (insufficient funding): 1. Crew of qualified assistants should be employed or experts should be consulted on and on. 2. Avoiding projects which are over the financial ability of the contractor. 3. Establishing partnerships with other companies (if preliminaries for this risk appear) to assure financial liquidity. 4. Delivery of the project to other able subcontractors. 10- Inadequate terms and conditions in tender documents