COASTAL DAMAGE REDUCTION FLOOD DAMAGE REDUCTION NAVIGATION ECOSYSTEM RESTORATIONREGULATORY INTERAGENCY & INTERNATIONAL SERVICES BUILDING STRONG ® US ARMY.

Slides:



Advertisements
Similar presentations
BUILDING STRONG ® Do not include this Slide. This template is a guide for preparing power points presentations. The information requested is important.
Advertisements

US Army Corps of Engineers BUILDING STRONG and Taking Care of People! Ecosystem Restoration Along the Los Angeles River: Creativity within Concrete Dan.
UMR = Balance of Environment and Transportation 1. Pool # 8 - Environmental Management Project 2. Transportation Route – human habitation & settlement.
TVI Resource Development (Phils), Inc. September Canatuan Tailings Management Completion of Stage 1 Tailings Management Facilties Gossan Dam and.
Study on Wave calculation of an air cushion surge chamber
John H. Kerr Dam and Reservoir John H. Kerr Dam and Reservoir U.S. Army Corps of Engineers Wilmington District.
Conversion of Petroleum Contaminated Soil into Asphalt-Treated Road Base U.S. Army Corps of Engineers, Alaska District.
PowerPoint ® Presentation Chapter 4 Flatwork Flatwork Applications Site Preparation Concrete Reinforcement Flatwork Procedures Joint Control Bleedwater.
Watershed Dams in Georgia 1. –357 Total –195 High Hazard (NRCS) –NRCS constructed – owned by local sponsors –Most built between 1950s-1970s for flood.
Infiltration Trenches Dave Briglio, P.E. MACTEC Mike Novotney Center for Watershed Protection.
Earth and Rockfill Dams
East Branch Dam Safety Modification Project
ENGINEERING GEOLOGICAL STUDIES for DAM CONSTRUCTION
Detention / Infiltration Structure. Figure 21–1 Point Discharge and Downstream Stability Analysis Procedure.
US Army Corps of Engineers BUILDING STRONG ® Louisiana Coastal Area Modification of Davis Pond Study Overview Governor’s Advisory Commission on Coastal.
US Army Corps of Engineers BUILDING STRONG ® FOLSOM DAM MODIFICATIONS APPROACH CHANNEL EIS/EIR Major Robert Dion and Cameron Sessions Project Managers.
Dams. Enhanced economic prosperity Public health Agriculture Altered natural environments Reduced streamflows Water quality degradation Fish and wildlife.
MINE WASTE DUMP The Overburden of waste and uneconomic mineralized rock is required to be removed to mine the useful mineral resource in a surface mining.
City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010.
1 Scoggins Dam Overview of Seismic Risk July 18, 2012.
US Army Corps of Engineers BUILDING STRONG ® Skiatook Lake Drought Issues and Management.
Agricultural Pond Private Engineering Resources & Costs Agricultural Water Resource Development Workshops Presented by: Cavanaugh & Associates P.A. 530.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Elements of Dam Engineering
One Team Destined For Greatness US Army Corps of Engineers BUILDING STRONG ® Operations Division Mark Yuska Chief, Operations Division.
Water Supply.
One Corps Serving The Army and the Nation Tulsa District The Tulsa District Corps of Engineers and Its Cooperative Partners.
Dams Mehmet Özger (Barajlar) Department of Civil Engineering, I.T.U.
Professional Engineering Services For Restoration Project John Mitnik, P.E. Engineering & Construction Bureau Chief Operations, Maintenance & Construction.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
Hydrologic Modeling with SSARR and HEC-HMS
US Army Corps of Engineers ® Engineer Research and Development Center Coastal and Hydraulics Laboratory Greenup Locks and Dam, Ohio River.
Cost Allocation Studies for the MP Region Bureau of Reclamation April 29, 2008 Central Valley Project Cost Allocation Study Update Public Meeting #2: October.
BUILDING STRONG ® Do not include this Slide. This template is a guide for preparing power points presentations. The information requested is important.
Central Valley Flood Protection Board Meeting – Agenda Item No. 4E APPLICATION NO
VILLAGE OF PATCH, NM, FEASIBILITY STUDY Village of Patch Case Study Seattle Environmen tal Planning Class June, 2009 US Army Corps of Engineers Albuquerque.
Power Plant Construction and QA/QC Section 7.2 – Dams, Spillways, Water Conductors and Power Houses Engineering Technology Division.
15 Water Supply. 2 Objectives Describe the sources of water for a municipal water supply system. Explain the purpose of a water treatment facility. Describe.
US Army Corps of Engineers BUILDING STRONG ® U.S. Army Corps of Engineers St. Paul District Channels & Harbors Project Presentation for 2012 WEDA Midwest.
Power Plant Construction and QA/QC Section General Features of Hydro Electric Project Engineering Technology Division.
Chapter 33 Dam Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Give reasons why.
The Health Care Center Dauphin County, PA Ken Lorenz Penn State University Architectural Engineering Construction Management April 17, 2007.
Peabody Coal Lower Basin Pipeline Engineering Appraisal Study Bureau of Reclamation September 18, 2002.
DAMS Dept. Of Civil Engineering
Otter Creek Watershed Meeting January 19, 2008 Mike Dreischmeier Agricultural Engineer Natural Resources Conservation Service.
Martin Rule Curve Study Ashley McVicar, APC Maurice James, Water Resources Consulting LLC.
3 Easy Steps STEP 1: SITE SELECTION Select Area with Unsuitable Rock Types.
US Army Corps of Engineers BUILDING STRONG ® Boise River Feasibility Study Ellen Berggren, PMP Outreach Coordinator/ Project Manager Idaho Governor’s Roadless.
Christopher Knotts, P.E. Public Works & Water Resources Association of Levee Boards of Louisiana Annual Meeting December 3, 2015.
US Army Corps of Engineers BUILDING STRONG ® Mississippi Coastal Improvements Program (MsCIP) “Comprehensive Barrier Island Restoration Plan” PIANC 2012.
US Army Corps of Engineers BUILDING STRONG ® Repairing the Mississippi River Levee with Dredged Material after the Historic 2011 Flood Dredging 2012 Shane.
MS Dam Safety Program Dusty Myers, P.E. Chief, Dam Safety Division.
Dam Safety Program March 2011 Dam Safety Program March 2011.
US Army Corps of Engineers BUILDING STRONG ® Name of Levee Segment Presenter Name Presenter Title Duty Location Date of Presentation.
Table Discussions 2015 SE Meeting. Scenario #1-Project Completion A $1 million bridge replacement project has a completion date of August 1 th. This date.
Ruttinger & Sons Engineering Designed by: Taylor Kasperick Jacob Wilson Loren Ruttinger Presented by: Loren Ruttinger.
Beth Kacvinsky - Lead Project Manager Office of Everglades Policy and Coordination March 1, 2016 IRL-S / C-44 Overview.
CVE 515 EMBANKMENT DAM ENGINEERING ENGR S.O ODUNFA DEPT. OF CIVIL ENGINEERING UNIVERSITY OF AGRICULTURE, ABEOKUTA.
DAM 1. RIGID DAMS: (a) Timber Dams (b) Steel dams (c) Arch dams (d) Buttress dams (e) Solid gravity dams 2.NON-RIGID DAMS: (a) Rock fill dams (b) Combined.
Presentation Overview
Infrastructure, Innovation and Standardization
Hoover Dam.
Taum Sauk Dam Failure Missouri, 2005
SAFETY IS TVA’S NUMBER ONE PRIORITY
FBE05 – Mathematics and Statistics
Illinois Waterway 2020 Consolidated Closure
Earth and Rock fill Dams
Aldine Westfield Stormwater Harris County Flood Control District
Sacramento Environmental Commission January 2019.
Further Your Career Join the US Army Corps of Engineers Galveston District USACE Vision Deliver vital public and military engineering services; partnering.
Presentation transcript:

COASTAL DAMAGE REDUCTION FLOOD DAMAGE REDUCTION NAVIGATION ECOSYSTEM RESTORATIONREGULATORY INTERAGENCY & INTERNATIONAL SERVICES BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | JACKSONVILLE DISTRICT Portugués Dam Portugués and Bucaná Project Portugués Dam Portugués and Bucaná Project 1 Steve Duba, P.E. Chief, Construction Division

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Project Video Project Video

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Project Map Project Map

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Authorization: R&H Act 1970, WRDA 1986 (PL ) WRDA 1986 (PL ) Urban Area Affected: 1,833 Acres Population: - Subject to severe flooding: 40,500 - Subject to severe flooding: 40,500 - Residential Structures: 13,200 - Residential Structures: 13,200 Commercial & Public Structures: - Commercial Area: 5 Million SF - Commercial Area: 5 Million SF - Hospital, Schools, Courts, Police Depts. - Hospital, Schools, Courts, Police Depts. Estimated Project Cost: $300 M Range of Damages Prevented: $400M-$600M (100-year event) Direct Jobs Created: 650 (Peak) Sponsor: Department of Natural and Environmental Resources Environmental Resources Portugués Dam Pertinent Facts Pertinent Facts

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Initial Thin Arch Conventional Concrete Alternative Initial Thin Arch Conventional Concrete Alternative  Nov 93 - Apr 96: Left Abutment Excavation  Dec 96 - Sep 98: Right Abutment Excavation  Oct 97 - Dec 99: Foundation Grouting  Sep 00: Advertised Arch Dam ► One Bid – Outside of Awardable Range After several studies and cost estimates, design was changed to Roller Compacted Concrete and detailed studies and design began for a 5-yr program.

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Goals in Changing to Thick Arch RCC Goals in Changing to Thick Arch RCC  Explore technology initially ruled out due to its newness in the 80’s  Utilize advancements in RCC technology and techniques  Realize savings in construction time  Maximize utilization of investment on site Arch-shaped foundation excavations Installed initial grout curtain  Avoid extensive new excavations mandated by a gravity design  Pursue Optimal Geometry to reduce total quantity of RCC  Ensure utilization of local regular use cement manufacturing  Deliver the final component of a much need flood reduction project

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Thick Arch RCC Design Thick Arch RCC Design  Only 10 in the world (from 17 to 100 meters in height) ► 3 in South Africa ► 7 in China  First Thick Arch RCC by USACE ► USACE did the first Gravity RCC dam in US Willow Creek 1981 (Oregon)

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Thick RCC Design Pertinent Data Thick RCC Design Pertinent Data Dam Height: Crest Length: Spillway Crest Width: Flood Control Storage: Max Pool Area: Dam Crest Elevation: Spillway Crest Elevation: RCC Volume: Thickness: Contraction Joints: Design: 220 ft 1,230 ft 140 ft 9,484 acre-ft 215 acres ft ft 367,000 cy ft base, 30 ft crest Spaced 70 ft. In-house w/ITR & Other Corps

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Hydraulic / Hydrologic Hydraulic / Hydrologic  Normal River Flows Low (less than 50 cfs)  10.5 Square Mile Basin  Outlet Works include Intake Structure with Emergency Sluice/Roller Gates, Two 60-inch Diameter RO’s, Emergency and Service Valves in Valve House, Emergency Spillway.  Emergency Spillway - Ogee Crest with Flip Bucket Designed for PMP (45,000 cfs) 2,800 yr event Durations Used for Scour Evaluation

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Structural Structural  Single Centered Thick Arch Dam  Designed for Static, Dynamic, and Thermal Loading  Thermal Analysis Determined Placing Temperature and Contraction Joint Spacing.  Designed as a 3-dimensional structure  Designed for Closed Contraction Joints  Horizontal Joint Tensile Strength Important During Seismic Events  Extensive RCC Design and Testing Program  Cold Joint Considerations

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Geotechnical / Geology Geotechnical / Geology  Foundation Block Stability Analyzed for Dam Induced Loads, Water Gravity Loads, Uplift, and Seismic Loads  Grout Curtain utilized to Reduce Seepage and Uplift  Seepage Analyzed and Foundation Drains Designed  Slope Stabilizations  On-site Quarry Source of RCC Aggregate  Foundation Dental Concrete/Treatments

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Main Dam Portugués Dam Design Features Design Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Dam Sections Portugués Dam Design Features Design Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Outlet Works Portugués Dam Design Features Design Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Outlet Works Portugués Dam Design Features Design Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Dam Gallery Portugués Dam Design Features Design Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District  PHASE 1 – $24,465,435  MOBILIZATION, CLEARING, QUARRY OVERBURDEN EXCAVATION, POWERLINE RELOCATION  PHASE 2 – $47,625,652  FOUNDATION EXCAVATION, AGGREGATE PRODUCTION, DENTAL CONCRETE  PHASE 3 – $37,293,763  AGGREGATE PRODUCTION, ½ DAM RCC PLACEMENT  PHASE 4 – $41,061,083  FINAL DAM RCC PLACEMENT, SPILLWAY, INTAKE STRUCTURE  PHASE 5 – $29,672,717  REMAINING ITEMS, VALVE HOUSE, ACCESS ROAD, MECHANICAL, ELECTRICAL. Portugues Dam Project Phasing Project Phasing

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Project Map Project Map

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Quarry Excavation Approx. 567,170 cy excavated

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Aggregate Production and Stockpiling

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Foundation Excavations

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities RCC Production

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities RCC Mix Design Diversion and Care of Water System

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities RCC Mix Design Diversion and Care of Water System

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Diversion and Care of Water Delay-causing Over-toppings: Sep 30, 2010 Oct 4, 2010 Oct 5, 2010 Oct 6-10, 2010 Oct 17, 2010 Delay-causing Over-toppings: Sep 30, 2010 Oct 4, 2010 Oct 5, 2010 Oct 6-10, 2010 Oct 17, 2010

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Diversion and Care of Water

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Foundation Preparation Work Foundation Preparation Work AS- 11/12 : Foundation Excavation Cleanup

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Drilling and Consolidation Grouting

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities RCC Conveying, Spreading, Compaction, Joint Installation

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Gallery Gallery Gallery Formwork

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Construction Activities Construction Activities Dam RCC Work Topped Out

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Gallery Gallery Gallery Finish

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Foundation Preparation Work Foundation Preparation Work Grouting Setup & Grout Curtain Drill

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Instrumentation Instrumentation Stress / Strain Meters & Joint Meters

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Dam Features Dam Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Dam Features Dam Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Dam Features Dam Features

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District Portugués Dam Conclusions Conclusions  QC Process critical and perhaps more involved than Conventional Concrete Need for sound QC planning and preparatory work process Need for qualified and energetic individuals overseeing the process Need for intense tracking of RCC production and placement parameters  Safety a constant challenge due to multiple activities in close proximity Management involvement in Safety is fundamental Production Staff needs to adopt a Safety Culture Accountability is a must Position of Competent Person as defined by OSHA is critical  Choice of Dam type always based on site considerations, but RCC nowadays a hard to beat choice.

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District ContractorsContractors Prime: Main Sub: : Others: Dragados USA José Carro Const. RC Professionals GEHS Environmental EST Electrical HEAT Security JV Geoland ARC Surveying Frank Electric Altol Laboratories CCG Drilling & Blasting Award: Notice to Proceed: Original Completion Date: Final (Actual) Completion: Beneficial Occupancy: 03/14/ /03/ /08/ /27/ /01/2014 Contract Milestones Award Amount: Modifications: Contract Total: $180,118, $36,718, $216,837, Contract Cost Portugués Dam Contract Data Contract Data

BUILDING STRONG ® US ARMY CORPS OF ENGINEERS | Jacksonville District The End