MICE hydrogen review Commissioning, testing and operations.

Slides:



Advertisements
Similar presentations
1 CM24 – 2 nd June 2009 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
Advertisements

Hydrogen Pre-Operation Safety Review 4 th October 2011 Hydrogen R&D System Operational Procedures and Test Plan M Courthold.
MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton.
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
Hydrogen Hazard Summary and Preliminary FMECA and HAZOP Yury Ivanyushenkov Elwyn Baynham Tom Bradshaw.
1 Status of Hydrogen System Development MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov, Tom Bradshaw, Elwyn Baynham, Mike Courthold,
MICE RF Module Safety Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting February 12, 2005.
CM26 – 26 th March 2010 Step IV: Liquid Hydrogen Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
1 MICE Absorber working group Columbia, 13 June 2003 MICE Hydrogen System. Preliminary HAZOP. Elwyn Baynham, Tom Bradshaw and Iouri Ivaniouchenkov,
MICE Safety System DE Baynham TW Bradshaw MJD Courthold Y Ivanyushenkov.
Absorber/vacuum windows and absorber assembly 1.Window Requirements 2.MICE experimental constraints 3.Welded vs. non-welded windows 4.Installation 5.Testing.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
March 14, 2003 MICE Absorber/Coil Integration MICE LH2 Absorber 1.Assembly 2.Safety 3.Staging 4.Instrumentation.
MICE collaboration meeting RAL 28 October 2004 Absorber R & D Plan by Wing Lau – Oxford University.
1 Infrastructure at RAL Iouri Ivaniouchenkov, RAL MICE Collaboration CERN, 29 March 2003.
Hydrogen R&D system HAZOP and failure analysis Yury Ivanyushenkov, Elwyn Baynham, Tom Bradshaw, Mike Courthold, Matthew Hills and Tony Jones.
1 Technical Arguments in Favor of using the Cryomech PT-415 Cooler for Cooling the LH 2 Experiment Michael A. Green Lawrence Berkeley Laboratory Berkeley.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
MICE Hydrogen System Design Tom Bradshaw Iouri Ivaniouchenkov Elwyn Baynham Columbia Meeting June 2003.
MICE Hydrogen System MICE Collaboration Meeting, CERN, 29 March-2 April 2004 Elwyn Baynham, Tom Bradshaw, Yury Ivanyushenkov Applied Science Division,
MICE hydrogen review Summary of system hardware. System function To provide 22 litres of liquid hydrogen for use as a muon absorber within a superconducting.
Mechanical Safety Systems and DSEAR Compliance
MICE hydrogen review System modifications. Relief circuit repair During leak testing of R&D tests, the insulating vacuum would not go lower than
The MICE vacuum system Presented by Mark Tucker at CM-39, 26 June 2014.
MICE Hydrogen System Tom Bradshaw Yury Ivanyushenkov Elwyn Baynham Meeting October 2004 – Coseners House.
Patrick Thornton, SNS/FPE June 9, 2008
MICE Hydrogen Control System MICE H2 Review Meeting RAL 15 th Jan 2015 PJ Warburton – STFC Daresbury Lab.
MICE - UK Project Progress Roy Preece 30 th April 2013.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
MICE Hydrogen Safety Functions IEC61508 Compliance & Emergency Procedures MICE Safety Review Meeting 4 th Oct 2011 PJ Warburton - Daresbury Lab.
1 Liquid Hydrogen R&D test report Video Conference – 23/08/12 S Watson P Warburton M Courthold.
MICE Hydrogen Control System MICE Collaboration Meeting CM33 27 th July 2012 PJ Warburton – STFC Daresbury Lab.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Conceptual Design Review of the NPDGamma Experiment in Beam Line 13 Seppo Penttila NPDGamma project manager September 25, 2007 at SNS.
Hydrogen Pre-Operation Safety Review 4 th October 2011 Results from Helium Commissioning M Hills.
The MICE Hydrogen System Safety Review Introduction Tom Bradshaw, Yury Ivanyushenkov, Elwyn Baynham, Tony Jones, Mike Courthold and Matthew Hills Rutherford.
ERL: G-5/e-Gun Cryogenic & Pressure Safety Committee Review ERL G-5/e-gun Beam Line Vacuum Failure Analysis April 24, 2009.
MICE Hydrogen Control System MICE Safety Review Meeting 4 th Oct 2011 PJ Warburton - Daresbury Lab.
MICE hydrogen review Approval process. Process Working group Document pack PPD Director & ISIS Director Prerequisite testing Completed action list Approval.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
CM 28 – 6 th October 2010 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
MIPO meeting 12/05/15. Exec summary Working group satisfied in integrity of absorber vessel and windows, pending review of reports – Proof test at 2.2.
1 Small Coolers for MICE Michael A. Green University of Oxford Department of Physics Oxford OX1 3RH, UK MICE Collaboration Meeting RAL.
Hydrogen Control System MJD Courthold TW Bradshaw Y Ivanyushenkov D Baynham.
Hydrogen System Update Video Conference 19 th January 2012 S Watson.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
1 Liquid Hydrogen R&D test report CM34 – 17/10/12 S Watson P Warburton M Courthold.
1 Liquid Hydrogen update CM33 S Watson P Warburton M Courthold.
1 MICE absorbers work package MPB – 27/10/15 Mike Courthold Mark Tucker Phil Warburton Steve Watson.
1 MICE Absorbers work package MPB – 17/04/15 RAL Tom Bradshaw Vicky Bayliss Mike Courthold Matt Hills Andy Nichols Roy Preece Mark Tucker Steve Watson.
1 MICE Hydrogen system Working group mtg – 01/09/14.
H.-G. Moser, PXD Workshop, Valencia, January 2016 IBBelle for VXD 1 Use one unit first Assemble on a platform which fits in a 20’ container No redundancy.
Working group meeting 07/05/15. Agenda Overview of review and current action list Relief system – Summary of problem – Details of analysis, testing and.
S A Griffiths CM42 June 2015 Electrical & Control.
MICE Absorber and Focus Coil Magnet – Test Results
Hydrogen System Update
Absorber progress MICE-ISIS review of the liquid hydrogen system will be held in early January; guidance from Nominated Engineers on the imported absorber.
MICE Hall Summer Workplan
Proximity Cryogenics P&IDs meeting
MICE Safety Review Meeting 4th Oct 2011 PJ Warburton - Daresbury Lab
Project Manager’s Report + DC/MoM Report
Status of Hydrogen System Development
Cryogenic System Commissioning Summary Report
ESS elliptical cryomodule
Presentation transcript:

MICE hydrogen review Commissioning, testing and operations

Commissioning progress Transfer line manufactured and (roughly) fit-checked Vacuum line manufactured and fit-checked Absorber assembly – Window – absorber indium seals made – 2 MLI blankets applied

Testing Pre-sign off – Pressure test of absorber/window assembly* – Pressure test of newly installed pipework – Leak testing of overhauled relief circuit Pre-cryogenic operation – Leak test of modified sub-assemblies – Leak test of entire system – Turbo pump run-in test in isolation* – Test of gas detection system – Systematic test of valve and instrumentation operation Pre-experimental operation – Purge sequence* – Fill/empty cycle with helium* – Fill/empty cycle with hydrogen

Absorber system pressure test LH2 Vacuum Gas panel Two failure scenarios – Heat load into absorber, causing rapid boiling of LH2 through absorber relief line – Absorber window rupture, causing rapid boiling of LH2 predominantly through vacuum relief line AbsorberVacuum Both PRV Δ0.5 bar

Absorber system pressure test Heat load scenario – Significant heat can only feasibly come from a vacuum failure but… A safety window rupture would not cause a vacuum failure The surrounding vacuum vessels are substantial and unlikely to fail in a catastrophic way Small leaks, such as from seal degradation, would not result in rapid boil-off – Nevertheless, if such a vacuum failure were to occur, two estimates of the heat load into the LH2 were made: Film boiling i.e. maximum possible rate of heat transfer, regardless of ΔT ~ 19kW CERN paper with experimental data suggesting actual max heat transfer would be ~5kW – The latter figure was taken, doubled, and used to calculate a boil-off rate of kg/s – This was used to calculate a total pipe pressure drop from absorber to flame arrestor of 1.92 bar – PRV pressure is 1.5 bara. 1.1 x 1.25 x 1.5 bar = 2.06 bar, so a pressure test to this will be adequate. Note, windows have already been burst tested to above 8 bar

Absorber system pressure test Window failure scenario – Boiling rate from hydrogen spill would be considerable but has not been calculated with similar rigour to previous scenario (estimated at 0.12 kg/s in worst case) – However… Absorber and vacuum relief lines are effectively in parallel in this scenario, thus halving the pipe impedance There is a ‘bucket’ in the vacuum space to reduce the surface area which a spillage would be subject to The safety windows are 0.21mm at their thinnest point, as oppose to 0.18mm in the absorber windows The most likely window failure scenario is a crack or small breach, resulting in a much slower rate of heat transfer than in a full-scale rupture – MICE argues that testing to a higher pressure for the safety windows is unnecessary A burst test as per the absorber windows should be carried out however

Turbo pump Failures experienced – Pictured failure was seemingly random (and also not our pump!) – However, also had bearing problems due to excessive periods of inactivity Preventative maintenance programme – Gradual run in every 6 months – Pumps in storage for longer than 1 year sent to Leybold for bearing replacement – Project also has multiple spares now

System tests Helium purge – Pressurises with helium and pumps out three times – Tests operation of the gas panel, pumps, pressure gauges and control system Helium fill – no liquid – Uses the control valve to maintain helium pressure in the absorber vessel as it cools – Radiative heat load means the system will not reach 4.2K – Tests operation of the temperature sensors and cryocooler and provides an indication as to the cryogenic performance of the system as it cools down – Will have to be manually terminated Hydrogen vent – Replaces the old hydrogen empty sequence – Opens the vent line valve and switches the heater onto the absorber – won’t be particularly representative with cold helium but will still test the interlocks, valve operations etc

Milestones November December January February March April May June PRY installation 2015 FC contractual acceptance Absorber assembly FC#2 to MICE Hall Hydrogen safety review Vacuum and leak testing Pressure testing of absorber Cryogenic (helium) testing Hydrogen safety sign-off Cryogenic (hydrogen) testing Magnet testing begins

Operations General principle is that only designated ‘hydrogen experts’ interact with the system when hydrogen is present – Broadly speaking, this statement also stands during helium operations Hydrogen experts are: – Myself – Mike Courthold (part-time) – Phil Warburton (based at DL) – Mark Tucker (based at RAL) R&D tests took 4 weeks and required 14 people to staff 24/7 Same coverage will be required for: – Hydrogen commissioning – Active hydrogen sequences during operation – …but not for remainder of user runs – this will covered by on-call arrangements

Operations Run schedule handled by Steve Boyd (Warwick Uni)