PHYSICAL MODELING OF BREACH FORMATION Large scale field tests Kjetil Arne Vaskinn, Sweco Gröner Norway.

Slides:



Advertisements
Similar presentations
E4014 Construction Surveying
Advertisements

Changing Earth TEK 5.7B.
Flood Profile Modeling with Split Flows and Weirs
Stability and Failure Mechanisms of Dams A dam safety research project Kjetil Arne Vaskinn.
IMPACT Project Breach Modeling Tests. Dam Failures Increasing (?) Worldwide.
IMPACT ~ Breach Physical Modelling Review of Modelling Work Undertaken So Far...
Kelly Barnes Dam Failure
TVI Resource Development (Phils), Inc. September Canatuan Tailings Management Completion of Stage 1 Tailings Management Facilties Gossan Dam and.
Soil Compaction.
The Failure of Teton Dam
Lower Yellowstone River Diversion Dam Project – Phase II - Physical Modeling of the Rock Ramp BRT, COE, MTAO Update Meeting November 4, 2010.
A COMPARISON OF HOMOGENEOUS AND MULTI-LAYERED BERM BREAKWATERS WITH RESPECT TO OVERTOPPING AND STABILITY Lykke Andersen, Skals & Burcharth ICCE2008, Hamburg,
The Asphalt Core Embankment Dam A Very Competitive Alternative
Weirs and Canal Intakes By: Nell Kolden and Taylor Barnett Thursday April 12, 2012 CIVE 717.
Course : S0705 – Soil Mechanic
Grade Control Structures Chris Shrimpton and Jonathan McIntosh CIVE 717 River Mechanics Spring 2012.
Earth and Rockfill Dams
DAMS.
Sharif University of Technology Civil Engineering Department Tehran-Iran Dam Safety An Approach to Prevent Dam Incidents.
Construction Monitoring For Earth Dams 1 Fars Science and Research Branch, Islamic Azad University.
2006 Project Alternatives Pit and Dike Risk Evaluation MEADOWBANK GOLD PROJECT.
MINE WASTE DUMP The Overburden of waste and uneconomic mineralized rock is required to be removed to mine the useful mineral resource in a surface mining.
Sediment Movement after Dam Removal
SESSION 3 Subgrade This module presents the concepts and methods of characterizing the subgrade for the purpose of concrete pavement design. It also highlights.
WINDAM Technology Workshop Sept 1-3, 2009 WINDAMb-e (Windows Dam Analysis Modules)
DAMS Dams are built for one or more of the following purposes: Irrigation Irrigation Flood Control Flood Control Power Generation Power Generation Water.
“Research in dam breaching" Sílvia Amaral PhD Student (1 st year) December, 14 th 2009.
What is compaction? A simple ground improvement technique, where the soil is densified through external compactive effort. + water = Compactive effort.
6.4 Improving Diversion Works
The sand filter has to be moved from this location. The embankment cross section used in the slope stability analysis did not include the sand filter.
TVI Resource Development (Phils), Inc. September Gossan Dam Embankment Construction Late July 2005 Placement of Core Zone Material. Placement of.
BREACH FORMATION A Review of State-of-the-Art Mark Morris HR Wallingford IMPACT Project Workshop Wallingford, 16/17 May 2002.
Deposition. When transported material settles or comes to rest Caused by: running water, glacial ice, waves, or wind losing energy so they can no longer.
Power Plant Construction and QA/QC Section 7.2 – Dams, Spillways, Water Conductors and Power Houses Engineering Technology Division.
9. Seepage (Das, chapter 8) Sections: All except 8.2, 8.6, 8.7, 8.8, 8.9.
Formulation of a New Breach Model for Embankments IMPACT Project Workshop, Wallingford 2002 Breach Formation Theme.
DAMS Dept. Of Civil Engineering
Large Scale Embankment Failure
PART 3 – USING SITES SOFTWARE C. Overview of SITES output a. Key text outputs b. Key graphical outputs SPECIALTY WORKSHOP: SITES TRAINING AND INTRODUCTION.
DAM BREAK RISK IN COLOMBIA A Geospatial Assessment of Population Vulnerability from Flood Inundation Eugene Derner, GEOG 594a Spring 2014.
Dam Safety in the 21 st Century PFMA as a Dam Safety Tool – Joe Ehasz FERC Regulator Perspective – Doug Johnson USACE Perspective – Doug Boyer Owner Perspective.
3 Easy Steps STEP 1: SITE SELECTION Select Area with Unsuitable Rock Types.
THE TETON DAM FAILURE.
EPSRC Grant: EP/FP202511/1 WP4.4 A Rapid Embankment Breach Assessment (AREBA) Myron van Damme Sept 2011.
Group 14 Angelina Hand Mark Kelly Lydia Rooney Seán Stapleton.
Chapter 2: Total Hydrostatic Force on Surfaces
IMPACT 4 November 20044th IMPACT Workshop - Zaragoza1 Investigation of extreme flood Processes and uncertainty Model uncertainty How uncertain are your.
SOIL MECHANICS AND CLASSIFICATION. FACTORS WHICH HOLD SOIL TOGETHER o Cohesion  Internal Friction.
HYDROLOGY & WATER RESOURCES ENGINEERING TYPES OF SPILLWAYS
01/2012 The Shikwamkwa Replacement Dam Five Years Later C. Richard Donnelly, Hatch ● Bryan Tatone, University of Toronto ● Warren Hoyle, Noel Boucher,
CVE 515 EMBANKMENT DAM ENGINEERING ENGR S.O ODUNFA DEPT. OF CIVIL ENGINEERING UNIVERSITY OF AGRICULTURE, ABEOKUTA.
Bartolome, Mark John Faustino, Frank Lipaopao, John Rei
EXAMPLE Water flows uniformly in a 2m wide rectangular channel at a depth of 45cm. The channel slope is and n= Find the flow rate in cumecs.
FLUID MECHANICS.
Explain the formation of a glacial trough. [7 marks]
In geotechnical engineering, soil compaction is the process in which a stress applied to a soil causes densification as air is displaced from the pores.
EROSION.
Taum Sauk Dam Failure Missouri, 2005
Bituminous-faced Rockfill Dam Seismic Performance Prediction of stress-strain behaviour and potential damages Proposal for the 15th International Benchmark.
THE FAILURE OF SHIH-KANG DAM
Construction Monitoring
REGULATION WORK UNIT – 10 LECTURER IN CIVIL ENGG. GP MEHAM SANDEEP.
EROSION.
Earth Science Chapter 8 Section 3
Lake 16 Dam Repair Presentation
Estler Lake Dam Rehabilitation
Earth and Rock fill Dams
Dams.
IMPACT ~ Breach Formation (WP2)
Civil Engineering Dept.
Presentation transcript:

PHYSICAL MODELING OF BREACH FORMATION Large scale field tests Kjetil Arne Vaskinn, Sweco Gröner Norway

Test site Test area at the reservoir lake Røssvatnet Tustervassdammen Røssvatnet

Test area at the reservoir lake Røssvatnet

Instrumentation Water levels (stage-discharge measurements): Upstream of the dam Downstream of the dam Discharge through the gates at Røssvassdammen Photo (several points) Video (3 different cameras) Pressure sensors in the dam Breach sensors

Large scale field-tests 2002

2 m m 1 Rock 1 Clay, moisture content 30%, placed in 0.15 m layers compacted with dozer Homogenous clay dam

A 0.5 m deep and 3 m wide channel at the top of the dam for initiation of the breach Due to high water content in the clay deposit (w = 28-33%) construction of the dam became difficult. To improve construction the layer thickness was increased to 0.4 m and the compaction pressure was reduced. Homogenous clay dam

Water elevation and discharge Homogenous clay dam

2 m 5m Concrete sill Clay Rock Homogenous (minimum cohesive) dam. Gravel 0-60 mm, fines (0,074mm)<5%, 4 mm<d 50 <10 mm, d max <60 mm 0.5 meter layer, compaction by 4 tons roller compacter, 2 layer with pore pressure sensors. Gravel dam

Left hand side Right hand side Gravel dam

Large scale field-tests 2003

Rockfill dam with moraine core – breaching by overtopping. 5.9m m m 1.5m Concrete sill and V- notch weir Clay Rock 0.24m deep and 8 m wide notch in dam crest during breach test 2 Rock from tunnel spoil 0-500mm 3 Rockfill mm Defects built into dam for test of leakage detection Pressure tranceducers Moraine 1

Rockfill dam with moraine core – breaching by overtopping.

Rockfill dam with moraine core – breaching by piping/internal erosion 6m Concrete sill and V- notch weir 6m Small defect Large defect 3m Clay Rock Defects built into dam for initiation of piping, two 200 mm half-pipes embedded in uniform sand Moraine, vibratory compaction, 0.5 m layer thickness 1 2 Rock from tunnel spoil 0-500mm, vibratory compaction, 1 m layer thickness 3 Rockfill 3-400mm, vibratory compaction, 1 m layer thickness 1 2 3

Rockfill dam with moraine core – breaching by piping/internal erosion

Homogenous moraine 4.5m Concrete sill and V- notch weir 4.5m 3m Clay Rock Defect built into dam for initiation of piping. 200 mm half-pipe with slots embedded in uniform sand Moraine, vibratory compaction, 0.5 m layer thickness Remaining portions of previous test dam 2 2

Homogenous moraine

Analysis of the data has started and is likely to continue for some years. The data will assist in the development of understanding and validation of predictive models. Prior to this analysis, some initial, broad observations may be made based upon field observations and data analysis to date. These include the following: Summary / conclusions

1.The failure processes of the different embankments have been observed. 2.Features such as cracking, arching (pipe formation), headcut formation and progression were all observed. 3.Existing breach models does not accurately simulate many of these features. Summary / conclusions

4.The first phase in the external erosion of the downstream slope due to overtopping is slow and very gradual. 5.When the scour and unraveling finally reaches the upstream edge of the dam crest, the breaching is rapid and dramatic. 6.The same general observations were made for the rockfill, gravel and clay dams. 7.The opening of the breach first progresses down to base of the dam, before it expands laterally. The sides of the breach were very steep, almost vertical, in all three materials. Summary / conclusions

8.The rate of breach growth for the homogeneous clay and gravel dams was not as expected. 9.The clay dam failure more quickly, whilst the gravel dam more slowly than expected. It is likely that this was due to the condition of material and nature of construction / compaction. This demonstrates the significant impact that material condition and construction method may have on breach formation and hence the need to consider these aspects within predictive models. Summary / conclusions

10.The internal erosion process, initiated at the defects built into the moraine core of the rockfill dam (Test ), took a very long time to develop, even in this dam with no filters between the moraine core and the downstream rockfill. 11.Breaching of the dam did not take place until the erosion had proceeded up to the dam crest, and then the dam failed by overtopping as in Test , but the breach opening was not so wide. Summary / conclusions

12.The difference in rate of embankment failure for the homogeneous moraine embankment and the composite moraine / rockfill embankment was significant. This demonstrates the importance of the interaction between layers of material within a composite structure. This has implications for overall dam stability and in the development of predictive breach models. Summary / conclusions

13.Many of the field test scenarios simulated typical rockfill embankment dams. As such, there was surprise that the rate and mechanisms of failure observed were typically more resistant than existing analyses and guidelines prescribe. Summary / conclusions