Design/Build Team for the US 36 Express Lanes Project.

Slides:



Advertisements
Similar presentations
Click to edit Master title style »Click to edit Master text styles –Second level Third level –Fourth level Fifth level Construction Update 11/13/2012 Larry.
Advertisements

Some things cant wait for traffic Capital Beltway HOT Lanes Project New Travel Choices Ahead.
Project Description and Needs Lincoln Way Widening Addition of a center-turn lane and safety improvements to the grade and horizontal alignment. Needs.
Maryland Avenue and Arkwright Street Nick Fischer, EIT Ramsey County Jerry Auge, PE Project Manager Ramsey.
Maryland Avenue and Arkwright Street Jerry Auge, PE Project Manager Ramsey County June 25, 2013.
Meeting Agenda Introduction of Project Team Connective Corridor Project Onondaga County Sewer Separation Project Civic Strip Project Syracuse University.
County of Fairfax, Virginia Sully District Council Meeting November 19, 2014.
Congressional District Projects New CD-2 SH 392 Interchange at I-25: — Bridge replacement and widening, will also improve on/off ramps and frontage roads.
I-80 Robb Drive to Vista Boulevard Design-Build Project I-80 Robb Drive to Vista Boulevard Design-Build Project.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
WELCOME! October 28, 2013 ODOT District 1 & District 2.
Project Construction Update August 30, 2011 I-5 North Stockton Freeway Widening and Pavement Reconstruction Project Between Dr. Martin Luther King Jr.
75 Express Lanes Segment D Construction From South of Sheridan Street to North of Griffin Road Presentation to Ivanhoe Community August 27, 2014.
New I-65 Interchange at Worthsville Road Welcome!.
January 31 st, 2012 North Coast Corridor A Better Environment for the Future.
Transportation Infrastructure Bond Corridor Mobility Improvement Account.
ROUTE 7 TRAFFIC FLOW IMPROVEMENTS POTOMAC VIEW ROAD TO AUGUSTA DRIVE LOUDOUN COUNTY DEPARTMENT OF CONSTRUCTION AND WASTE MANAGEMENT A. MORTON THOMAS &
Tysons 1 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County.
Route 28 South of I-66 Corridor Safety and Operations Study Technical Committee Meeting #2 June 25,
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
I-65 Added Travel Lanes Project in Tippecanoe County
75 Express Lanes Segments A&B Construction From NW 170 Street to South of Miramar Parkway Community Meeting Presentation Tuesday April 28, 2015.
© 2011 HDR All rights Reserved. Value Engineering Ken L. Smith, PE, CVS (360) April 27 th, 2011.
North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013.
MAINTENANCE & TRAFFIC OPERATION INCIDENT MANAGEMENT.
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Fast Forward Full Speed Ahead Presented at the Joint ITS Georgia / Tennessee Annual Meeting September 25, 2006 by Carla W. Holmes, P.E., PTOE Georgia Department.
Current Construction Projects Major Projects Pinellas County.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
Congressional District Projects New CD-7 North I-25 Record of Decision (ROD): — Recently signed the Environmental Impact Statement (EIS), for the corridor.
What are Managed Lanes What are Express Lanes What are HOT Lanes Regional Express Lanes Network I-95 Express I-595 Express I-75 Express.
SR 997 / KROME AVENUE Florida Department of Transportation April 27th, 2006 South Miami-Dade Watershed Study Advisory Committee.
Briefing on the Washington Metropolitan Area Transportation Operations Coordination (MATOC) Program Presentation to the Transportation Planning Board Michael.
I-394 MnPASS Technical Evaluation Preliminary Findings March 23, 2006 Doug Sallman – Cambridge Systematics, Inc.
THE I-75 DAYTON RECONSTRUCTION
Decision Support Needs for Transportation Systems December 5, 2000 Emil Wolanin Montgomery County, Maryland.
Office of Traffic, Safety and Technology Module 4 Work Zone Applications Traffic Control Plan Development Course.
PUBLIC MEETING November 19, 2003 Lower Manhattan Redevelopment D015183, PIN NYCD NYSDOT, REGION 11 Route 9A Project.
Route 55: Lauer Rd –TSP & Access Management. Agenda  Welcome and Introductions  Workshop Purpose  Project Introduction & Background  Citizen Advisory.
Tom Norton, Executive Director Colorado Department of Transportation American Association of State Highway and Transportation Officials September 9, 2003.
1 Rehabilitation of 188 th Street over Grand Central Parkway PIN: X Contract #: D Deck Replacement October 2015.
I-80 Robb Drive to Vista Boulevard Design-Build Project I-80 Robb Drive to Vista Boulevard Design-Build Project Jeff Lerud, PE, CPM Project Manager APWA.
Line 22 BRT: Summary Santa Clara Valley Transportation Authority May 2003.
I-495 NORTHERN SECTION SHOULDER USE PROJECT State Project No , P101, C501 CITIZEN’S INFORMATION MEETING UPC NOVEMBER 19, 2013.
Design Manager: Chris Thomas CEAL July 17, Interstate 8 (I-8) to Interstate 5 (I-5) Connector Widening and Auxiliary Lane Project.
I-15 Express Lanes Project January 2012 I-15 Express Lanes Project January 2012.
Minnesota’s Urban Partnership Agreement UPA Timeline The UPA agreement with the US DOT requires that the project be operational by September 30, 2009,
September 14, 2015 Transportation Board of Directors John M. Terry Assistant Director- Engineering SR-160 from SR-159 to Mountain Springs Phase 2 Final.
Orange County Business Council Infrastructure Committee Overview of RCTC’s Major Projects December 8, 2015.
Update on the Escambia/Santa Rosa Regional Advanced Traffic Management System (ATMS) Feasibility and Implementation Plan Ben Faust, P.E. Advanced Traffic.
2010 Regional Intelligent Transportation Systems Plan: 2015 Progress Report on Implementation.
Campus Plan Roosevelt Island campus > Laboratory of innovation > Open and inviting to the public > Sustainable and energy-efficient.
Madison Avenue Reconstruction Department of Planning and Development.
1 MD 5 (Point Lookout Road) Leonardtown (Phase 1) Intersection Reconstruction At Abell and Moakley Streets Informational Meeting January 19, 2016.
HAMILTON COUNTY SR-317 (Bonny Oaks Drive) Widening From SR-17 to I-75 January 21, 2016 Robert Rodgers - C.E. Manager 2 TDOT Region 2 Project Development.
South/West Corridor Transit Improvements ZARZAMORA AND MILITARY PRIMO BRT PROJECTS ENVIRONMENTAL AND PRELIMINARY DESIGN PHASE September 9, 2014 VIA Community.
U.S. ROUTE 202 – SECTION 300 IMPROVEMENT PROJECT East Whiteland Township – Tredyffrin Township Chester County TMACC Information Session January 24, 2011.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
US 36 Bus Rapid Transit RTD Board Update January 6, 2015.
RTD Board Update October 8, 2013 US 36 Bus Rapid Transit.
GEORGE WASHINGTON HIGHWAY WIDENING PROJECT E.V. WILLIAMS, INC.
Orange County Transportation Authority
Four Winds Condominium Association August 2, 2017
2010 Regional Intelligent Transportation Systems Plan: 2017 Progress Report on Implementation The Florida-Alabama, Okaloosa-Walton, and Bay County Transportation.
SE 12th Street Roadway Improvements February 8, 2005.
Contract 60X10 Informational Meeting Weber I-55
S.R. 261 Intersection Improvement at Fruitwood Lane in Newburgh
Metropolitan District | mndot.gov
Dakota County Board Of Commissioners August 6, 2019
Presentation transcript:

Design/Build Team for the US 36 Express Lanes Project

 Selected Ames/Granite Joint Venture on Feb. 29  In addition to the base project elements, the team has committed to:  Extending the terminus of the project from Interlocken Loop west to 88 th Street in Louisville/Superior;  Reconstructing the Sheridan Boulevard Bridge over US 36, along with roadway approaches and ramp intersections  Reconstructing the US 36 bridge over the Burlington Northern Santa Fe Railway  Improving RTD stations along the corridor, including new canopies with enhanced weather protection Selection of the Design-Build Team

Proposed Phase 1 Construction Schedule (August 2012 – April 2013)

Proposed Phase 2 Construction Schedule (April 2013 – December 2013)

Proposed Phase 3 Construction Schedule (December )

Final Configuration/Completion

 Maintain all existing general purpose and HOV lanes during all phases of construction  No long-term closures  Required lane closures will be on off-peak traveling hours  Median work will be minimized  Shortened the overall duration of the project  Minimize traffic switches to improve driver familiarity  Maintain a consistent temporary traffic pattern to enhance driver expectancy Key Elements to Proposal MOT Plan

 Arterial CCTV Cameras to monitor key intersections along the diversion routes.  Deployment of two Hotspot Traffic Trailers  Additional Web page with travel information  Proposed phone application Proposed Value-Added Strategies of MOT Plan