Environmental Safety Case and Changes to Waste Acceptance Date: 25th April 2012 Dr Richard Cummings – LLWR ESC Project Manager Presentation to: Customer.

Slides:



Advertisements
Similar presentations
Best Available Techniques (BAT)
Advertisements

Regulation of Low Level Waste Management
Land Remediation Section – Environmental Management Branch Update on Contaminated Sites Changing Legislation John E.H. Ward Land Remediation Section Ministry.
ADBA PERMITTING WORKSHOP 27 March 2013 Stephen Barnes, Technical Director, Wardell Armstrong.
RIIO-T1 impact on allowed revenues and network charges 6 September 2012.
Challenges in LLW Management: a Local Government Perspective Fred Barker, Executive Director, NuLeAF SAFESPUR FORUM 29 April 2009.
1. European Commission Status GHS Implementation in the European Community Global Thematic Workshop on Strengthening Capacities to Implement the GHS Johannesburg.
Exemption, Clearance, Discharges
Branch Technical Position on Concentration Averaging and Encapsulation
© Grant Thornton UK LLP. All rights reserved. Review of Sickness Absence Vale of Glamorgan Council Final Report- November 2009.
School for drafting regulations Nuclear Safety Decommissioning Vienna, 2-7 December 2012 Tea Bilic Zabric.
Environmental Permitting Regulations Tom Fowler – Environment Officer
Time for a new standard - AS General Conditions of Contract
Date (Arial 16pt) Title of the event – (Arial 28pt bold) Subtitle for event – (Arial 28pt) Internal models Gareth Truran Head of Department, London Markets.
SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Protection of the environment from ionising radiation - views of a regulator.
PART IX: EMERGENCY EXPOSURE SITUATIONS Module IX.1: Generic requirements for emergency exposure situations Lesson IX.1-2: General Requirements Lecture.
Challenges in developing a Safety Case WG5. How to Develop a Safety Case SC can be a tool for providing information to stakeholders other than regulators.
SAFESPUR FORUM - Challenges in reducing the burden on the UK’s national Low Level Waste Repository 29 April 2009, Birchwood.
GLA REVIEW The Government’s Proposals for Additional Powers for the Mayor of London and London Assembly.
Water Seminar – 14 April 2010, Athlone European Communities environmental objectives (Groundwater) Regulations 2010 S.I. 9. of 2010 Colin Byrne Water Inspector.
NuLeAF presentation Magnox ILW strategy 14 th May 2015 May 14th
Project Tracking. Questions... Why should we track a project that is underway? What aspects of a project need tracking?
The Contaminated Land Regulations – Consolidated Review 21 September 2005 Craig Edwards.
Current and future challenges in disposing of LLW – the LLWR perspective SAFESPUR WORKSHOP 29 April 2009 Presented By: Chuck Conway, Head of Consignor.
1 IDEM Overview of March 14, 2008 Draft Antidegradation Rule Presented at the April 29, 2008 Antidegradation Stakeholder Meeting.
TBT 14: Permit Compliance HILLS’ ETHOS: IMPROVEMENT ENGAGEMENT PREVENTION ACCOUNTABILITY PROGRESSIVE FRONT FOOT ROLES AND RESPONSIBILITIES HWS – Toolbox.
Local Assessment of Code of Conduct Complaints. 2 Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due.
1 Workshop on the Directive 96/61/EC concerning (IPPC) Integrated pollution prevention and control INFRA Public participation & access to environmental.
Revision of the UNC Post-Emergency Arrangements draft proposal July 2009.
Nicolas Solente Workshop on Regulatory Requirements to Ensure Safe Disposal of Disused Sealed Sources for Operators and Regulators Amman, JORDAN 7-11 April.
IAEA International Atomic Energy Agency Summary and Overview of TECDOC Russel Edge Decommissioning and Remediation Unit Division of Radiation,Transport.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
Mats Wallin Swedish Univ. of Agricultural Sciences Dept. of Environmental Assessment Catarina Johansson Swedish Environmental Protection Agency Development.
Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
DNPC08 Review of Standard LDZ System Charges 6 September 2010.
Specific Safety Requirements on Safety Assessment and Safety Cases for Predisposal Management of Radioactive Waste – GSR Part 5.
1 10 CFR Part 61: Licensing Requirements for Land Disposal of Radioactive Waste Gregory Suber, Branch Chief Environmental Protection & Performance Assessment.
1 Modeling Under PSD Air quality models (screening and refined) are used in various ways under the PSD program. Step 1: Significant Impact Analysis –Use.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
The Permitting Process under the Pollution Prevention and Control (Scotland) Regulations Ian Halliday Senior Policy Officer.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
-1- UNRESTRICTED / ILLIMITÉ Demonstrating the Safety of Long-Term Waste Management Facilities Dave Garrick 2015 September.
Fair Go Rates System Dr Ron Ben-David Chairperson MAV Rate Capping Forum 26 November 2015.
Update on NRC Low-Level Waste (LLW) Program Activities.
International Atomic Energy Agency Regulatory Review of Safety Cases for Radioactive Waste Disposal Facilities David G Bennett 7 April 2014.
Energy Networks Association RIIO-ED1 Update for Suppliers December 2012.
Status Update on the NRC Proposed Rule to Amend 10 CFR Part 61.
Created by Decontamination and Decommissioning of UK Pharmaceutical R&D Sites: a Radiological Protection Perspective Vincent Hart, Alan S Muir* and Glenn.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
International Atomic Energy Agency V. Nys Definition and practical application of demonstration of operational and long-term safety for predisposal RWM.
National workshop Pilot testing of Guidelines for updating of national implementation plans to address the new persistent organic pollutants in Abuja,
Organizations of all types and sizes face a range of risks that can affect the achievement of their objectives. Organization's activities Strategic initiatives.
Lisa Edwards Sr. Program Manager, EPRI LLW Forum April 13-14, 2016
Proposed Revisions to 10 CFR Part 61
10 CFR Part 61 Low Level Waste Disposal Rulemaking Update
Fall Low Level Waste Forum Meeting
Kevin Motherway ESTG Meeting, 24th April 2018
Alignment of Part 4B with ISAE 3000
Revisions to the Concentration Averaging and Encapsulation Branch Technical Position A. Christianne Ridge Division of Decommissioning, Uranium Recovery,
2003 consultant contract reform agenda
Presentation to the Environmental Health Sub-committee – November 2017
Key Value Indicators (KVIs)
Sellafield Major Permit Review
Presentation to the Environmental Health Sub-committee – November 2018
Key Value Indicators (KVIs) Version 3.0
Water Framework Directive 2000/60/EC
Consumer Conversations and Aged Care Standards
Presentation to the Environmental Health Sub-committee – November 2013
EPA’S ROLE IN APPROVING BASIN PLAN AMENDMENTS
Presentation transcript:

Environmental Safety Case and Changes to Waste Acceptance Date: 25th April 2012 Dr Richard Cummings – LLWR ESC Project Manager Presentation to: Customer Forum

Presentation Objective: Discuss changes to waste acceptance arising from the 2011 ESC

Environmental Safety Case Major submission Delivered to Environment Agency on the 1 st May 2011 Available on LLWR website:

Agency Review of 2011 ESC: Current Schedule ESC delivered 1 st May 2011 Initial review: May to Jul 2011 Main technical review: Aug 2011 to Jul 2012 LLWR submit application for new permit: late 2012 Agency publish review: Mar 2013 New permit: Sep 2013 Planning permission process running in parallel

Implementation of 2011 ESC 2011 ESC approved by LLWR – believe we should implement to ensure environmental safety Required in current Permit to do so Implementing where consistent with current Permit Implementation: –As a ‘live’ safety case under change control –New waste acceptance requirements

Waste Acceptance in the ESC Waste acceptance requirements derived from assumptions and assessment results of the ESC Four workshops held with consignors in 2011

New Draft Waste Acceptance Criteria (WAC) New draft WAC based on 2011 ESC just issued for consultation along with an explanatory customer notice Rest of talk focuses on: –Background to changes –Changes to current WAC and processes –Further changes after revised permit issued

Approach ‘Within the bounds of what is environmentally safe, we have adopted an approach in the 2011 ESC that seeks to minimise, as far as practicable, the impact on consignors, whilst maximising the potential use of the LLWR for LLW disposal. It remains the case, however, that there will be significant changes required that will affect consignors.’

Most Significant Implications of ESC Requirements: 1.To control the total radiological capacity of the vaults 2.To limit and/or have emplacement controls on certain consignments due to either their activity or (potential) voidage To limit local voidage in waste stacks (and hence differential settlement of the cap) and to limit radiological impacts

Key Components Key components of the implementation of new waste acceptance arrangements: –Revisions to the Waste Acceptance Criteria (WAC) –Revisions to the Waste Acceptance Process –Introduction of a revised Inventory Control Process –Introduction of an Emplacement Strategy to manage certain consignments

Changes to Current WAC and Processes Putrescible materials Waste degradation and settlement Non-radiological materials Asbestos Total radiological capacity Specific activity of consignments Activity heterogeneity Fissile radionuclides

Putrescible Materials One percent limit by volume May accept more if supported by: –BAT assessment –Assessment of potential health implications

Waste Degradation and Settlement Controls required to limit cap settlement Use of BAT to limit potential voidage Combined control on inaccessible, compression and biodegradation voidage Total potential voidage not to exceed 20% unless agreed in advance

Non-radiological Materials Hazardous Waste, Hazardous Substances and Non- Hazardous Pollutants In discussion with Environment Agency on impact assessment and acceptance Such materials will only be accepted following approval of a Waste Consignment Variation Form Will allow us to implement changes at an appropriate point

Asbestos The ESC proposed that asbestos wastes should be excluded unless treated or conditioned to produce a form that would be acceptable if released during coastal erosion Work underway to refine our approach to implementing this proposal Asbestos will only be accepted following approval of a Waste Consignment Variation Form Will allow us to implement changes at an appropriate point Environment Agency is considering its position on the disposal of asbestos at the LLWR

Total Radiological Capacity Will control total repository activity through allocations of capacity by waste stream Allocation at characterisation stage Waste streams will be rejected if exceed or use disproportionate amount of remaining capacity Remaining capacity analysis will take into account expected future disposals based on UKRWI Checks against allocation will be made at consignment stage

Specific Activity of Consignments Need to limit specific activity of individual consignments using a ‘sum-of-fractions’ inequality Approval of a waste consignment via a Variation Form where sum of ratios of specific activities of individual radionuclides and their trigger levels (specified in WAC) exceeds one Will need to be supported by a strong BAT case

Activity Heterogeneity Explicit criterion added to follow regulatory guidance Reasonably practicable measures to limit items of waste to below the 4 and 12 GB/t LLW limits

Fissile Radionuclides Relaxed conditions on reduced set of nuclides No limit on mass of graphite in a consignment

Importance of Accurate Consignment Data ‘Provision by consignors of accurate data on activity, materials and potential voidage for individual waste consignments (rather than averages for waste streams) will be essential.’

Changes to Come Relating to asbestos Relating to non-radiological hazardous materials Refined approach to complexants Revised controls on sealed sources Arising from revised permit

Complexants Potentially enhance mobility of radionuclides Present in decontamination agents Under current Permit, can only accept with written permission – will be issuing guidance to help with identification ESC proposed accepting non-persistent types (at low concentrations) Working to justify non-zero quantitative limits on all types Will be consulting with consignors on use and waste characterisation

Sealed Sources ESC proposed relaxing limits on some radionuclides in sources previously agreed with Agency Hope to implement changes under revised permit

Conclusions New waste acceptance requirements arising from 2011 ESC being implemented Implementation phased Significant changes affecting consignors New draft disposal WAC issued for consultation We want to engage with consignors to ensure changes are as practical as possible whilst protecting repository capacity and safety 24