Superior Solar Conjunction Planning May 8, 2014 Dan Ossing STEREO Mission Operations Manager (240) 228-8319.

Slides:



Advertisements
Similar presentations
PLATO Phase A/B1 Status TOU Meeting Catania 28 Feb 2011 PLAnetary Transits and Oscillation of stars.
Advertisements

Comprehend the Challenger accident Comprehend the Columbia accident The Space Shuttle Program: Challenger and Columbia Accidents.
Chandra X-Ray Observatory CXC Paul Plucinsky CUC September Overall Status of the Instrument 2.Update on Controlling the FP Temperature ACIS Ops.
SECCHI – Sun-Earth Connections Coronal and Heliospheric Investigation SECCHI Synoptic and Special Observing Programs Simon Plunkett SECCHI Operations Lead.
2007 March 61 The SECCHI Campaign Jean-Pierre Wuelser SECCHI Consortium Meeting Orsay.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
GLAST LAT ProjectISOC CDR, 4 August 2004 Document: LAT-PR-04500Section 4.11 GLAST Large Area Telescope: Instrument Science Operations Center CDR Section.
Page 1HMI Team Meeting – January 26, 2005 HMI Mission Operations Rock Bush HMI Stanford Program Manager Stanford University
DAO March of 9 STEREO Unattended Track CONOPs Review March 27, 2007 Daniel Ossing THE JOHNS HOPKINS UNIVERSITY.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
Technological Design STS-118 Lunar Plant Growth Chamber Challenge © 2013 International Technology and Engineering Educators Association STEM  Center for.
EECS 823 MACHARIA.  Four-frequency, linearly-polarized, passive microwave radiometric system which measures atmospheric, ocean and terrain microwave.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
NASA’s Goddard Space Flight Center LRO Operations Concept Richard Saylor Jr. HTSI/Code 444 August 16-17, 2005.
SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA Cosmic Origins Spectrograph Hubble Mission Status Review Charles D. (Tony) Keyes Last Review:
“Joint planning” session Preliminary instrument operation & science plans of SOT/XRT/EIS for several months after the launch. Instrument checkout and Performance.
20a - 1 NASA’s Goddard Space Flight Center Attitude Control System (ACS) Eric Holmes, Code 591 Joe Garrick, Code 595 Jim Simpson, Code 596 NASA/GSFC August.
Van Allen Probes Spacecraft Operations July 29, 2015 Kristin Fretz
University of Wisconsin System HRS Project Update to ITC November 19, 2010.
STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project.
SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA COS Monthly Status Review 20 October 1999.
Spacecraft and Ground Segments Status March 21, 2014 Dan Ossing STEREO Mission Operations Manager (240)
Consortium Meeting La Palma October PV-Phase & Calibration Plans Sarah Leeks 1 SPIRE Consortium Meeting La Palma, Oct. 1 – PV Phase and.
SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA Hubble Mission Status Review Charles D. (Tony) Keyes Last Review: 10 June August 2003.
STEREO Science Center Status Report William Thompson NASA Goddard Space Flight Center STEREO SWG April 2008 Meudon, France.
TREADS Semester Review Dec. 14, Objectives Assess and Communicate Current Design Identify interfaces Approve the System Requirement Specification.
1 Mission Discussion & Project Reviews 祝飛鴻 10/14/93.
GLAST Science Support CenterNovember, 2005 GSSC User Committee Meeting Tools for Mission and Observation Planning Robin Corbet, GSSC
SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA COS Monthly Status Review 15 January 2002.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
Deep Impact FRRJan. 8, 2005Page 1 Deep Impact Overview/Status Flight Readiness Review January 8, 2005 Rick Grammier Project Manager.
STEREO - Solar Terrestrial Relations Observatory Mission SECCHI Calibration Activities Simon Plunkett SECCHI Operations Scientist Naval Research Laboratory.
1/15/02Bowman/Harch1 CONTOUR Science Ops Update Ann Harch Cornell University (607) Alice Bowman Applied Physics.
Telemetry Constraints during Early Operations The STEREO telemetry rate is restricted during the phasing orbits due to S/C RF interference with each other,
Mission Operations Review February 8-10, 2010 Cordoba, ARGENTINA SECTION 16.x Aquarius Science Commissioning and Acceptance Draft 2 Prepared by: Gary Lagerloef,
Final Version Kequan Luu May 13-17, 2002 Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF) Flight Software.
LISA News from ESA O. Jennrich LISA Project Scientist.
1 Browser Compatibility Assessment June 2 nd, 2015.
JWST Mission CDR Northrop Grumman Space Systems Redondo Beach (CA) April 10-16, 2010.
SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA Cosmic Origins Spectrograph Hubble Mission Status Review Charles D. (Tony) Keyes Last Review:
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
1 EOS Aqua Mission Status at AMSR Science Team Meeting September 16, 2015 Huntsville, Alabama Bill Guit Aqua/Aura Mission Director - Code 584 phone
23-Nov-1999STScI Projects Monthly Status Review1 of 8 SpaceTelescopeScienceInstitute COS Status Report for period December, 1998 to November, 1999 Tony.
NMP / EO-1 NMP EO-1 LE&O HANDBOOK September 24-26, 2000 Section 1 Master Timeline (Day 1-10)
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR Section 5 IOC Subsystem 1 GLAST Large Area Telescope: IOC Subsystems WBS: 4.1.B.
Jan 2008 LMSSC - 1 SWEA Plume Impingements Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission.
GIST Meeting 5 February MSG-1 - PROGRAMME STATUS Presentation to the GERB GIST/PSG meeting.
IMPACT Conjunction and Sidelobe Operations Janet Luhmann, Dave Curtis, Peter Schroeder, Dick Mewaldt and the IMPACT Team July 2, 2014.
Welcome to Uppsala! Thursday May 18 13:00, room Å :00 Coffee (17:30 Dinner) Friday May 19 09:00, room Å :00 Coffee splinters (other locations)
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Progress report of the tilt monitor Daisuke OKAMOTO Tohoku University.
Van Allen Probes VAP Spacecraft and Programmatic Status Ed Reynolds
Pre-landing Orbiter Observations
CINEMA System Engineering
GLAST Large Area Telescope:
Mini-RF Requirements Overview
Baseline CPT Test Baseline CPT Testing June 2017 Mission Simulation 2
Team Thumbs Up Final Presentation
Current SOC-Ground System Integration Schedule (Jan )
Level 2 Requirements (MRD)
Integration, Test, and Calibration
SDO Flight Dynamics Subsystem
Thermal Vacuum Test: Plans and Procedures
Launch and On-orbit Checkout
LAT Operations Scenario Subsystem Meetings
EagleSat 2 – Mission and Development Overview
GLAST Large Area Telescope
Instrument Commissioning SDO SOWG - January 18-19, 2007 Purpose/Goal:
Observation and Checkout Modes (1) - Introduction -
Presentation transcript:

Superior Solar Conjunction Planning May 8, 2014 Dan Ossing STEREO Mission Operations Manager (240)

2 Spac e Agenda  HGA Feed Temperature Constraint  Schedule  Key Dates

3 Spac e HGA Feed Temperature Constraint  HGA feed will increase in temperature beyond acceptable limits with SPE angle below 6.5 degrees.  If SPE angle exceeded, damage to the feed assembly will render the HGA unusable.  Thermal modeling and analysis in progress –Results due by the end of May –Not done before launch as the mission was only two years.  Off point HGA to prevent excessive heating  Keep feed temperature below 125 deg C –Temperature sensor limit = 136 deg C –Damage 150 deg C (adhesives)  AHEAD – September 2014 through December 2015  BEHIND – November 2014 through January 2016  At this time, anticipating instruments will off for these durations due to low data rates  Investigating HGA side lobe for low data rate communications  Testing on May 10 th (AHEAD) and May 17 th (BEHIND)

4 Spac e HGA Feed Assembly

5 Spac e HGA Auto Track Low Data Rates (155 days) HGA Nominal Rates STEREO AHEAD Timeline Schedule - DRAFT Reviews FP Readiness MOps Readiness Test on S/C Months Solar Conjunction Readiness Date SPE (deg) 9/ / /24 2 5/20 0 7/7 2 12/ /9 6.6 Post Solar Conjunction Assessment Activities Load C&DH FSW Load Parameters Load MOps Macros & FP & Set EA Bypass Test on S/C HGA on Side Lobe Instrument Power Down & SSR Reconfiguration Rehearse w/ DSN Solar Conjunction No Communications (105 days) HGA on Main Lobe SSR Playback & Reconfiguration & S/C Checkout Instrument Power on & Recommissioning HGA Calibration S/C Config 3 axis & Op Mode Rotate 3 axis & Op Mode 3 axis & Standby Mode (198 days) 5 deg/min HCLT Reset Every 3 days (105 days) 3 axis & Standby Mode (155 days) 3 axis & Op Mode RF HGA Nominal Rates HGA Low Rates HGA Auto Track Low Data Rates (198 days) HGA Nominal Rates DSN Nominal Tracks Nominal Tracks 70m, 3 hrs 70m, Daily 3 hrs (198 days) Nominal Tracks No Coverage (105 days) 70m, Daily 3 hrs (155 days) Nominal Science Instruments Nominal Science All Instr. off Instruments Off (~469 days) Nominal Science HGA Calibration No Communications (105 days)

6 Spac e HGA Auto Track Low Data Rates (64 days) 5 deg/min HCLT Reset Every 3 days (60 days) HGA Nominal Rates STEREO BEHIND Timeline Schedule - DRAFT Reviews FP Readiness MOps Readiness Test on S/C Months Solar Conjunction Readiness Date SPE (deg) 11/ / /22 2 2/19 0 3/23 2 1/ / Post Solar Conjunction Assessment Activities Load C&DH FSW Load Parameters Instrument Power Down & SSR Reconfiguration Rehearse w/ DSN Solar Conjunction No Communications (60 days) Instrument Power on & Recommissioning HGA Calibration S/C Config 3 axis & Op Mode Rotate 3 axis & Op Mode 3 axis & Standby Mode (295 days) 3 axis & Op Mode RF HGA Nominal Rates HGA Low Rates HGA Nominal Rates DSN Nominal Tracks Nominal Tracks 70m, 3 hrs 70m Daily 3 hrs (64 days) Nominal Tracks No Coverage (60 days) 70m, Daily 3 hrs (295 days) Nominal Science Instruments Nominal Science All Instr. off Instruments Off (~432 days) Nominal Science HGA Calibration Test on S/C SSR Playback & Reconfiguration & S/C Checkout No Comm (60 days) 9/24 2 HGA on Main Lobe HGA on Side Lobe 3 axis & Standby Mode (64 days) HGA Auto Track Low Data Rates (295 days) Load MOps Macros & FP & Set EA Bypass

7 Spac e Key Dates EventAHEADBEHIND HGA side lobe test5/10/145/17/14 LGA calibration test6/8/145/23/14 Load C&DH FSW to EEPROM Copy 15/20/14 Load G&C and C&DH parameters to EEPROM5/28/14 Load MOps macros & FP releases to EEPROM6/10/14 MOps Readiness for S/C Testing Review6/19/149/18/14 S/C Testing – Instruments off/on7/7 thru 7/15/149/29 thru 10/6/14 HGA Calibration – Pre-conjunction7/23/14 Load C&DH FSW to EEPROM Copy 27/28/14 Solar Conjunction Readiness Review8/14/1410/23/14 Instrument Power Down & SSR Reconfiguration9/2/1411/14/14 Rehearse with DSN9/5/1411/16/14 HGA on Side Lobe9/7/1411/19/14 Superior Solar Conjunction3/24 thru 7/7/151/22 thru 3/23/15 HGA on Main Lobe12/9/151/12/16 SSR Playback & Reconfiguration & S/C Checkout12/10/151/13/16 Instrument Power on & Recommissioning12/15/151/18/16 HGA Calibration – Post-conjunction1/27/16 Post Solar Conjunction Assessment Review3/16

9 Spac e Three Laws of STEREO Solar Conjunction 1.Take all reasonable precautions to keep the observatory safe. Of course, “reasonable” is subject to interpretation and judgment. We will be guided by the usual risk assessment methodology of weighing both probability and impact, which is, after all, the implicit thinking behind “engineering judgment.” 2.Return to normal science operations as soon as reasonably possible. In cases where this law conflicts with the First Law, the First Law takes precedence. There’s that word “reasonably” again. We do not have infinite time and manpower to prepare for conjunction. So, some management judgment is required. 3.Conduct science operations during conjunction, if reasonably feasible. In cases where this law conflicts with the first two, the first two laws take precedence. We do not have infinite time and manpower.