MICE CM15 wrap-up Alain Blondel 11 June 2006 1 MICE CM 15 wrap-up Collaboration meeting 8-11 June 2006 at Fermilab complete review of the project. thanks.

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
DAQ WS03 Sept 2006Jean-Sébastien GraulichSlide 1 Wrap Up o Control and Monitoring o DDAQ o Interface between DDAQ and MCM o Infrastructure Jean-Sebastien.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Changing the absorbers: how does it fit in the MICE experimental programme? Besides the requirement that the amount of multiple scattering material be.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
CHIPP Sept 2005Jean-Sébastien GraulichSlide 1 What is MICE  Muon Ionisation Cooling Experiment  What is Ionisation Cooling ? Cooling = Reduction of Beam.
Paul drumm daq&c-ws august/september Cooling Channel.
Alain Blondel MICE: Constraints on the solenoids 2.Field Homogeneity: or ? this will be dictated by the detector requirements. TPG will be.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
MICE CM15 Alain Blondel 8 June MICE CM 15 Collaboration meeting 8-11 June 2006 at Fermilab complete review of the project. today: -- reviews and.
MICE analysis meeting Alain Blondel 5 August MICE -- what running strategy? disclaimer: of course we will evolve the running strategy as problems.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MICE CMPB 3-Feb-2006 Alain Blondel 1 Status of MICE.
1Malcolm Ellis - Software Meeting - 31st May 2006 Data Challenge Requirements  First list of requirements, based on Yagmur’s document: u
DPNC Sept 2007Jean-Sébastien Graulich MICE The international Muon Ionization Cooling Experiment o o Introduction o o Beam Line o o Cooling Channel o o.
CMPB Alain Blondel 14 April STATUS OF MICE.
1 EMCal design MICE collaboration meeting Fermilab Rikard Sandström.
MICE Video meeting Alain Blondel 7 December MICE -- what running strategy? reflections on steps I and II.
17 March 2005Edda Gschwendtner1 MICE Cooling Channel: Can we predict cooling to ? Edda Gschwendtner Challenge Systematics Cooling Channel Beam Line.
Progress on the MuCool and MICE Coupling Coils * L. Wang a, X. K Liu a, F. Y. Xu a, A. B. Chen a, H. Pan a, H. Wu a, X. L. Guo a, S. X Zheng a, D. Summers.
Spokesmouse’s News Agenda: o VC 22nd April o 12th-13th May posters for EPAC (Vittorio Palladino) o VC 20th May o VC 17th June o CM27 (RAL) 7th-10th July,
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE CM Alain Blondel 1   MICE GOALS OF THE MEETING Welcome to MICE CM28.
MICE CMPB Alain Blondel 19 April spokesperson remarks CMPB MICE NEWS.
MICE CM15 wrap-up Alain Blondel 11 June MICE News Collaboration meeting 8-11 June 2006 at Fermilab complete review of the project. for those who.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
MICE collaboration meeting Alain Blondel 27 – Welcome to the 10th MICE collaboration meeting. 1.Global neutrino factory situation 2.Possible.
MICE CM in New York Alain Blondel, June MICE COLLABORATION Columbia University June 2003 Action List (online) 1.Funding and some organization.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006.
Alain Blondel – introduction MICE CM Collaboration meeting June 2007 at RAL Complete review of the project Organization of efforts towards.
Sci-Fi Tracker: Progress Report Malcolm Ellis, MICE Video Conference Wednesday 6 th October 2004.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Takashi Matsushita Imperial College T. Matsushita 1 MICE Status Excerpt from talks at MuTAC review:
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MCTF 8/17/06 A. Bross MTA Activities and Plans MCTF August 17, 2006 A. Bross.
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE CM16 Goals Alain Blondel 8 October MICE CM 16 Collaboration meeting 8-11 October 2006 at RAL Goals of the meeting thanks to John Cobb & Marco.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
MICE RF Workshop Alain Blondel MICE = critical R&D for neutrino factory and muon collider 1 neutrino factory: accelerate muons and store to produce.
1M. Ellis - NFMCC - 31st January 2007 MICE Analysis.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
MICE CMPB Alain Blondel 1 Highlights on MICE.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
MICE VC Alain Blondel MICE News 9 March 2005 we did not succeed in preparing a good enough I3 proposal for EU on neutrinos. Problems were.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
- MICE - The Muon Ionization Cooling Experiment Jean-Sebastien Graulich, Univ. Genève o Introduction: Aims And Concept o Design o Infrastructure: Hall,
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
MICE CM32 Goals of the Meeting Alain Blondel 1 WELCOME TO MICE CM32! – Goals and Status - Many thanks to Victoria Blackmore, Stefania Ricciardi and Mary-Elizabeth.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
ch/~bdl/lepc/lepc.ppt 1 MICE Status and Plans Rikard Sandström Université de Geneve International Scoping Study CERN,
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
CHIPP Oct 2007Jean-Sébastien Graulich Status of MICE Jean-Sebastien Graulich, Univ. Genève o o Introduction o o Beam Line o o Technical Design o o PID.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
(one of the) Request from MPB
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
MICE VC Alain Blondel, April MICE exectutive board met on 1 April 2004 after the collaboration meeting and remarked the very large amount of.
MICE news Alain Blondel 20 – NEWS 1.CERN’s SPSC at Villars: recommandations 2.MICE step Upcoming gateway steps 4.RF from LBNL (Mike)
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
Presentation transcript:

MICE CM15 wrap-up Alain Blondel 11 June MICE CM 15 wrap-up Collaboration meeting 8-11 June 2006 at Fermilab complete review of the project. thanks to Alan Bross, Malcolm Ellis, Jean-Sebastien Graulich and Jim Norem for organisation of the meeting and agenda and Dinner! Wrap up was much helped by ‘what can go wrong’ session… self evaluation is very efficient! should follow-up! Please comment and complete as I go along!

MICE CM15 wrap-up Alain Blondel 11 June STEP I: 15 September 2007 = 460 days away! STEP II: soon after PHASE I  MAIN GOAL of meeting: Understand where we stand in our preparations for Steps I and II. -- beam line: target, optics, tuning and correction abilities, diffuser -- TOF, Cherenkov1, EMCAL (size of shield&TOF2&EMCAL must be decided) -- tracker -- spectrometer solenoid -- installation and cabling -- controls and monitoring -- trigger, DAQ and event processing -- software: upstream and downstream particle ID, reconstruction of tracks -- analysis: form run plan, reconstruction of « beam», emittance, transmission

MICE CM15 wrap-up Alain Blondel 11 June Target Clearly the highest risk issue in MICE review tomorrow Much progress and growing team! The depth of dip will be carefully written on data stream… Precious for understanding of rates, etc.. Issues raised: -- heating problem when exciting to 40A (instead of presently 5 A) ==> personnally believe that redesign may be necessary to include more-than-adequate cooling system -- avoid that failure leads to target stuck in beam! + should have a fool-proof indicator that target is in beam position. Not obvious that test in October will be able to be performed with final system. How far from it will it be? Will it address enough critical issues?

MICE CM15 wrap-up Alain Blondel 11 June Beam Line and Optics Want to see the full performance matrix: Still needed before in-hall final design and construction begins and a few more features: correctors, (can we adjust five parameters with four magnets?) collimators, are they needed for the small emittance beam? diagnostics (any?) review tomorrow much progress in engineering

MICE CM15 wrap-up Alain Blondel 11 June CKOV1 Louvain-Mississipi collaboration Design will allow improved separation between muons and pions in the high momentum range. two units needed. ( and ) yes/no but also pulse height? beam test at fermilab this summer, will be ready for MICE start-up.

MICE CM15 wrap-up Alain Blondel 11 June TOF Ennoying questions: TOF2 said to be mid Can this be brought forward? what will happen with x-ray radiation when we run with RF? Issue: particles crossing material in the downstream end of the spectrometer this is a beam of MeV/c, all generated with 4T field in spectrometer. How about the size of the hole in the shielding Preparations of TOF0 test on-going (Milano-Pavia) double layer allows measurement of resolution, meast is of this is the main aim of the test

MICE CM15 wrap-up Alain Blondel 11 June EMCAL fully Active Scintillator upgraded simulations show much better performance eff 99.90% -> rejecting 97.7% wrt Osaka: to be verified for the whole matrix and for the non-flip mode. SIZE is the matter now! New design Intense preparation in Roma3 for the testbeam in July

MICE CM15 wrap-up Alain Blondel 11 June Tracker excellent review passed in April ! KEK beam results: alignment to a few tens of microns very precise metrology! (see how pitch was measured! -->) still some to be understood (chi2?) residuals in # channels channel number Production of final tracker 1.QA will be very careful to avoid misalignment (loss of light) and channel garbling that occured previously: planning: QA verified on earlier stations 5th station starting mid-august evaluation by mid september then start production

MICE CM15 wrap-up Alain Blondel 11 June Spectrometer Solenoid conductor purchased and accepted. Final vendor selection nearly complete Procurement contract expected to be placed before the end of June --> delivery expected end-summer (how about second solenoid?)

MICE CM15 wrap-up Alain Blondel 11 June DAQ and monitoring two connected issues Controls and Monitoring: Basic system with EPICS. The use of Hytec 9010 IOC and IP modules is recommended for most applications. Two such IOC systems already procured for target (sheffield) and for H2 system (at RAL) More complex systems may require VME interface DAQ Will acquire the particle-generated signals and data. global « spill trigger » + still needs a particle-based trigger (supp. TOF0+TOF1) Based on ALICE software DATE will record at every spill the system data required for analysis (list should be established of a minimum sufficient set of such data) Final electronics choices and DAQ modules will be proposed at RAL meeting in october

MICE CM15 wrap-up Alain Blondel 11 June AFC module Cryocoolers GM or PT???? that is the question. We will for sure have a mixed system since tracker cryo uses GM and spectrometer solenoid uses PT. Any advantage in unification? Sensitivity to magnetic field to be tested/understood for both. Beautiful field calculations by H. Whitt Absorbers Situation was very advanced in much slowed down by interruption of ICAR funding a number of issues remain (i.e. QA of production windows, for instance) … and production of course. A problem to be solved LH2 Safety & HAZOP response to safety document will be finished well before next CMPB! HAZOP document (impressive) almost final 22 recommandations! which to implement? working group-->collab --> TB review. what will be the users interface? (only instructions on how to respond to alarms and phone experts?)

MICE CM15 wrap-up Alain Blondel 11 June G-10 Support Absorber & Pipes Mini In-Flange 30 Pin Feedthrough Tee  L-H2 IN G-H2 OUT He/N2 OUT He/N2 IN Ishimoto slight changes and improvements to the design. <-- Instrumentation, feedthroughs.. being worked out. Indication of cooling time to be 57 h -- better solution for convection to be found New development of two phase hyperfluid He cooling, big jump in conductivity (>10 orders of magnitude)

MICE CM15 wrap-up Alain Blondel 11 June RF cavities 200 MHz cavity powered and first measurements made, including effect of stray magnetic field (multipactor!) measurements of background rates are about to begin B=0 or stray field (up to 1.25 T). will constitute precious normalization for simulations (the level of V at which we run will be determined by RF power limit or Bkg hit limit whichever is smallest) 5 ports have been foeressn to identify electron sources

MICE CM15 wrap-up Alain Blondel 11 June RF power LBNL: Two “4MW” + three “300kW” systems shipped to DL Strip down and rebuild as a test stand CERN: Two “3MW” systems available at CERN Request to CERN to refurbish DL/RAL: New B4616 tubes (1 working LBNL tube) New TH116 tube bases (purchase in time) New kW power supplies (Dressler) MICE should have 201 MHz available by 2008 given possibility to run with L.N2 re-acceleration by ~34 MV should be available from two RFCC modules aim at having it all working by end of 2007

MICE CM15 wrap-up Alain Blondel 11 June Physics and analysis aligment of magnetic axis of exeriment electric field (Li): measurement of pulse amplitude vs time + phase for each cavity master clock? LH2 thickness (measurement of absorber warm shape vs pressure) LH2 density from pressure and temperature measurements OK OK (< ) for L. H2 and most solids. Marginal or difficult for LiH and He channel transmission measurement (Marco Apollonio) --> trigger must be based on TOF0 + TOFI (not TOFII) so that T= muons in tracker 2/ muons in tracker 1 can be measured. PID performance (Sandström) much improvement must be turned into a user friendly package before RS flies away! tuning on data? Measurement of longitudinal emittance (Rogers) issues with minimizing the effect of propagation of tracker precision measurement of tracker resolution will be very important (step III) Very important to keep all acceptance. still needed; run plan + note on TOF2 need Software is in great progress… Interface with engineering reference system to be envisaged (so that we simulate what is built) (or at least that we think that we simulate what we think is built)

MICE CM15 wrap-up Alain Blondel 11 June

MICE CM15 wrap-up Alain Blondel 11 June

MICE CM15 wrap-up Alain Blondel 11 June PHASE II discussion main issue: accelerator physics case for MICE PHASEII. Q: why do we test study II cooling cell rather than the (simpler one) of Study Iia, or the ISS recommended one or the more powerful one of Muons Inc..? A1: The MICE hardware is very mature and ready to construct and test -- in fact it is the only one in that state, other possibilities (such as study IIa,b, or ISS recommended) a re not studied and designed quite yet. A2: Equipment that MICE builds is not only useful to test Study II cooling channel, it (in particular AFC module) has flexibility for many other optics or absorber materials, and MICE is precise enough to evaluate small expected (and unexpected) differences between them. A3: The RF modules are absolutely essential in demonstrating the fact that beam can be reaccelerated, in all cooling systems envisaged.

MICE CM15 wrap-up Alain Blondel 11 June or: of MICE and MANX MANX LOI was submitted in may 2006 to Fermilab MANX is a cooling system based on a helicoidal focusing channel a very challenging magnet (3-5m long SC) around L.He. absorbers. Claim of 500% cooling (vs 10% for MICE) incl. long. emittance reduction. It is suggested that MANX can eventually be tested in the RAL muon beam, using the spectrometers and diagnostics of MICE Caveats: -- the matching of all this has not been completely demonstrated -- the gauge ‘how much beam is cooled’ may not be the same between MANX LOI and MICE -- re-acceleration of muons after such cooling requires matching to RF cavity modules such as those of MICE -- not demonstrated either -- MICE is an approved experiment (this was hard enough!) and will be completed as proposed Given these caveats, we certainly support MANX and wish it success, as a possible follow-up on MICE. Looking forward to fruitful collaboration « PHASE III: »

MICE CM15 wrap-up Alain Blondel 11 June MANX minimal step (no RF) (T.Roberts)

MICE CM15 wrap-up Alain Blondel 11 June To be achieved by next CM meeting at RAL: (incomplete to-do list) target and beam line solutions to be found for several target problems: 1. heating at high drive current ? would like to see an engineering design ready for target test in October organize tour of target at CM :-) beam line pending issues correctors verify all the optics we want status report VC end of July check the diffuser (a small edge effect at 200 MeV/c) (resp of Tracker group) check also the scraping at the downstream end! -->He window and radiation shield are also responsibility of tracker! Magnetic shield 2 could be responsibility of TOF group --> Palladino Response to H2 safety committee decisions on HAZOP interim report TB end of July. review in September Decisions on cryocoolers to be placed on agenda of TB to be followed to Exec. Board (Decision is said to be: Pulse Tube for everything except the VLPC cryostat) blue/red = exec-board comment or decision

MICE CM15 wrap-up Alain Blondel 11 June Test beam in Frascati! Finalize downstream PID size and shield setup (VC in 19 july) Study issue of RF x-rays to TOF --> on Yagmur Production of first ‘final’ tracker station progress report in september Finalize DAQ scheme report after test beam i.e. August Understand precisely the schedule of Spectrometer solenoids report on 19 july what happens from delivery in US to operation in RAL Submission of UK Phase II bid First engineering study of CC by Harbin VC in July Launch MICE data challenge! --> on Yagmur To be achieved by next CM meeting at RAL: (incomplete to-do list)

MICE CM15 wrap-up Alain Blondel 11 June MICE SCHEDULE modification since OSAKA: -- ISIS schedule shift -- excellent news from spectrometer solenoids (being ordered!) -- better news on coupling coils (MUCOOL coil, from DOE; MICE coils, from Harbin ICST)

MICE CM15 wrap-up Alain Blondel 11 June MICE schedule as could be found in the proposal (january 2003)

MICE CM15 wrap-up Alain Blondel 11 June MICE proposal: January 2003 MICE approval: March 2005

MICE CM15 wrap-up Alain Blondel 11 June  - STEP I: April 2007 STEP II: October 2007 STEP III: 2008 STEP IV: 2008 STEP V 2008? STEP VI 2009? implementation in steps physics-based: understanding of systematics all configurations successfully matched optically PHASE I PHASE II MICE schedule in Frascati June 2005

MICE CM15 wrap-up Alain Blondel 11 June  Aspirational MICE Schedule now (reasonably optimistic as always) 15 September 2007 NB: picture does not include target, beam line, hall infrastructure, electronics, DAQ, shifters etc… ! STEP I 15 November 2007 STEP III: Winter 2008 STEP II STEP IV Fall 2008 STEP V Spring 2009 STEP VI Fall 2009

MICE CM15 wrap-up Alain Blondel 11 June A few Uncertainties (or risks) as I see them (please complete!) 1. Will target be ready and operating? 2. Will PSI solenoid resurrect? 2. Will EMCAL be ready on 15 september 2007? 3. Will TOF2 be ready end 2007? 4. Will MICE UK Phase II bid be approved? 5. Will a solution be found to finish absorber body and windows R&D and construction? 6. Will Harbin funding request come through? etc… How will MICE survive when Chris and Rikard have finished their thesis? How will we man/woman the shifts? These will be three years of intense activity: are there going to be enough of us?

MICE CM15 wrap-up Alain Blondel 11 June CONCLUSIONS 1. This has been an extremely sucessful meeting, excellent and well prepared talks described lots of work 2. so much is happening in MICE! 3. ***460 days*** to data taking 4. We are welcoming new collaborators and having an increasing (still very cautious!) confidence in the schedule! 5. Both ‘done’ and ‘to-do’ lists are growing fast… 6. See you many at RAL, 8-12 october 2006!