Delhi Metro A Project Management Bench Mark Presentation By Kumar Keshav Director (Project &Planning), DMRC 23 rd June, 2011.

Slides:



Advertisements
Similar presentations
INDEPENDENT WATER SCHEMES IN SAMOA
Advertisements

DaZee Hotels (Management & Allied Services)
Quality Management Training Quality circles Bench Mark Kaizen.
Enable Procurement Agencies to Fulfill their Roles Push Smooth Implementation of Project Procurement Foreign Debts Management Center, Hebei Provincial.
NETLIPSE Infrastructure Project Assessment Tool Professor Hans-Rudolf Schalcher, ETH Zürich Amsterdam, 21 April 2009.
Guidelines for “Central Sector Scheme for Salvaging & Rearing of Male Buffalo Calves” GoI has introduced a Centrally Sponsored Scheme called.
12-May-151 Khan Younis Waste Water Treatment Plant Management Arrangements Khan Younis Waste Water Treatment Plant Management Arrangements.
Contractor Safety Management
Briefing on Cape Town’s Integrated Rapid Transit System 2009.
1 Alignment to the Local Government Turn Around Strategy (LGTAS)
ATAL INDORE CITY TRANSPORT SERVICES LIMITED (AICTSL) Performance Management System Madhav Pai Prajna Rao Srinivasan Vasudevan.
Financial Management and Auditing First Level Controls 3 rd round operations Rostock, Elise Oukka.
Spring 2008, King Saud University Engineering Administration Dr. Khalid Al-Gahtani 1 What is a Project? “A Project is a one-shot, time-limited, goal- directed,
 PPP Projects ◦ Re structuring of Brownfield Airports (Delhi & Mumbai Airports) ◦ Greenfield Airports (Hyderabad & Bangalore Airports)  AAI Projects.
HOSPITALITY MANAGEMENT Ch. 16 HS. THE GENERAL MANAGER  General Manager – is a person responsible for the entire operation of one unit of a hospitality.
PROCUREMENT PLAN States should prepare Procurement Plan for the entire outlay approved by the PAB for the State Component and all the Districts. The Procurement.
Regional Policy ESIF : Technical Assistance Platform for financial instruments (TAP) DG Regional and Urban Policy, Unit B.3 Financial Instruments,
Process Engineer’s Role in Project Management Dr Abdullah Malik.
‘SIDF’s role in Development of Industrial Sector in Saudi Arabia’ By Ali Al-Dhalaan 8th Rajab, /05/2012.
WHAT IT TAKES TO BECOME A RESPECTED PROPERTY MANAGER & SUBJECT MATTER EXPERT Robert J McFarland CPPM/CF 1.
08/2009 The Benefits of Mentoring. Mentoring Mentoring has evolved in the workplace to be less about bosses grooming their handpicked successors to being.
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
Project Management. Managing Capital Projects  What is a Project?  Something that: has a beginning and an end, and is carried out to meet established.
Peter Defranceschi ICLEI - Local Governments for Sustainability An Introduction European Commission GPP Training Toolkit.
Jawaharlal Nehru National Urban Renewal Mission JNNURM PROGRESS REVIEW JUNE 2007 Reforms-Projects-Funds Mobilisation & Grant Utilisation State:- Goa City:-
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
The role of ERE in Costumer Protection Eduard Elezi Albanian Regulatory Authority ERE Conference “Albanian Energy Sector, Challenges and Regulation” Tirana,
Chapter 11 – Managing a Business
1 INTERREG IIIB “ATLANTIC AREA” Main points of community regulation 438/2001 financial management and control systems EUROPEAN COMMISSION SPAIN.
New Decade - New Challenges Annual Conference September 2010 Water Services Training Group 14 th Annual Conference New Decade – New Challenges 9 th September.
SOLAR POWER, A SUSTAINABLE ENERGY SOURCE AN INITIATIVE OF DMRC, AT DWARKA METRO SECTOR – 21 STATION By: Anoop Kumar Gupta Director/Electrical/DMRC Mahendra.
Report of the Comptroller and Auditor General Of India For the year ended 31 March 2000 Removal of Garbage and Sanitation Work Government of National Capital.
Donald R. Rainey, Sr., CPPB/VCO Director, Office of General Services Virginia Department of Social Services.
James Aiello PricewaterhouseCoopers Africa Utility Week 06 International Good Practice in Procurement.
STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February Briefing by Department of Water Affairs.
An Introduction to World Bank Organization and Operations Jean-Charles Crochet Senior Transport Economist World Bank.
Project Information Brief project description Cairo, Egypt Bus Rapid Transit System with potential capacity of 45,000 people per person per direction Phase.
AIRPORT SHUTTLE SERVICE. Survey Objectives Demand assessment Finalization of routes Finalization of station locations Fare Structure.
PUBLIC PURCHASING IN FLORIDA ROLES IN THE PURCHASING PROCESS (rev. 05/27/2008)
DELHI METRO TRAINS {A BOON FOR ALL} Advertise inside the Swank Passenger Cabins through Inside Panels & Handle Bars Delhi’s Pride A Metro Ride.
Management Skills.
SOLAR ROOF-TOP is A necessity for DELHI METRO DR. MANGU SINGH Managing Director, DMRC.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Ensuring Good Quality PPP Projects Martin Darcy United Kingdom.
Out of Home Media on Ladies Frisking Booth at Metro Stations Vishwavidyalya to Huda City Centre Noida City Centre to Dwarka Sector - 21 Yamuna Bank to.
MANSI V. GAGDANI.  INTRODUCTION  HISTORY  ROUTES  ROUTES UNDER CONSTRUCTION  FUTURE EXTENTIONS  OPERATIONS & SAFETY  CHOICES FOR TICKET.
 The mission of the Human Resources Department is to safeguard the employee’s best interest, as they are Garrison’s most valuable asset, and without.
1 On-Farm Irrigation Project, Credit No KG On-Farm Irrigation Project, Credit No KG Presentation: On-Farm Irrigation Project Prepared by N.A.
Utility Financial Management AWWA Intermountain Section Leadership Forum Session Two November 10, 2015.
1 Chapter 10 Instructor Shan A. Garib, Winter 2013.
State IT Agency Briefing on Annual Report 2014/15 to Parliamentary Portfolio Committee on Telecommunications and Postal Services 16 October 2015.
Board Chair Responsibilities As a partner to the chief executive officer (CEO) and other board members, the Board Chair will provide leadership to Kindah.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
CCTV SECURITY & MONITORING SERVICES DAY SEVEN TECHNOLOGY CONSULT DSTC Monitoring Services Ltd DSTC.
Regional Accreditation Workshop For Asia and Eastern Europe Manila, Philippines th March, 2012.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, May 3 rd, 2016.
Welcome. Contents: 1.Organization’s Policies & Procedure 2.Internal Controls 3.Manager’s Financial Role 4.Procurement Process 5.Monthly Financial Report.
Safety Management Systems Session Four Safety Promotion APTA Webinar June 9, 2016.
Sahara Q Shop Locator Delhi. Store Name: GOSWAMI TRADING CO. Site Address: MAIN ROAD MUKUND VIHAR MUKUNDPUR, POSTAL CODE ,CONTACT PERSON- FHULENDRA.
ECO TOWERS Energy efficient office spaces next to Delhi in NOIDA
Light Rail Transit Project
Gurudronacharya Metro Station to
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Bangkok Metropolitan Administration’s activities to control air quality 1.
Presentation to the Portfolio Committee on Finance
ROAD SAFETY AUDIT & PROPOSAL FOR CORRIDOR EXTENSION PLAN: CASE STUDY BARAPULLAH CORRIDOR, NEW DELHI (INDIA) Namit Kumar Assistant Manager (Urban Transport)
PROJECT MANAGEMENT (ARCH 484) DEPARTMENT OF ARCHITECTURE & BUILDING SCIENCE.
City:- Corporation of City of Panaji
Dell Service Providers -

Presentation transcript:

Delhi Metro A Project Management Bench Mark Presentation By Kumar Keshav Director (Project &Planning), DMRC 23 rd June, 2011

Delhi Metro Rail Corporation (DMRC) Set up in May’95 under the Indian Companies Act. A joint venture between the Federal Government of India and the Provincial Government of Delhi State, with equal equity. DMRC has the responsibility for construction and operation of Delhi Metro. 2

Delhi Metro Rail Corporation (DMRC) A Master Plan had been drawn up for Delhi Metro expansion, consisting of 12 lines, covering 420 kms. to be completed by 2021 in four Phases. Works started on Phase I on 1 st October, 1998 and completed in December, Phase-I – 65 kms. Cost US $ 2.5 billion. Completed in 7 years and 3 months (2 years & 9 months ahead of schedule) 3

Phase-II covers 124 kms. This also includes a high speed Metro connection from centre of the city to the new airport in 18 minutes. Phase-II works commenced in January 2006 and completed in October, 2010 – 5 months ahead of schedule. Phase-III will consist of about 104 km at a cost of US $ 8.6 billion. The first contract for Phase-III has since been awarded. 4 Delhi Metro Rail Corporation (DMRC)

Funding of the Metro –20% of the cost is borne by the Federal Government. –20% of the cost is borne by the State Government. –About 50 – 60% of the cost through JICA Loan. –5% of the cost by DMRC through Property Development. 5

2500 train trips with 200 train sets on 6 lines. Each train used to consist of 4 coaches. Trains progressively being lengthened to 6 coaches and finally to 8 coaches. Average daily ridership - About 16.5 lakh passengers with average lead of 14 kms. Frequency during peak hours – 2 m 30 sec. System fully Barrier Free for Physically challenged. DMRC has introduced feeder bus short loop services Punctuality measured with a least count of 60 Sec. and average punctuality percentage is above 99%. Operation Highlights 6

Fare : From Rs. 8/- (17 cents) to Rs. 30/- (65 cents) - fare structure lowest in the world except Kolkata. The system making operational profit from Day-1. Delhi Metro receives no subsidy from the two Governments. We are able to meet the operating and maintenance expenditure fully. In addition we are servicing and repaying the loans taken from JICA. 20% of DMRC’s revenue is from Non-operational sources – mainly real estate development and advertisements. Financial Success of Delhi Metro 7

Challenges in Implementation Delhi Metro Project is the biggest urban intervention since Independence. Project is to be executed in very difficult urban environment. Being in the capital city all actions under close scrutiny of VVIPs. Project approved on completion cost. The Project implementation period extremely compressed and strict completion targets. Metro being constructed to world class standards with frontline technologies.

Challenges The sensitivities of the city to be respected during construction – No hardship or inconvenience to the public – Calcutta Experience. Each day’s delay in completion of project costs DMRC Rs. 2.3 Cr (Rs. 1.4 Cr by way of escalation and Rs.90 lakh by loss of revenues).

Large scale land acquisition in the city Tree cutting permission - Substantial No. of trees are transplanted. - For every tree cut, compulsory afforestation of 10 trees is undertaken. Utility diversions for Telecom, Electrical, Sewerage & Water pipe lines Special permissions such as for Ridge (Reserve Forest) Land, from Archaeological Survey of India, National Monument Authority Constraints in Project Implementation

How Challenges have been met

Work Culture & Organizational Values of DMRC 1.Punctuality. 2.Integrity – highest premium 3.Professional Competence. 4.Physical Fitness. 5.Quick Decision Making 6.High Discipline and loyalty to the Organization. 7.Prompt response to the needs of the Public and Contractors.

Dynamic Management Style Corporate Mission and Corporate Culture A slim but effective organization - No ineffective layers such as clerks, peons Reverse Time clocks. Democracy in management – Weekly HOD meetings and Monthly Dy. HOD meetings. Discourage paper oriented work – replies to outsiders within 10 days. Predominant use of information systems. High premium for integrity in the organisation

Dynamic Management Style Ample delegation of powers – accountability with delegation Redefined the role of Finance – Finance equally accountable with executive. Officers encouraged to take decisions on the spot. The fear of Audit and Vigilance not allowed to cramp the style. Leading from the front and not pushing from the rear. - Top Management readily available for decisions. Management based on trust

Project Monitoring at all Stages

Tendering & Award of work General philosophy – success of the project depends upon success of the contractors. Tenders from Pre-qualified list of bidders A unique filtering criterion evolved for prequalification covering vital items of technical & financial capabilities of the tenderers Objective evaluation criteria based on ‘scoring system’ The tender conditions finalized keeping in view the JBIC Procurement guidelines, FIDIC document and Indian Contract Act. Full powers for dealing with the tenders within organization Tenders are decided fast – so that no lobbying is possible.

Monitoring during execution Contractors prepare detailed Base – line work schedule for execution including duration of activities and identification of critical activities/path Close monitoring of work schedule, mobilization of ‘Manpower’, ‘Machinery & Plant’ and ‘Materials’ Weakly meetings with Contractors for planning the work and solving their problems. Practical approach to solve the genuine problems of contractors. Failing contractors are enabled to perform by timely assistance. Streamlined prompt payment procedure and quick decision-making.

Monitoring during execution Stringent penalties for failures to deliver. Prompt resolution of claims. Round the clock supervision guaranteed Strict independent quality & safety audit. Monthly progress presentations by the contractors DMRC directly handles works pertaining to other Government and Civic Departments to speed up. Have been able to establish that we are different than the normal executing agencies and mean business.

Interface Management - “Access dates” and “Key dates” listed in contract document itself. The important items which require interface with other contractors are clearly identified and indicated in contracts. Other contractors with whom the contractor has to interface are also clearly defined.

Monitoring during Testing & Commissioning Each activity of testing identified and duration of all these activities pre-determined Trials conducted as per schedule pre-determined jointly by System Contracts Service trial schedules also laid out in advance Sufficient time provided before actual commissioning

Training and motivation of employees –A rigid screening process for inducting staff and officers. –Training and exposure in the appropriate areas. –Management objectives and philosophy clearly shared with executives and staff. –Chief Executive and Top Managers themselves set an examples. –Immediate appreciation and reward for good work done but no castigation for failures. –No witch hunting for genuine mistakes. Officers encouraged to take quick decisions. Tendency to push decisions to higher levels curbed.

Public relations initiative –Works planned and managed with the least inconvenience to the public. –Press regularly briefed on the progress and programmes. –Community interaction at difficult work sites. –Proper barricading and good house keeping. –Proper signages, security men to guide traffic. –Special measures taken to protect the environment. Control on noise levels and vibrations during work. Washing tyres of vehicles. Performance is our best publicity. Have been able to establish credibility with the public by delivery on time.

Benefits of Delhi Metro A study by CRRI has brought out benefits of Delhi Metro Phase-I and worked out EIRR = 19.96%. Thus the entire cost of Phase-I recovered by the city of Delhi in 5yrs by 2010.

DMRC: An organisation with a difference…..

Thanks DMRC Ltd. Metro Bhawan, Fire Brigade Lane, Barakhamba Road, New Delhi

R K ASHRAM JHANDEWALA KAROL BAGH RAJENDRA PL PATEL NAGAR SHADIPUR KIRTI NAGAR MOTI NAGAR RAMESH NAGAR RAJOURI GARDEN TAGORE GARDEN DWARKA MOR NAWADA UTTAM NAGAR WEST UTTAM NAGAR EAST JANAKPURI WEST JANAKPURI EAST TILAK NAGAR SUBHAS NAGAR DWARKA DWARKA SEC-14 DWARKA SEC-13 DWARKA SEC-12 DWARKA SEC-11 DWARKA SEC-10 DWARKA SEC-9 INDRAPRASTHA B K RD MANDI HOUSE PRAG MN SHAHDARA WELCOME SEELAMPUR SHASTRI PARK KASHMERE GATE TIS HAZARI PULBANGASH PRATAP NAGAR SHASTRI NAGAR INDERLOK KANHAIYA NGR KESHAV PRM N S PLACE KOHAT ENCLAVE PITAMPURA ROHINI EAST ROHINI WEST RITHALA CHANDNI CHOWK CHAWRI BAZAR RAJIV CHOWK PATEL CHOWK Central SECTT CIVIL LINES VIDHAN SABHA VISWAVIDYALAYA NDLS LAXMI NAGAR YAMUNA BANK NIRMAN VIHAR PREET VIHAR KARKAR DUMA ANAND VIHAR ISBT KAUSHAMBI VAISHALI HAUZ KHAS UDYOG BHAWAN RACE COURSE JOR BAGH AIIMS GREEN PARK MALVIYA NAGAR SAKET QUTAB MINAR CHHATARPUR SULTANPUR GHITORNI ARJAN GARH INA HUDA CITY CENTRE IFFCO CHOWK GURU DRONACHARYA SIKANDARPUR M G ROAD AKSHARDHAM MAYUR VIHAR I MAYUR VIHAR EXT. NEW ASHOK NGR NOIDA SECTOR 15 NOIDA SECTOR 18 BOTANICAL GARDEN GOLF COURSE NOIDA CITY CENTRE NOIDA SECTOR 16 KHAN MARKET JLN STADIUM JANGPURA LAJPAT NAGAR MOOLCHAND KAILASH COLONY NEHRU PLACE KALKAJI MANDIR GOVIND PURI OKHLA SARITA VIHAR MOHAN ESTATE TUGHLAKABAD BADARPUR JASOLA MANSAROVAR PARK JHILMIL DILSHAD GARDEN GTB NAGAR MODEL TOWN AZADPUR ADARSH NAGAR JAHANGIRPUR I SHIVAJI STADIUM DHAULA KUAN DELHI AEROCITY AIRPORT DWARKA SEC 8 DWARKA SEC 21 PUNJABI BAGH SRS MARG ASHOK PARK SHIVAJI PARK MADIPUR PASCHIM VIHAR E PASCHIM VIHAR W PEERAGARHI UDYOG NAGAR SURAJMAL STADIUM NANGLOI NANGLOI RLY. STN RAJDHANI PARK MUNDKA ASHRAM MAYUR VIHAR ph-1 TRILOKPURI VINOD NAGAR IP EXTN N SRINIVASPURI DHAULA KUAN JAGATPURI ARJUN NAGAR BHOLANATH NAGAR MAUJPUR YAMUNA VIHAR JAFFRABAD DELHI CANTT NARAINA 1 NARAINA 2 MAYAPURI` ` ESI HOSPITAL SHAKURPUR SHALIMAR BAGH S MUKUNDPUR MOTI BAGH BHIKAJI KAMA PLACE SAROJINI NAGAR SOUTH EXTN HAZARAT NIZAMUDDIN AMITY NOIDA KALINDI KUNJ JASOLA VIHAR JOKHALA VIHAR JAMIA NAGAR ISHWAR NAGAR JOKHALA PH-III NEHRU PLACE G. K. ENCLAVECHIRAG DELHI PANCHSHEEL PARK I.I.T. R. K. PURAM VASANT VIHAR MUNIRKA I.G.D. AIRPORT PALAM DHSRATH PURI DABRI MOR JANAKPURI C-2B JANAKPURI WEST BOTANICAL GARDEN ROHINI SEC. 18 SHALIMAR PLACE BADLI JAHANGIRPUR I ITO JANAPATH DELHI GATE JAMA MASJID LAL QUILA KASHMERE GATE Central SECTT