Should we build this plant? The Basics of Capital Budgeting
What is capital budgeting? Analysis of potential additions to fixed assets. Long-term decisions; involve large expenditures. Very important to firm’s future. Analysis of potential additions to fixed assets. Long-term decisions; involve large expenditures. Very important to firm’s future.
Steps 1. Estimate CFs (inflows & outflows). 2. Assess riskiness of CFs. 3. Determine k = WACC (adjusted). 4. Find NPV, IRR, MIRR, etc. 5. Accept if NPV > 0, IRR > WACC, etc. 1. Estimate CFs (inflows & outflows). 2. Assess riskiness of CFs. 3. Determine k = WACC (adjusted). 4. Find NPV, IRR, MIRR, etc. 5. Accept if NPV > 0, IRR > WACC, etc.
What is the difference between independent and mutually exclusive projects? Projects are: independent, if the cash flows of one are unaffected by the acceptance of the other. mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other. Projects are: independent, if the cash flows of one are unaffected by the acceptance of the other. mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.
An Example of Mutually Exclusive Projects BRIDGE vs. BOAT to get products across a river.
Normal Cash Flow Project: Cost (negative CF) followed by a series of positive cash inflows. One change of signs. Nonnormal Cash Flow Project: Two or more changes of signs. Most common: Cost (negative CF), then string of positive CFs, then cost to close project. Nuclear power plant, strip mine.
Inflow (+) or Outflow (-) in Year NNN N N N
What is the payback period? The number of years required to recover a project’s cost, or how long does it take to get our money back?
Payback for Project L (Long: Large CFs in later years) = CF t Cumulative Payback L 2+30/80 = years 80
Project S (Short: CFs come quickly) CF t Cumulative Payback L /50 = 1.6 years =
Strengths of Payback: 1.Provides an indication of a project’s risk and liquidity. 2.Easy to calculate and understand. Weaknesses of Payback: 1.Ignores the TVM. 2.Ignores CFs occurring after the payback period. 3.Subjective
Discounted Payback: Uses discounted rather than raw CFs CF t Cumulative Discounted payback /60.11 = 2.7 years PVCF t % = Recover invest. + cap. costs in 2.7 years.
NPV:Sum of the PVs of inflows and outflows.
What’s Project L’s NPV? % Project L: = NPV L NPV S = $19.98.
Calculator Solution Enter in CFLO for L: CF 0 CF 1 NPV CF 2 CF 3 I = = NPV L
Rationale for the NPV Method NPV= PV inflows – Cost = Net gain in wealth. Accept project if NPV > 0. Choose between mutually exclusive projects on basis of higher NPV. Adds most value.
Using NPV method, which project(s) should be accepted? If Projects S and L are mutually exclusive, accept S because NPV s > NPV L. If S & L are independent, accept both; NPV > 0. If Projects S and L are mutually exclusive, accept S because NPV s > NPV L. If S & L are independent, accept both; NPV > 0.
Internal Rate of Return: IRR 0123 CF 0 CF 1 CF 2 CF 3 CostInflows IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.
NPV: Enter k, solve for NPV. IRR: Enter NPV = 0, solve for IRR.
What’s Project L’s IRR? IRR = ? PV 3 PV 2 PV 1 0 = NPV Enter CFs in CFLO, then press IRR: IRR L = 18.13%.IRR S = 23.56%.
IRR = ? Find IRR if CFs are constant: -100 Or, with CF keys, enter CFs and press IRR = 9.70% % INPUTS OUTPUT NI/YRPVPMTFV
IRR = ? Q.How is a project’s IRR related to a bond’s YTM? A.They are the same thing. A bond’s YTM is the IRR if you invest in the bond IRR = 7.08% (use TVM or CF keys)....
Rationale for the IRR Method If IRR > WACC, then the project’s rate of return is greater than its cost--some return is left over to boost stockholders’ returns. Example:WACC = 10%, IRR = 15%. Profitable.
IRR Acceptance Criteria If IRR > k, accept project. If IRR < k, reject project. If IRR > k, accept project. If IRR < k, reject project.
Decisions on Projects S and L per IRR If S and L are independent, accept both. IRRs > k = 10%. If S and L are mutually exclusive? If S and L are independent, accept both. IRRs > k = 10%. If S and L are mutually exclusive?
Construct NPV Profiles Enter CFs in CFLO and find NPV L and NPV S at different discount rates: k NPV L (4 NPV S (4)
NPV ($) Discount Rate (%) IRR L = 18.1% IRR S = 23.6% Crossover Point = 8.7% k NPV L (4) NPV S S L
NPV and IRR always lead to the same accept/reject decision for independent projects: k > IRR and NPV < 0. Reject. NPV ($) k (%) IRR IRR > k and NPV > 0 Accept.
Mutually Exclusive Projects k 8.7 k NPV % IRR S IRR L L S k NPV S, IRR S > IRR L CONFLICT k > 8.7: NPV S > NPV L, IRR S > IRR L NO CONFLICT
To Find the Crossover Rate 1.Find cash flow differences between the projects. See data at beginning of the case. 2.Enter these differences in CFLO register, then press IRR. Crossover rate = 8.68%, rounded to 8.7%. 3.Can subtract S from L or vice versa, but better to have first CF negative. 4.If profiles don’t cross, one project dominates the other.
Two Reasons NPV Profiles Cross 1.Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high k favors small projects. 2.Timing differences. Project with faster payback provides more CF in early years for reinvestment. If k is high, early CF especially good, NPV S > NPV L.
Reinvestment Rate Assumptions NPV assumes reinvestment at k (opportunity cost of capital). IRR assumes reinvest at IRR. Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects. NPV assumes reinvestment at k (opportunity cost of capital). IRR assumes reinvest at IRR. Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.
Managers like rates--prefer IRR to NPV comparisons. Can we give them a better IRR? Yes, MIRR is the discount rate that causes the PV of a project’s terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at the project’s required rate of return.
MIRR = 16.5% % MIRR for Project L (k = 10%) % TV inflows PV outflows MIRR L = 16.5%
To find TV with HP 10B, enter in CF’s: I = 10 NPV = = PV of inflows. Enter PV = , N = 3, I = 10, Press FV = = FV of inflows. Enter FV = , PV = -100, N = 3. Press I = 16.50% = MIRR. CF 0 = 0, CF 1 = 10, CF 2 = 60, CF 3 = 80
Why use MIRR versus IRR? MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs. Managers like rate of return comparisons, and MIRR is better for this than IRR.
Project P: NPV and IRR? 5,000 -5, k = 10% -800 Enter CFs in CFLO, enter I = 10. NPV = IRR = ERROR. Why?
We got IRR = ERROR because there are 2 IRRs. Nonnormal CFs--two sign changes. Here’s a picture: NPV Profile IRR 2 = 400% IRR 1 = 25% k NPV
Logic of Multiple IRRs 1.At very low discount rates, the PV of CF 2 is large & negative, so NPV < 0. 2.At very high discount rates, the PV of both CF 1 and CF 2 are low, so CF 0 dominates and again NPV < 0. 3.In between, the discount rate hits CF 2 harder than CF 1, so NPV > 0. 4.Result: 2 IRRs.
Could find IRR with calculator: 1.Enter CFs as before. 2.Enter a “guess” as to IRR by storing the guess. Try 10%: 10STO IRR = 25% = lower IRR Now guess large IRR, say, 200: 200STO IRR = 400% = upper IRR
When there are nonnormal CFs and more than one IRR, use MIRR: ,0005,000,000 -5,000,000 PV 10% = -4,932, TV 10% = 5,500, MIRR = 5.6%
Accept Project P? NO. Reject because MIRR = 5.6% < k = 10%. Also, if MIRR < k, NPV will be negative: NPV = -$386,777.
The End