KEY CONSULTATIONS an overview Louise Masters InnogyOne, Innogy UK Offshore Wind 2003.

Slides:



Advertisements
Similar presentations
July 2003 Structure of Electricity Distribution Charges Update and Proposals Martin Crouch Director, Distribution.
Advertisements

EDCM update Mo Sukumaran (on behalf of CMG)
Gas Development Master Plan Steering Committee Meeting – 28 March 2013 GDMP Overview.
June 2003 Structure of Electricity Distribution Charges Next Steps Martin Crouch Director, Distribution.
July 2003 Structure of Electricity Distribution Charges Welcome and Introduction Charles Gallacher Deputy Director, Scotland.
5 February 2009 energynetworks.org 1 Common Methodology Group Work PRESENTED BY OLIVER DAY ON BEHALF OF WORKSTREAM 3 Workstream 3 Tariff Application.
UNC Modification Proposal Revised Timescales for LDZ Shrinkage Arrangements Simon Trivella – 25 th September 2008 Distribution Workstream.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
BWEA OFFSHORE CONFERENCE 17 – 18 APRIL 2002 Offshore Consents Planning for the Future Nigel Peace Director, Energy Regulation Department of Trade & Industry.
John Zammit-Haber National Grid
The information in this presentation has been collated by ELEXON and while all due care has been taken to ensure the accuracy of this information, ELEXON.
David Halldearn, ERGEG Conference on Implementing the 3 rd Package 11 th December 2008 Implementating the 3rd Package: An ERGEG Consultation paper.
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP.
1 st April 2010 energynetworks.org 1 Common Methodology Group Work PRESENTED BY Tony McEntee, ENW Workstream 4 Update Common Connection Charging Methodology.
SO Incentives from April 2010 John Perkins. 2 Gas System Operator (SO) Incentives National Grid operates the high pressure Gas Transmission System in.
FUTURE OFFSHORE Update on the Consultation Nigel Peace Licensing & Consents Unit 27 March 2003.
1/20 ea technology MicroCHeaP: Month 24 meeting Athens Work Package 4 presentation 21 September 2006 Presented by Yvonne Dickson Partners in power asset.
19 March 2010 energynetworks.org 1 PRESENTED BY Nigel Turvey Workshop on Distributed Generation Connected pre April March 2010.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review of the UNC Post-emergency Arrangements Workshop 1 March 2009.
EASTERN AFRICA POWER POOL EAPP 5 th Coordination Meeting Of African Regional Power Pools 6 th – 7 th May 2010 Harare, Zimbabwe.
V5 p.1 Consultation Period Offshore Electricity Transmission – milestones (1) Apr - JuneJuly - SeptOct - DecJan - Mar KEY: 2006/7 Initial Framework Oct/Nov.
17 May 2011 Generation Dominated Areas Oliver Day UK Power Networks (on behalf of DNOs) 1 | Energy Networks Association.
System Operation Changes – Interaction with ELEXON APEx Conference: Leipzig October 2004.
Provision of third party access to licence exempt electricity and gas networks Tony McEntee 5 April | Energy Networks Association - DCMF.
Renewables Integration Development Project North West of the Island of Ireland Louis Fisher, EirGrid.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Energynetworks.org 1 PRESENTED BY Andrew Neves, Chair CMG CMG and Workstream Update.
Initial view on changes to Codes OTEG, 3 rd July 2006.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
The outcomes of the WICS review into regulatory methodology A presentation given by Chief Executive Water Industry Commission for Scotland Water 2010 Alan.
Open letter on Development of the regime ahead of winter 2007/8 Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 28 June 2007.
Energy Networks Association RIIO-ED1 Update for Suppliers December 2012.
Pamela Taylor, Head of European Strategy, Ofgem Madrid Forum, March 2011 ERGEG’s draft framework guideline for gas balancing.
Code Governance Review UNC Modification Proposals Beverley Viney - National Grid NTS.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
An Overview of: Generation Connections: Transmission Connection Cost Responsibility Review July
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Gas SO Incentives For 1 April 09 Transmission Workstream 3 July 2008.
Energy Market Issues for Biomethane Projects Workshop - 31 October 2011 RIIO-GD1 Environmental Incentives.
Consumer Research for DPCR5 Stakeholder meeting 15 June 2007 Laura Nell, Quality of Service, Ofgem.
Industry Dialogue on xoserve Services 14 th September 2007.
1 Dublin 23/24 April CONCLUSIONS Regulatory Co-ordination Responses to Deliverables 3 and 4 due by 8 th May Papers redrafted to take comments into account.
European Developments Transmission Workgroup 3 rd May 2012.
Guidelines on Transmission Tarification ERGEG Public Hearing 30. June 2005.
12 November energynetworks.org 1 PRESENTED BY MO SUKUMARAN, ON BEHALF OF WSB Presentation from Workstream B Pricing Modelling (EDCM/CDCM) Common.
Integration of Demand Side Management, Distributed Generation, Renewable Energy Sources and Energy Storages Task status report, Task XVII EXCO meeting.
Modification Proposal 0283 Update
Transmission Planning Code – Draft Document
Review Group 291- Ofgem Update
Grid Code Development Forum – 6 September 2017
Code Governance Review UNC Modification Proposals
Grid Code Review Panel 16th August 2017
SO Incentives Consultation
Transmission Planning Code
SO Incentives from April 2010
NTS Entry Charging Review Update
Development Modification Proposal 0337: Introduction of a Inter-day Linepack Product – OPEN LETTER Review Group August th November 2010.
0291 – NTS Licence Special Condition 27 – Balancing Arrangements
Exit Capacity Substitution and Revision
Generation Dominated Areas(GDA)
Review Group 291- Ofgem Update
Entry Capacity Transfer and Trade
Ofgem presentation to Gas Transmission Workstream
Information Provision for Transitional Exit Capacity
Open Letter - Summary of Responses
Commercial Arrangements For Gas Quality Service – Introduction
Incremental Entry Capacity Release Methodology Statement
Gas Customer Forum 28 July 2008
Capacity Access Review
Presentation transcript:

KEY CONSULTATIONS an overview Louise Masters InnogyOne, Innogy UK Offshore Wind 2003

INTRODUCTION To highlight the raft of ongoing regulatory and technical consultations that will impact upon the connection of offshore wind farms onto the transmission and distribution systems of Great Britain.  Key Ofgem and DTI Consultations (current and recent)  Grid Code Reviews  Scottish Grid Code Review  England and Wales (NGT) Grid Code Review  GB Grid Code  Distributed Generation Coordinating Group (DGCG) UK Offshore Wind 20032

KEY OFGEM AND DTI CONSULTATIONS UK Offshore Wind  Transmission losses in a GB market  NGT system operator incentive scheme  Distributed generation: a review of progress  Developing network regulation: open letter to the DNO’s  Structure of electricity distribution charges  Electricity distribution losses  Modifications to the Distribution Code to clarify the data interchange requirements between Users and DNOs  Developing network monopoly price controls  Distribution Price Control Review (DPCR)  BETTA (various consultations)

TRANSMISSION LOSSES IN A GB MARKET  DTI launched consultation in January Examines the use of average zonal losses to charge for losses in the new GB market.  In particular it invites views on the impact that average zonal losses will have upon the development of renewables in the short to longer term  Responses required by 28 th March 2003 UK Offshore Wind 20034

NGT SYSTEM OPERATOR INCENTIVE SCHEMES  Initial consultation published October 2002  Further consultation published December Proposed phased implementation  Phase 1- revised “shallow” incentive scheme until October requirement on NGC to put into place a new transmission access regime  Phase 2- SO transmission capacity buy-back and balancing incentive, in October SO transmission capacity release incentive, with long- term firm tradable rights, no later than April 2004  Closed for comments in February 2003  Final proposals on Phase 1 expected February Further Consultation on Phase 2 expected during 2003 UK Offshore Wind 20035

DISTRIBUTED GENERATION: A REVIEW OF PROGRESS  Consultation held March 2002, workshop held September Proposed interim measures for removing barriers to the connection of distributed generation until the next DPCR  Review of Progress published January Responses required by 7 th March 2003  Further work is being taken forward by Ofgem through:  framework of price controls for monopoly networks consultation  distribution charging structures consultation  open letter to DNO Chief Executives  DPCR UK Offshore Wind 20036

DEVELOPMENT OF NETWORK REGULATION: OPEN LETTER TO THE DNO’S  Open Letter from Callum McCarthy to the DNO’s in January 2003  Responses required in February 2003  Brings together the issues and proposals that are being put forward in the many consultations  Sets out Ofgem’s thoughts on how a future regulatory framework can be developed to give the appropriate incentives to DNO’s UK Offshore Wind 20037

STRUCTURE OF ELECTRICITY DISTRIBUTION CHARGES  Consultation held late 2002, followed by a workshop in February 2003, to gather views on the proposed new connection and UoS charging arrangements  Suggests a move from deep to ‘shallow-ish’ or shallow connection charges with a new UoS charge for generators  Initial proposals document expected for consultation in March/April 2003  Proposals document expected to be issued in June 2003 UK Offshore Wind 20038

ELECTRICITY DISTRIBUTION LOSSES  Initial consultation paper issued in January 2003, to gather views on the suggested incentives. Closed February 2003  Suggests new mechanisms/incentives to encourage DNO’s to reduce losses, within the context of the DPCR  Possible industry workshop planned for March/ April 2003  Further consultation paper expected May 2003, to set out the developed thinking and invite comments.  Final decision paper expected August 2003 UK Offshore Wind 20039

DISTRIBUTION CODE - DATA INTERCHANGE REQUIREMENTS  DCRP issued consultation in February Proposed changes to the Distribution Code and a Guide to Data Interchange for Distributed Generation Projects  Clarifies the terminology in the Distribution Code in line with Grid Codes  Introduces other terminologies from the Grid Codes  Proposes data requirements for non-synchronous and converter connected generation  Proposes standard network data, for networks below 33 kV, that should be provided by DNO’s  Comments required by 28 th March 2003 UK Offshore Wind

DEVELOPING NETWORK MONOPOLY PRICE CONTROLS  Update on Ofgem’s work on developing network monopoly price controls and its impact on the next DPCR, published February 2003  Open letter published 13 th March 2003, detailing,  Frontier Economics work on dealing with uncertainty and the incentive framework for price controls  a detailed timetable and workplan for the next DPCR  Comments on both required by 14 th April 2003  Statement Document on Developing Price Controls to be published May 2003, which will feed into the work on the next DPCR UK Offshore Wind

DISTRIBUTION PRICE CONTROL REVIEW (DPCR)  Current Price Control runs until March  Preparation for setting the next Price Control will commence this year, building on work done in “Developing network monopoly price controls” and other consultations  Initial consultation document on the DPCR expected May  Initial proposals on the DPCR expected for consultation June 2004  Final proposals expected October 2004  Price Control implemented April 2005 UK Offshore Wind

BETTA CONSULTATIONS  British Electricity Trading and Transmission Arrangements (BETTA) expected to “go live” late 2004-mid 2005  BETTA is an extension of NETA to incorporate Scotland  Several consultations out at the moment,  The Grid Code under BETTA  The Connection and Use of System Code under BETTA  The Balancing and Settlement Code under BETTA  Changes to electricity generation, distribution and supply licences under BETTA  Numerous further consultations expected UK Offshore Wind

GRID CODE REVIEWS  Scottish Grid Code Review  England and Wales (NGT) Grid Code Review  GB Grid Code UK Offshore Wind

SCOTTISH GRID CODE REVIEW UK Offshore Wind  Formal consultation in March 2002  Currently with Ofgem for approval  Main issues,  timescales for phasing in of requirements  MW thresholds  manned control points  capability of wind turbine technology to meet the requirements for frequency response, frequency control, range of power factors, fault ride through, ramp rates

NGT GRID CODE REVIEW UK Offshore Wind  Generic Provisions Working Group looking at the requirements for asynchronous generators and converter connected generation, for inclusion into the Grid Code  Interim requirements for medium wind farms that apply for Licence Exemption listed in Bilateral Agreement  Main issues of the interim requirements,  timescales for phasing in of requirements  capability of wind turbine technology to meet the requirements for frequency response, frequency control, range of power factors, fault ride through

GB GRID CODE  Consultation issued in December Seeking views on a single GB Grid Code, based on the England and Wales Grid Code, and the differences between the existing Grid Codes and how they should be resolved. Responses by 27 January 2003  Report on the conclusions to be published in March 2003  Two further consultations on the draft text to be published in April 2003, and July 2003  Conclusions and final draft text to be published by September 2003  GB grid code to be given legal force after the Electricity (Trading and Transmission) Bill has been given royal assent UK Offshore Wind

Distributed Generation Coordinating Group (DGCG) UK Offshore Wind DTI/Ofgem DGCG Ofgem Internal Distributed Generation Board Technical Steering Group TSG Workstream 1: Distributed generation status and projections Workstream 2: Standardisation of information solutions Workstream 3: Short term network solutions Workstream 4: Short term micro-generation solutions Workstream 5: Long term network concepts and options Workstream 6: Industry skills and resources

USEFUL WEBSITES UK Offshore Wind   