Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 COMMISSIONING & OPERATION OF SOLEIL. J.C. Besson, J.F. Lamarre, A. Bence, X.

Slides:



Advertisements
Similar presentations
Transparent Re-alignment of the Diamond Storage Ring M. Apollonio – Diamond Light Source Ltd ESLS – XXII Workshop, ESRF Grenoble, November 25 th /11/2014M.
Advertisements

F. Fernandez 28/10/ Ferran Fernandez WAO2014 Operators training experience at the ALBA synchrotron light source.
R. Nagaoka, A. Nadji, M.E. Couprie, O. Marcouillé
Necessity of Moving from Green Book to White Book M. Hadi Hadizadeh Yazdi International Scientific Meetings Office Iran October 26, 2002 Amman, Jordan.
Design and Performance Expectation of ALPHA accelerator S.Y. Lee, IU 2/26/ Introduction 2. Possible CIS re-build and parameters 3. Issues in the.
Dr. Zafer Nergiz Nigde University THE STATUS OF TURKISH LIGHT SOURCE.
ALPHA Storage Ring Indiana University Xiaoying Pang.
Searching for Quantum LOVE at the Australian Synchrotron Light Source Eugene Tan On behalf of Rohan Dowd 120/10/2010Eugene Tan – IWLC 2010, Genega ASLS.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
June 14th 2005 Accelerator Division Overview of ALBA D. Einfeld Vacuum Workshop Barcelona, 12 th -13 th September 2005 General 10 th September 2005.
June 14th 2005 Accelerator Division Overview of ALBA D. Einfeld Vacuum Workshop Barcelona, 12 th -13 th September 2005 General 10 th September 2005.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Orbit Control For Diamond Light Source Ian Martin Joint Accelerator Workshop Rutherford Appleton Laboratory28 th -29 th April 2004.
Simulation and Experimental Results of SSRF Top-up Operation Haohu Li, Manzhou Zhang SSRF Top-up Workshop, Melbourne
Matthew Cox VSSLS Workshop Barcelona Sept SLIDE 1 1 Diamond Light Source Vacuum Systems Matthew Cox
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS II: Accelerator System Overview NSLS II Advisory Committees October 18/19, 2006 Satoshi Ozaki.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
1 FFAG Role as Muon Accelerators Shinji Machida ASTeC/STFC/RAL 15 November, /machida/doc/othertalks/machida_ pdf/machida/doc/othertalks/machida_ pdf.
1 Proposal for a CESR Damping Ring Test Facility M. Palmer & D.Rubin November 8, 2005.
Jørgen S. Nielsen Institute for Storage Ring Facilities (ISA) Aarhus University Denmark 1 ESLS-RF 14 (29-30/9 2010), ASTRID and ASTRID2 new LLRF.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Overview Satoshi Ozaki Director, Accelerator Systems Division NSLS-II Project March 27, 2007.
February 2010 ALBA Synchrotron Light Source Francis Perez.
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
Accelerator Science and Technology Centre Extended ALICE Injector J.W. McKenzie, B.D. Muratori, Y.M. Saveliev STFC Daresbury Laboratory,
28-May-2008Non-linear Beam Dynamics WS1 On Injection Beam Loss at the SPring-8 Storage Ring Masaru TAKAO & J. Schimizu, K. Soutome, and H. Tanaka JASRI.
14th ESLS RF Workshop ELETTRA / Trieste, Italy / 2010 September The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis.
Automatic Machine Review Dec 2015 MAX IV Storage Rings Automation Pedro F. Tavares.
Canadian Light Source Commissioning Progress CLS Annual Users Meeting –
ATF Fast Ion Study Plan N.Terunuma (KEK) Results in 2007, 2008 Vertical emittance studies at ATF Plan.
1 September 2007 – Tango Meeting – A.Buteau ICALEPS 2005 Status report SOLEIL September 2007.
The Introduction to CSNS Accelerators Oct. 5, 2010 Sheng Wang AP group, Accelerator Centre,IHEP, CAS.
Operational experience of high-power RF at Diamond Light Source
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Global Design Effort ILC Damping Rings: R&D Plan and Organisation in the Technical Design Phase Andy Wolski University of Liverpool and the Cockcroft Institute,
Machine Operation and Studies at SSRF Wenzhi ZHANG Dec. 16, 2013 Spain.
Workshop on Accelerator R&D for Ultimate Storage Rings – Oct Nov.1 – Huairou, Beijing, China A compact low emittance lattice with superbends for.
Experience with Novosibirsk FEL Getmanov Yaroslav Budker INP, Russia Dec. 2012, Berlin, Germany Unwanted Beam Workshop.
ASTRID2 Niels Hertel Nov 2012 AARHUS UNIVERSITET ASTRID2 – Status ESLS XX Berlin 2012 Niels Hertel ISA, Aarhus University, Denmark 1.
SOLEIL OPERATION AND ON-GOING PROJECTS C. Herbeaux On behalf of SOLEIL Groups C. Herbeaux, November ESLS23, 24-25, 2015, PSI1.
Jørgen S. Nielsen Center for Storage Ring Facilities (ISA) Aarhus University Denmark ESLS XXIII (24-25/ ), ASTRID2 facility 1.
Ultra-low Emittance Coupling, method and results from the Australian Synchrotron Light Source Rohan Dowd Accelerator Physicist Australian Synchrotron.
ESLS Workshop Nov 2015 MAX IV 3 GeV Ring Commissioning Pedro F. Tavares & Åke Andersson, on behalf of the whole MAX IV team.
Andreas Lüdeke, Trieste, 24. Sep., WAO '07 Operation Information Management at the Swiss Light Source Andreas Lüdeke of the Swiss Light Source at the Paul.
Operation Status of the RF Systems and Taiwan Photon Source
MACHINE OPERATION AT ALBA Montse Pont, CELLS-ALBA 16-18/12/2013.
Montse Pont ARW 2013 Operation and Reliability at ALBA Montse Pont.
Report Technical Director Storage-Ring-Installation Completed
Operations Machine Simulator.
Long Term Plans at MAX IV
Performances of the French synchrotron light source SOLEIL Actions to enhance the reliability of the equipment J.F. Lamarre*, E. Patry X. Delétoille, A.
PETRA III, Status and Upgrade
Machine operation and daily maintenance management in SOLEIL
Status of HESR 18th March Gießen Dieter Prasuhn.
Diamond Light Source Status and Future Challanges
STATUS OF THE ALBA SYNCHROTRON LIGHT SOURCE: FROM COMMISSIONING TO OPERATION M.Pont, CELLS-ALBA
Status of the ASTRID2 facility
Bocheng Jiang SSRF AP group
Coupling Correction at the Australian Synchrotron
SOLEIL Fast Orbit Feedback System
The SPEAR3 Upgrade Project at SLAC
The SPEAR3 Upgrade Project at SLAC
Machine Operation and Progresses in SSRF
Operation Progress and Upgrade in SSRF
Специализированный источник синхротронного излучения Anka Характеристики и экспериментальные возможности.
Overview LINAC BOOSTER STORAGE RING 100 Mev Commissioned in 2008
WELCOME TO SOLEIL Amor Nadji On behalf of Synchrotron SOLEIL
Status of the ASTRID2 RF systems
ThomX – Commissioning Meeting – 25/01/2018
Presentation transcript:

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 COMMISSIONING & OPERATION OF SOLEIL. J.C. Besson, J.F. Lamarre, A. Bence, X. Deletoille, Y. Denis, S. Petit, R. Cuoq, P. Da Silva, D. Pereira, G. Roux, Synchrotron Soleil, St Aubin, France.

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 SOLEIL Synchrotron

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Summary 1)Installation and Commissionning 2)The Control Room 3)Software and Hardware Architecture 4)Some Software Applications 5)Balance-Sheet 6)Conclusion

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Installation Accelerators SOLEIL is a third generation Synchrotron radiation Source, located at the Plateau de Saclay near Paris. Storage Ring Booster Linac Sextupoles (220/280 Kg) Quadrupoles (900/1200 Kg) Dipoles (3,5T) Long Girder (4,8m–7,8T) Cell with 3 girders The 354 m circumference storage ring is mainly composed of 32 (+1) dipoles, 160 quadrupoles, 120 sextupoles, 2 RF cryomodules, ~ 200 vacuum chambers, 6 injection equipments; 12 beamline front-ends and 4 insertion devices (initially). The 157 m circumference Booster comprises 36 dipoles, 44 quadrupoles, 28 sextupoles, 1 RF cavity and 8 injection/extraction equipment

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Installation Accelerators

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Installation Accelerators General Planning 1st beam in the Linac on July 2nd,2005 1st beam in the Booster at 110 MeV on July 23rd 2005 Booster : 1st beam accelerated to 2.75 GeV on October 13th 2005 Booster : 1st extraction of 2.75 GeV beam on May 6th, st turn in the storage ring on May 14th, 2006

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Commissioning organization A commissioning team of about 20 persons composed of the machine physics group and people coming from different areas was constituted in the early stage. They shared their experience and their knowledge in the preparation of the different phases of the commissioning and in the analysis of the results. This organization allowed a fast progress of the commissioning (round clock operation) and different ways to see and solve the encountered problems.

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Commissioning organization  General planning  Detailed protocol for each session  Electronic logbook  One report of each session  A commissioning team  People working 3 x 8h; 7d/7; (example : 7h am-3h pm-11h pm-7h am)  Overlap of 1/2 an hour between 2 successive team  On-call and shift people.  weekly meeting for commissioning team and for each encountered problem

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 J. M. Filhol M. P. Level P. Brunelle M. A. Tordeux A. Loulergue A. Madur A. Nadji L. Nadolski R. Nagaoka B. Pottin J. C. Besson J. F. Lamarre J. C. Denard L. Cassinari M. E. Couprie P. Marchand P. Lebasque Magnets & insertions Group Security Group Vacuum Group Power supply group RF Group Elect. Control & Acquisition Group Diagnostics Group The team: at less one representative from each sudivision operation Group Inf. Control & Acquisition Group Facilities Group Linac Group Commissioning team

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Commissioning Milestones in effective weeks 14/5 First turn 04/6 First stored beam 04/6 First beam accumulation : 8.35mA 04/7 100mA achieved 10/7 5 A.h beam dose Shutdown 11/7 – 4/09 13/9 First photons to a beamline (DIFFABS) 16/9 200mA 21/9 First photons to a beamline (TEMPO) 25/9 300mA achieved ; 30A.h 29/9 U20 at 5.5mm gap 21/9 First photons to a beamline (ODE) 15/10 Beam lifetime in 312 bunches 12/12 First photons to a beamline (SAMBA) 13/12 First photons to a beamline (DESIRS) 21/12 70 A.h beam dose 21/12 Beam lifetime in 312 bunches

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007  Quadrupoles and Correctors ON, Sextupoles and RF OFF.  After correction of first turn trajectory and closing the first turn.  Sextupoles ON and RF OFF. successive turns detected by the FCT First turns (May 14, 2006)

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO mm vertical aperture chambers When the beam could be circulated for the first time in the Storage Ring it goes several times through the 10 mm small vertical aperture of the 10 insertion device chambers distributed along the ring without any correction.

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Closed Orbit with All correctors OFF (BPM offsets included after BBA) H rms=3.1mm max=6.40mm V rms=0.41mm max=1.44mm => Excellent magnet alignment

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Current and Integrated Dose, year 2006 maximum current of 300mA possible with only one cryomodule RF was reached after only 30A.h of integrated current dose

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Beam position stability (with SOFB) mA Beam current X (PX1) X (CASSIOPEE) Z (PX1) Z (CASSIOPEE) mm injection (Source point Positions) on 2 straight sections during a 8 hours beamline shift. DX ~ 3 µm, DZ ~ 1 µm

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 ParametersDesignAchieved as of June 2007 Energy ( GeV ) RF frequency ( MHz ) Betatron Tunes / / Natural Chromaticities -53 / / -19 Momentum Compaction  1 /  x / 4.6 x x / 4.30 x Emittance H ( nm.rad ) ± 0.2 Energy spread x x Coupling,  V /  H <1%0.3% (without correction) Current Multibunch mode ( mA ) Average Pressure ( mbar ) 1 x x Beam Lifetime ( h ) mA / 100 mA Single bunch current ( mA ) 1220 Beam position stability,  m ( H ) 20 (rms)3 ptp Beam position stability,  m ( V ) 0.8(rms)2 ptp STORAGE RING COMMISSIONING

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Results and innovations We had no problems with innovations This good result clearly demonstrates the beneficial effect of the NEG coating on the aluminium chamber. This technology was never seen before on accelerators at such extensive use. 2 other innovations concern the RF system: the dedicated Superconducting cavities (1st cryomodule enable alone operation up to 300 mA, a 2nd cryomodule which is being build by ACCEL will enable to reach 500 mA) and the solid state RF amplifiers that are used for the first time in the world for such high power. Except few transistor failures, the system is very stable. Specific and innovative electromagnetic insertion devices were developed for VUV beamlines: –3 HU256 (10eV to 1000eV) 3.6 meter long –1 HU640 (5eV to 40eV) 10 meter long Extended spectral range :from UV (5 eV) up to hard X-Rays (15 KeV)

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 RF System Innovations Each of the four cavities is powered by a 190 kW solid state amplifier consisting in a combination of four “towers” producing about 50 kW each. Solid State RF Amplifiers 4 x 190 kW power amplifiers 1 st cryomodule inside SR tunnel

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 During the shifts, within the operation group, 8 operators take their turns every 8 hours in order to ensure the presence of one of them 24h/24h and 7 days a week in the control room. This operator is assisted by 1 or 2 part-time operators (like ESRF) who come for majority from SOLEIL source division. Before being ready to work in control room, they get training by the "machine physicists" on the general operation of the machine. During shutdown, permanence in control room is ensured by an operator during the normal schedule. Apart from the operation of the machine, the operators are implied in the result analysis and in the developments (software and equipment) enabling a better understanding and operation of the installation. Operation organization

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Formation of the operation group Staff Number According to their arrival Operators were involved in the machines installation and the supervision applications development

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 TL1BOOSTER/TL2 SR light monitor SR beam size measurement Pinhole camera TUNE Measurement Control room Organization

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 TL1 to BOOSTER BOOSTER to TL2 TL2 to Storage Ring Storage Ring FCT Machine Status FCT Linac & TL1 Control Room Organization

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Beam Orbit Control Room Organization

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Alarm Survey Application

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Booster injection & extraction Application

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Hardware architecture Supervision/Control CONTROL BOX

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 binding generic applications Machine Physics Device TANGO software bus Monitoring Equipments Device Configuration Archiving Devices TANGO binding MATLAB, IGOR, python, Labview JIVEDEV TREE Magnet power suppliesMotors Globalscreen Graphic User Interface 3 major tools used Software architecture TDB - HDB Flow meter Fault NO Fault

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 ELOG (ELectronic LogBooks) Making an entry for single event Attachement File

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Acquisition data Compilation (MTBF, breakdowns,…) Extraction results in Excel Extracted data from ELOG in Operator JAVA Program Post processing

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Automatic Excel file creation Sharing out of the effective beam time = 558h24 About the whole run From 2007, May the 25th to 2007, Jun the 20th Breakdowns total time = 171h01 About the whole run From 2007, May the 25th to 2007, Jun the 20th Accelerator physics time Mixed time Beam lines time Health physics time

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Number of lines that take beam per day, during 4th Run of to 8 lines used the beam of photons regularly Eventually: 25 Beamlines

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Balance - sheet In year 2006, over the 2084 operating hours The availability of the beam represented 83.5 % of total time, with 11.2 % of time of breakdowns and 5.3 % of time of injection, preparation of manipulations, or interventions In year 2007, From January to July, 93.8% of the 1426 total hours of beam were delivered to beam lines

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 planned of operation of the year 2007 Planned Objectives L 3096 hours Beam Lines hours Beam Lines M 1800 hours Machine hours Machine hours Shutdown L M

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 CONCLUSION AND MAIN OBJECTIVES FOR EARLY 2008 The SOLEIL accelerator complex is now fully operational. The transition from the commissioning phase to the operation phase went smoothly, thanks to: –The strong implication and participation of the operation group during the commissioning of the machine. –Significant efforts from the machine physics groups and from the different groups in charge of equipment to transfer their knowledge to the operation crew. –The machine availability already reached 93.8 % over the 1521 hours of beam time delivered to the beamlines during the first 7 months of We are now aiming at increasing further this availability. The next objectives set-up for 2008 are: –500mA operation (with second cryomodule) –Preparation for top-up operation –Single bunch and 8 bunches operation –Secure beam stability with many insertion devices –Increase beam availability.

Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007 Operator’s Team Operation manager Engineer