Outages During the Run Coping with the Power Company August 9, 2012.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Maintenance and Accelerator Support RHIC Run 12. RHIC species change completed: Major works in RHIC: Major works in RHIC: Power supply reconfigure (DO.
Systems Availability and Business Continuity Chapter Four Prepared by: Raval, Fichadia Raval Fichadia John Wiley & Sons, Inc
WAO Travis Shrey RHIC Machine Specialist Collider-Accelerator Dept Brookhaven National Laboratory 10/30/2014.
K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
Accelerator Support and Maintenance Run 14. Maintenance/Changeover Day Major efforts RHIC: Major efforts RHIC: Access hrs. Access hrs.
Accelerator Support and Maintenance Run 14. Maintenance Tomorrow Major efforts RHIC: Major efforts RHIC: Access hrs. Access hrs. RA.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Care Home Forum 19 th May 2015 Sarah Chittock – Merton Civil Contingencies Officer Taryn Milton – Emergency Planning Manager – Epsom St. Helier.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Maintenance and Accelerator Support RHIC Run 12. Accelerator Status: Complex is running for Physics. Complex is running for Physics. Checkout for NSRL.
1 Near-term machine performance — The next 5 years, before e-cooling — Wolfram Fischer Run Coordinator for RHIC Run-4 Open Meeting on RHIC Planning Berkner.
AGS Polarized Proton Development toward Run-9 Oct. 3, 2008 Haixin Huang.
1 QM2006 D.I.Lowenstein RHIC : The Path Forward Presented to Quark Matter 2006 Shanghai, PRC Derek I. Lowenstein Brookhaven National Laboratory November.
AGS PP Progress Haixin Huang January, 3, Haixin Huang2 Daily Activities of Last Week 12/19 Difficulty to bring beam into Booster. Source only pulses.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Maintenance and Accelerator Support RHIC run10. Last Wednesday: Nice recovery Nice recovery Good work all especially: Good work all especially: HP, RF,
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
Introduction to availability modelling in ELMAS Arto Niemi.
1.  Mission: Improve and operate accelerators, support the experimental program, and design and construct new accelerator facilities in an environmentally.
DESY: From High Energy Physics to Synchrotron Radiation Accelerator Operation in a changing Environment Michael Bieler DESY: From High Energy Physics to.
Accelerator Support and Maintenance Run 14. Maintenance Tomorrow AGS hrs CA Specific Jobs only. AGS hrs CA Specific Jobs only. RHIC.
Maintenance and Accelerator Support RHIC Start Up 12.
Maintenance and Accelerator Support RHIC StartUp10.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Maintenance and Accelerator Support RHIC Start Up 12.
May 4, 2010 EBIS ARR Jim Alessi May 4- 7, 2010 Pre-commissioning and Commissioning.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
May 06, 2013 Photo by Greg Vogel. Thursday, April 18, some tunnel work had to be suspended and many planned jobs had to be postponed due to the flooding.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
Run 12 RHIC Machine/Experiments Meeting 28 Feb 2012 Agenda: Discussion - when to end the 200 GeV pp run… presently scheduled to end early Friday morning,
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
Collider-Accelerator Department EBIS Commissioning Accelerator Readiness Review (ARR) Conduct of Operations Administrative Controls Ray Karol May 2010.
1 AGS RSVP Review 4-5 November 2004 Upgrade and Operations Cost & Schedule Summary Philip Pile Collider-Accelerator Department 4 Nov 2004.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
Run 12 RHIC Machine/Experiments Meeting 17 Apr 2012 Agenda: Status reports Polarization issues update (E. Aschenauer) Other business With 17 April update.
Feb. 23, 2005Wednesday Experiment Meeting BNL, Upton Status on AGS cold snake  Cold mass is now in the cryostat. It is in the phase of wiring, and because.
Maintenance Nov 28, Accelerator Access LINAC will remain on RA. It is not yet running. LINAC will remain on RA. It is not yet running. Booster-
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
AGS Run-9 Preparations, Status and Plans Dec. 16, 2008 Haixin Huang.
Run 12 RHIC Machine/Experiments Meeting 24 Apr 2012 Agenda: Status reports Other business.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
BooNE Meeting, January 15, Prebys 1 How are we doing? Best running Power loss (W) Protons (p/min) Energy Lost (W-min/p) Best running again ? Mysterious.
Accelerator Support and Maintenance Startup for Run 13.
Time Meeting March 29, W. Christie Blue Ring Magnet String issue: -on Friday morning 7am (18 March 2016) a problem developed in the RHIC Blue ring.
1 AGS RSVP Review 4-5 November 2004 Management Issues Philip Pile Collider-Accelerator Department 4 Feb 2004.
“New and Improved”: The JLab (state-of-the-art) HCO System Dr. Ken Baggett Engineering Support Liaison to Operations At least until the next guy talks…
Accelerator Support and Maintenance Startup13. Access LIPA work Friday LIPA taking feed for Booster MMPS down for emergency repair. LIPA taking feed for.
1 RHIC NSRL LINAC Booster AGS Tandems STAR 6:00 o’clock PHENIX 8:00 o’clock 10:00 o’clock Polarized Jet Target 12:00 o’clock RF 4:00 o’clock (AnDY, CeC)
A RHIC Low-Energy Test Run With Protons Todd Satogata (W. Fischer, T. Roser, J. DeLong, M. Brennan, D. Bruno, and others) April 11, 2006 Driven by discussions.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Maintenance and Efficiency
NERC Published Lessons Learned Summary
Machine operation and daily maintenance management in SOLEIL
Automatic emittance measurement in the CERN 1.4 GeV Booster
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Optimization of JLEIC Integrated Luminosity Without On-Energy Cooling*
Presentation transcript:

Outages During the Run Coping with the Power Company August 9, 2012

CAD:  RHIC (Relativistic Heavy Ion Collider) is part of the CAD (Collider Accelerator Department) at Brookhaven National Laboratory, Upton New York, USA.  The facility is comprised of three pre-injectors (Proton LINAC, EBIS and a Tandem van De Graaff, a Booster, a post booster (the AGS) and RHIC itself.  In addition to the primary purpose of providing beam for injection into RHIC, injectors provide beam for various secondary users: Brookhaven Lab Ion Production (BLIP): Protons from 200 MeV LINAC NASA Space Radiation Lab (NSRL): Slow extracted Protons and Ions from 2 GeV Booster to user facility August 9, Paul W. Sampson

RHIC Background:  Relativistic Heavy Ion Collider- species from protons to Uranium.  Two 3.8km SC rings, warm RF (SC upgrade in progress), 6 Intersection regions.  Ability to run dissimilar species.  Polarized proton collisions at 510GeV CM August 9, Paul W. Sampson

August 9, Paul W. Sampson

Power outages during Run 11 and 12  Scheduled work on the electrical grid, both inside and outside of the laboratory was originally planned to be completed during the shutdown periods following runs 11 and 12.  This work included upgrades to aging/outdated equipment as well as increasing capacity for the laboratory.  During the work, it was required that the feed for the Booster Main Magnet Power Supply remain off.  For various reasons, the work was not completed until each run had begun. August 9, Paul W. Sampson

Dealing with the power company  With the program was running, increased work coordination from Operations was necessary..  Communication and coordination between the Utility company, Facilities and Operations (F&O) and Operations was key to success.  Not only are emergencies unpredictable, but the general and long term Utility Company’s schedule is not readily available (to anyone?).  All of the information from the Utility was relayed to CAD second hand through F&O.  This was frustrating… August 9, 2012 Paul W. Sampson6

Scheduling:  Ideally, work that can interrupt Accelerator Operations must be completed during shutdown.  Conflict between the Lab and Utility schedules. Vacation at the lab and Utility coincide with shutdown (summer). Job cancellation: weather, failure, car accidents. Job Interdependence, waiting for the other guy. Other?  The result is that the utility company “requested” shutdowns during “the worst possible” times.  In Addition, complications arouse, adding more periodic shutdowns throughout the run. August 9, Paul W. Sampson

Work Planning:  Many fold and complicated: F&O, Utility company, Operations, Operations support groups…  Overall plan must include measures for shutdown and recovery of not only the accelerators, but services and support systems.  CAD administration, Operations, Accelerator Physics and Experiments determine the best schedule- studies, commissioning, special runs.  Repairs, maintenance, commissioning and/or installation to coincide with beam outages.  Each shutdown was designed to resemble a mini- shutdown. August 9, Paul W. Sampson

Step back: Power at CAD  Dedicated power feeds are critical for accelerator operations: CAD/RHIC complex requires ~35MW, the laboratory ~55MW total. Two Feeds: “Primary” and “Alternate”  A “Stiff grid” is essential to both private sector and laboratory: Power swings of many MW as large magnets pulse. AGS Booster ~3 MW swing. Harmonic content critical, risk of equipment damage/shutdown. Cross talk and power disruption to others. August 9, Paul W. Sampson

A little background, continued:  The Booster Main Magnet Power Supply uses 13.8kV AC off the BNL grid (i.e. coupled to the Utility grid).  Therefore, Booster operation must be carefully regulated and monitored.  Crosstalk “Solution” = use both available 69 kV feeds- “Primary” and “Alternate”.  The Alternate Feed is dedicated to run the Booster MMPS only, while the rest of the lab runs off the Primary Feed.  When work must be done on either line, the Booster cannot run. August 9, Paul W. Sampson

Booster cycles, harmonics, power August 9, Paul W. Sampson

Harmonic analysis- critical for operation August 9, Paul W. Sampson

69kV Feed- Normal positions August 9, Paul W. Sampson

“Alternate Feed” – No Booster August 9, Paul W. Sampson

Outage: Run 11  Work was originally scheduled for completion during the shutdown.  “Surprise” need for outage during early setup for NSRL run 11a and RHIC. Some affect of the schedule, though no cancelled experiments. Need for late outage, apparently known to the utilities company, was not relayed to BNL until startup was already underway.  Through scheduling and preparation, the impact of the 2011 outage had minimal (no) affect on the RHIC program.  Luckily it was a one time deal! August 9, Paul W. Sampson

2012 shutdowns:  Uncertainty again with last minute scheduling by Utility company.  Surprise discovery during pre-job inspection.  Downtime during critical startup period. Reduced Machine development critical for polarized proton development. Delays in commissioning of EBIS beams in the Booster needed for NSRL and RHIC.  Collider schedule and performance impact.  Cancelled, rescheduled ad delayed experiments at NSRL. August 9, Paul W. Sampson

December 2011  Dec 19 th : Utility company informs BNL that that they have not completed scheduled work. Additional shutdown necessary to complete planned upgrades. “Agreement” reached to schedule with Operations to reduce the impact of the outage.  Dec 20 th : Utility performs pre-job inspection and discovers an issue requiring immediate attention. An emergency outage scheduled. August 9, Paul W. Sampson

Alternate feed with Booster- Not used August 9, Paul W. Sampson

August 9, Paul W. Sampson

August 9, Paul W. Sampson

December 21 st : Before the RHIC run  Operations prepares for outage hrs. Equipment secured. Opportunistic maintenance schedule executed. Scheduled NSRL experiments delayed and or cancelled.  Utility company begins work (1000hrs!).  Beam activities and NSRL experiments suspended for the day.  1530hrs Utility company work completed. Booster restored by 1600hrs. Setup continues, NSRL runs abbreviated schedule.  “Emergency” situation resolved, shutdown scheduled for April 19 th (Changeover date). August 9, Paul W. Sampson

April 19: Changeover to Uranium  0700hrs: Prep for scheduled outage begins after RHIC filled for extended store.  0800hrs: Power outage/injector maintenance begins, proton store in RHIC for studies continues.  0815hrs: RHIC store lost! Commission Uranium ramp – no tunnel access. Experimental access begins  1100hrs: Maintenance in RHIC begins.  1530hrs: Power restored, begin U setup and NSRL experiments.  Next outage scheduled for April 24. August 9, Paul W. Sampson

Re-scheduling  April 24 th : Utility company cancels outage scheduled for the 25 th.  Re- schedule for May 9 th (Scheduled Maintenance Day).  NSRL informed- Experiments originally scheduled were not cancelled (they were getting smart).  April 25 th : Utility company must shutdown before May 9 th:  Re-rescheduling necess ary… August 9, Paul W. Sampson

And More Changes…  Agreement reached: Saturday April 28 th. NSRL not running scheduled on Saturday. Planned extended store in RHIC. No maintenance (overtime) scheduled. Experimental access scheduled between stores.  Minimal impact: Good luck never hurts.  Work still not complete… Re-re-re-schedule?  May 9 th outage (re)scheduled. August 9, 2012 Paul W. Sampson24

August 9, Paul W. Sampson

May 9: Scheduled Maintenance day  Abbreviated NSRL schedule cancelled.  Extended store, beam measurements scheduled in RHIC until early afternoon.  Scheduled maintenance in injectors throughout the day.  Installation and testing of new phase shifters to the RHIC power supply completed during and after maintenance while awaiting beam.  Recovery complicated and delayed by problems introduced by weather related power dips that occurred before the shutdown- Bad luck. August 9, Paul W. Sampson

Schedule for minimal impact: August 9, Paul W. Sampson

Speaking of bad luck… August 9, Paul W. Sampson

Overall Results  Efforts to minimize the loss to the RHIC program were successful, though some pain was felt by other users.  With some diplomacy and communication, some flexibility can be worked into the Utility company’s schedule.  Structured preparation and execution of complex shutdown and restart reduces the program loss. August 9, Paul W. Sampson

Planned shutdown and recovery:  Equipment unaffected by the outages were readied for operation prior to the restoration of power.  Specific plan and steps for recovery followed by multiple groups, divisions and companies proved effective in recovering the program.  BNL F&O personnel well prepared for power restoration.  System experts, Operations well prepared for accelerator recovery.  Shutdown recovery methods aided in overall complex recovery. August 9, Paul W. Sampson

Fallout  For the last two runs, disruptions arouse from last minute or “emergency” outages.  Stress in the relationship between the lab and utility company.  NSRL Experimenters and BNL liaisons: Reduced confidence.  Burden on Operations increased by complications before, during and after the outage.  Off hours work and ECI’s ($$$).  Decreased efficiency. August 9, Paul W. Sampson

How to improve?  Engineering Solution: single point failures: Initial design. Add Booster filtering $$$  Coordination: Create better flow of information between CAD, F&O and the power company- Web? Tweet? Ensure outages are planned to occur during shutdown!?  Communication  Communication…  Communication!!! August 9, Paul W. Sampson

Conclusions  With domain over the power at the lab and for the accelerators, we are subject to the outside utility’s scheduling.  By improving communication with the power company, delays and other problems may be avoided.  When known work on the grid is planned, always have alternate plans ready for outages during the run.  Continued upgrades to the electrical systems at the lab makes it necessary to deal with the power company… August 9, Paul W. Sampson

Thank you! August 9, Paul W. Sampson