CenterPoint Energy Houston Electric 2011 Response to Contamination Conditions John Kellum Director of Transmission Operations August 3, 2011.

Slides:



Advertisements
Similar presentations
Commissioning, Maintenance, and Troubleshooting
Advertisements

Building A Smarter Grid Through Distribution Automation DOE Projects OE & OE April 2013 Copyright © 2012 Consolidated Edison Company of New.
Spencer Murray, Sr. Telecom Eng. Distribution Automation.
Startup Training – TPS3 15. Siemens TPS3 Startup Training 2 Topics Covered  Visual Inspections  Verify environmental requirements are met  TPS3 15.
Restoring and protecting Louisiana’s coast Barrier Plan June 16, 2010 Kyle Graham Deputy Director of Planning and Programs Office of the Governor – Coastal.
Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr.
New Product Overview Homac STORM SAFE™ Connector Systems Presented by: Presented by: Roy Jazowski - Director of R&D Mark Hammer – Director of Marketing.
1 March 1, 2007 Report An Overview October 30, 2006 – Staff Workshop.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
Controlling Hazardous Energy
The effect of contamination on insulator flashover characteristics
Chapter 7 SYSTEM PROTECTION
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
E8 / PPA Solar PV Design Implementation O&M Marshall Islands March 31-April 11, Field investigation Installation site confirmation Roof-mounted.
1 Entergy Transmission Asset Preservation Department 2004 Objectives Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
AFCI Reaction to Utility Events. CenterPoint Energy 35 KV Distribution Capacitor Bank – Switched through an automated system.
Smart Grid Technologies Damon Dougherty – Industry Manager.
Electric Infrastructure Workshop Gulf Power Company January 23, 2006.
SDG&E Electric Reliability Reporting CPUC Workshops May 26-27, 2015.
Contamination Mitigation May 8, 2014 Dan Greenwood Asset Management Consultant.
ERCOT Drought Best Practices Workshop Contamination Issues February 27, 2012.
1 American Public Power Association Session 6 (PMA) September 24, 2007 Uses, Costs, and Implementation of AMR/AMI Herman Millican Austin Energy.
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
Electrical Power Grid. Parts of the Grid: Generation (Power Plants) Transmission Lines Substations Distribution Lines Transformers Customers.
Electrical Fire in Terminal Room at Collider-Accelerator Department Relay-Fire Investigation Committee
1 Overview of Reliability Requirements XYZ Cooperative Date: abc.
Lee County Electric Cooperative 2007 Hurricane Preparedness Activities.
Presentation Identifier (Title or Location), Month 00, 2008 Cost and Benefit Analysis Framework: Update EPRI Smart Grid Advisory Meeting October 14, 2009.
Substation Inspection Program. Mission Substation Incident The event occurred on December 20, 2003 during the peak Christmas shopping season A fire occurred.
FPSC Electric Utility Infrastructure Workshop Florida Municipal Electric Utilities Alan Shaffer Assistant General Manager - Delivery Lakeland Electric.
Using Infrared to Proactively Maintain the Distribution System Ben J Carranza.
Submission Slide 1 Project: IEEE P Working Group for Wireless Personal Area Networks (WPANs) Submission Title: [Smart Grid: Faulted Circuit Indicator]
MNM Fatal Electrical Accident Electrical Accident October 10, 2010 (Oklahoma) October 10, 2010 (Oklahoma) Granite Operation Granite Operation Contract.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Electric Utility Infrastructure Commission Staff Workshop January 23, 2006.
Jesus A. Guerra, P.E. Distribution System Reliability CenterPoint Energy SWEDE 2011.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
OCTOBER 2, 2013 Maine 2013 Outage Coordination Redacted Copy.
An Ice Blaster is a Portable Machine which Uses CO 2 Pellets to Clean Energized Equipment Power Source is a 120V Generator and Diesel Powered Air Compressor.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
2015 HURRICANE SEASON PREPARATIONS March 18, 2015.
2014 Hurricane Season Preparation Informal Meeting for Electric Utilities with Florida Public Service Commission Staff March 26, 2014.
2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of.
Tampaelectric.com Presented to the Florida Public Service Commission May 1, 2008 Tampa Electric Company 2008 Hurricane Season Preparation Regan Haines.
A PRESENTATION On 400KV GSS SURPURA JODHPUR
MNM Fatal Electrical Electrical November 18, 2013 (Kentucky) November 18, 2013 (Kentucky) Crushed Stone Mine Crushed Stone Mine Contract Electrician.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
Recreation & Security HPR 413. General Security Must encompass all operations of the organization Should be written into management plans – Plans include.
Survey of Smart Grid concepts and demonstrations Smart substation Ari Nikander.
Maryland Public Service Commission 2006 Summer Reliability Status Conference May 16, 2006 Baltimore, MD.
Panoramic Power and the Panoramic Power logo are trademarks of Panoramic Power Ltd. Other trademarks are the property of their respective owners. The Panoramic.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
Florida Keys Electric Cooperative Association, Inc. Storm Hardening Florida Public Service Commission May 1, 2008 Scott Newberry, CEO John Stuart, COO.
Maryland Public Service Commission 2005 Summer Reliability Status Conference May 9, 2005 Baltimore, MD.
CURRENT ® Smart Grid Overview July SMART GRID = ENHANCED FUNCTIONALITY Smart Grid delivers more than advanced metering infrastructures: -safe.
Utility Needs and Smart Grid for Major Storm Events
Impact of Hurricane Ike on
Predictive-Based Maintenance Strategy
Compliance Report to ERCOT TAC February 2007
OSHA’s Final Rule: Electric Power Generation, Transmission, and Distribution Electrical Protective Equipment Presented to: RESAP Area Administrators Presented.
Pacific Power Seismic Preparedness Update
Distribution Circuit Automation Scheme Design
AGA Distribution Best Practices Program Control Room Management
Use of Lightning Data for Electricity Transmission Operations
2007 Hurricane Season Preparedness Briefing
Control of Hazardous Energy
Public Safety Power Shutoff (PSPS)
Presentation transcript:

CenterPoint Energy Houston Electric 2011 Response to Contamination Conditions John Kellum Director of Transmission Operations August 3, 2011

Timeline of Initial Contamination Events Morning of April 25, Instantaneous operations on transmission circuit 63 from Stewart - Moody - West Galveston Substations. Evening of April 26, circuit 63 from Stewart - Moody - West Galveston locked out due to multiple operations. Substation crews were sent to man the island substations and feeds to the island. The line terminals that were de-energized were washed by hand. Also our crews inspected all island substations. Morning of April 27, circuit 63 from La Marque - Stewart locked out. The Stewart, Moody, and West Bay Substations lost service impacting 12,000 customers. Also, circuit 93 Hitchcock to West Galveston locked out, but there was no loss of distribution service. That same morning transmission crews washed and replaced suspect insulators on the previously identified hot spots on circuits 63 and :25 on April 27, Circuit 63 from La Marque - Stewart was restored. 02:00 on April 28, Circuit 63 from Stewart - Moody - West Galveston was restored after damaged insulators in the Moody Substation were replaced. Once these circuits were energized, corona camera patrols were performed and no activity was indicated. West Bay, Stewart and Moody Substations were patrolled with the corona camera also and no activity was indicated. 2

Insulator Damage 3 Flashed Moody Substation

WEATHER IMPACTS IN APRIL

WEATHER IMPACTS IN MAY

WEATHER IMPACTS IN JUNE

EXISTING PREVENTATIVE MEASURES CenterPoint Energy uses the following preventive or protective measures to address contamination issues regarding its transmission lines. –Use of several technologies of transmission and substation insulators that are designed for heavy salt contamination, including special ceramic resistive glazes and silicone rubber products. –Installation of Traveling Wave System fault locating technology on several transmission circuits that border the coastline as part of a multi-year, system-wide deployment plan. –A comprehensive transmission and substation inspection and maintenance program coupled with a transmission vegetation management program. –Specialized daytime corona camera inspections of the transmission system targeted to start in May each year and continue through the summer months when high contamination conditions are usually prevalent. Similar inspections of substation equipment are performed quarterly throughout the year. In addition, generator bays are inspected before and during peak. 7

ADDITIONAL PREVENTATIVE MEASURES CenterPoint Energy implemented or accelerated the following targeted inspection, maintenance, and service restoration plans to address the abnormal contamination issue. –Established proactive energized and de-energized transmission insulator washing crews as follows:  2 contract helicopter crews for energized washing  Each helicopter crew has the capacity to wash 50 to 100 structures per day, subject to limitations from prevailing winds.  2 contract bucket crews for energized washing 1 contract ground crew for de-energized washing 6 in-house ground crews for de-energized washing  Each bucket and ground crew has the capacity to wash 10 to 30 structures per day, subject to limitations from right-of-way accessibility. –Established proactive de-energized substation insulator washing crews as follows:  4 in-house ground crews for de-energized washing  Each ground crew has the capacity to wash 3 substation line terminals per day. 8

ADDITIONAL PREVENTATIVE MEASURES –Established an insulator washing plan  Wash all transmission lines on Galveston Island using helicopter- mounted washing rigs and manual crews and wash all substations on Galveston Island using manual crews to provide long term performance of the insulators until the natural rain washing cycle begins and re-establishes at the necessary frequency.  Special, high capacity, de-ionized water filter systems have been deployed at three substations across the southeast region of the transmission system, including Galveston Island, to provide the necessary water for energized washing of insulators that will allow transmission lines to remain in service during the washing process.  Utilize helicopter patrols on long distance lines to quickly identify insulators in need of washing or replacement on circuits that are presenting significant flashover potential 9

ADDITIONAL PREVENTATIVE MEASURES –Elevated patrol response to momentary transmission circuit operations  Accelerated from a next day patrol to an immediate patrol based on established call-out procedures.  Request immediate fault recorder information for all momentary outages on an accelerated response time if the circuit is not already covered by a Travelling Wave System that provides an immediate automated fault location.  Visually inspect substations before sunrise to identify insulators in need of washing on substation structures that are presenting significant flashover potential. –Accelerated specialized daytime corona camera inspections of transmission lines to verify which insulators require washing and to verify the adequacy of the washing done. –Established a response plan for washing generator leads on transmission-class towers as sites are identified and scheduled. 10

FURTHER INITIATIVES CenterPoint Energy has the following longer term, related initiatives to further mitigate this contamination issue. –Re-design polymer insulators for the Gulf Coast Region for improved contamination performance.  CenterPoint Energy and the Electric Power Research Institute (EPRI) recently completed a two-year study in January 2011 on polymer insulator designs for the Gulf Coast Region.  As a result of the study, CenterPoint Energy, EPRI, and a major insulator manufacturer have been working on a new design insulator that is targeted for a 3.8 mile trial installation on Galveston Island. –Implement a pilot research and development project with EPRI in 2011/2012 to establish a proactive transmission line insulator leakage current monitoring system.  Sensor technology will be investigated for possible deployment with a coupled communication system to make real-time readings that could then be translated through software to indicate when the optimum time to wash insulators is approaching. 11

INSULATOR WASHING MAP 12

WASHING AND REPLACEMENT STATISTICS 13 Circuit Washing and Insulator Replacements as of 7/25/2011 Total Structures Washed9,919 Insulators per Structure (avg)3 Total Insulators Washed29,757 Total Structures with Replaced Insulators105 Total Insulators Replaced371

WASHING AND REPLACEMENT STATISTICS 14 Total Substations Washed40 Total Generating Positions Washed13 Total Line Positions Washed20 Total Insulators Replaced11

HELICOPTER WASHING 15

HELICOPTER WASHING 16

BUCKET WASHING 17

18 Questions