NS Rickenbacker Norfolk Southern – The Thoroughbred of Transportation Chris Luebbers
The Heartland Corridor Norfolk Southern – The Thoroughbred of Transportation
Norfolk - Midwest
The Heartland Corridor Projects: Mainline Clearance Project: $150mm Heartland Route requiring no improvements Roanoke, Terminal $22mm Prichard, WV Terminal $19mm Central Corridor Total $191mm Government Funding Federal $95mm Ohio $1mm Virginia $22mm West Virginia $15mm Total Government$133mm Columbus Rickenbacker, Terminal The Heartland Corridor
Heartland Corridor: Central Corridor Double-Stack Project Scope 28 Tunnels 30,000+ feet to be Cleared Virginia, West Virginia and Kentucky 24 Overhead Obstructions Bracing Modifications, Fencing Modifications, Overhead Wire Removal, Miscellaneous Signal Work West Virginia and Ohio
Central Corridor Double-Stack Project: The current clearance envelope through West Virginia only accommodates railcars up to 19’1” multi-levels. No double-stack cars can be accommodated in West Virginia due to the height, as well as the square profile of the conveyance.
Rickenbacker Intermodal Norfolk Southern – The Thoroughbred of Transportation
Columbus Rickenbacker Intermodal Terminal 225 Acres 12,000’ Support Track 1,800 Wheeled Parking Spots 450 Stacked Spaces (2 high) Annual Lift Capacity 250,000 Ground Broken September 2006 First Train: March 3, 2008 Estimated Cost: $61 Million
Rickenbacker Benefits Support and Pad Tracks Improved Terminal Design Expanded Parking Automatic Gate System (AGS) Proximity to Rickenbacker Complex