Opportunities and Incentives for CHP in Massachusetts Interconnection Procedures June 19, 2013 Tim Roughan.

Slides:



Advertisements
Similar presentations
Definition of Firm Energy and Interruptible Transmission Two Issues Causing Problems for Business in the Western Interconnection.
Advertisements

Revised Draft1 Distributed Generation Interconnections - Group Study Process Option: Voluntary Rolling Window Presented to Massachusetts Distributed.
Distributed Generation (DG)
Summary of Customer Service Rules for Low-Income Electricity Customers Paul Gasparatto Policy Advisor.
DOD Microgrids The Missing Link: Microgrid Applications Michael Dempsey P.E. Burns & McDonnell June 12, 2013 © 2013 Burns & McDonnell. All Rights Reserved.
Interconnection of Distributed Generation and Net-Metering in MA Tim Roughan National Grid.
SRC Application Process Fall 2014 Version: November 12, 2014.
1 EERMC Public Meeting on Combined Heat and Power September 17, 2013.
Net Metering and Interconnection A Policy Perspective Brad Klein Staff Attorney Envt’l Law & Policy Center March 28, 2007.
Interconnection of Distributed Generation
BIOENERGY SYMPOSIUM 2013 ANAEROBIC DIGESTION Regulations Ollie Frazier, P.E., MBA.
Practical Ways For Towns to Save Money With Clean Energy Projects Paul Michaud Murtha Cullina LLP April 30, 2014.
PG&E’s General Market Virtual Net Metering Schedule NEMV
Welcome and Introductions CoServ Presentation & Member Input.
Small Farm Profitability: Is Wind Energy the Answer? 1
Genesis Solar Module Brochure ™
Interconnect Protection of Dispersed Generators
Topics to Cover Interconnection Process Overview
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
Interconnection of Small Wind & Solar Systems to Distribution Utilities: A Cooperative Perspective Patrick Parke Midwest Energy Hays, KS September 26,
Creating A Cleaner Energy Future For the Commonwealth Focusing on Solar PV: Technology, Siting Considerations, Incentives Natalie Andrews Renewable Energy.
Turkish Power System Overview March 2012
Summary Overview: MADRI Model Small Generator Interconnection Procedures Prepared by Brad Johnson* June 15, 2006 ACN Energy Ventures
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
Technical Conference on Net Metering Load Research Study November 5, 2014.
Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007.
> 30 kW Interconnection Work Group Meeting June 19, 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Small Renewable Generators Tony Marciano Public Utility Commission of Texas May 2, 2007 (512)
Storm Hardening Workshop Docket No Verizon Florida, Inc. July 13, 2006.
OSC Meeting April 27, Transmission Cost Allocation Overview.
1 Bilateral Interconnection Agreement Model Presented to HAPUA Working Group 5 (ESI Services), Project 6 By Power Purchase Agreement Division Electricity.
Demand Response: Keeping the Power Flowing in Southwest Connecticut Presented by: Henry Yoshimura Manager, Demand Response ISO New England September 30,
AmerenUE SHOW ME SOLAR June 15, 2010 MISSOURI NET METERING AND SOLAR REBATE PROGRAM Lisa Cosgrove – Renewables Specialist.
Net Metering and Embedded Generation NB Climate Action Change Hub Advisory Committee Meeting – October 1, 2008 Saint John, NB Linda Berthelot.
Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.
Renewable Generation Interconnection Ken Brunkenhoefer Distributed Generation Consultant
05/18/001 N.Treadway Distributed Resources and Competitive Energy Markets in Illinois Workshop Session III, “Interconnection Issues” Thursday, May 18,
Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009.
The Energy Policy Act of 2005 and Its Revisions to PURPA November 11, 2005 Grace D. Soderberg Assistant General Counsel National Association of Regulatory.
PJM© Demand Response in PJM 2009 NASUCA Mid-Year Meeting June 30, 2009 Boston, MA Panel: Price Responsive Demand – A Long-Term Bargain.
Demand Response: What It Is and Why It’s Important 2007 APPA National Conference San Antonio, Texas June 26, :00 a.m. to Noon Glenn M. Wilson Director.
San Marino Unified School District Contracts Presentation Presented by: Wesley Lee, Budget Analyst October 28, 2015.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Lead from the front Texas Nodal 1 Registration Market Call Mar 27, 2009.
Outage Planning Subcommittee Mark Wilson. Outage Planning Subcommittee Created to address Market Participant concerns with existing rules and procedures.
Distributed Generation Registration June 30, 2008.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. Southwest Connecticut RFP Markets Committee November 14, 2003.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
BIDDER’S CONFERENCE: Eskom Grid Connection Process and related matters Date: 16 August 2012.
Solving the Energy Puzzle Understanding the Rules of Energy Delivery Electricity Natural Gas Tariffs Solar Combined Heat and Power Generation Distribution.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Community Solar, Remote Net Metering, and Behind the Meter Solar Update Solar Progress Partnership* Summary of April 18, 2016 Comments The Solar Progress.
ROMANIA NATIONAL NATURAL GAS REGULATORY AUTHORITY Public Service Obligations in Romanian Gas Sector Ligia Medrea General Manager – Authorizing, Licensing,
Summary Overview: Maryland Straw Man Interconnection Rule Prepared by Brad Johnson* January 11, 2007 ACN Energy Ventures *National.
UTC STUDY OF DISTRIBUTED GENERATION AND RECOMMENDATIONS Presentation for the Washington Future Energy Conference October 19, 2011.
Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September
Direct Participation Enrollment Process for 2017 DRAM
The New Texas Wholesale/Retail Market
The Future of Demand Response in New England
Current as of 12/12/2017 RES-BCT.
GMD Data Request NERC Rules of Procedure Section 1600
Collaborative Results Restructuring Roundtable March 28, 2003
Net Metering John McComb: P.E.
Net Metering John McComb: P.E.
NYS Department of Public Service
SMART Program Specific Metering Wiring Diagrams May 2019
MA DG Collaborative – Year 1
Presentation transcript:

Opportunities and Incentives for CHP in Massachusetts Interconnection Procedures June 19, 2013 Tim Roughan

Agenda MA interconnection process Federal Energy Regulatory Commission (FERC) interconnection process at ISO-NE Appendix – Technical considerations Appendix – Net metering in MA

Safety Moment This morning’s session provides a great safety moment. – All the benefits derived from Distributed Generation quickly lose their value if someone is injured as a result of an improper interconnection.

DG Activity Trends – National Grid Received over 491 applications worth more than 77 MW of interconnection applications in Q (Last year estimated 1,811 apps, actual was 2086) Small (<100kW) Interconnection application are triggering large studies because of the aggregate generation on the circuit. More projects are in construction phase Some circuits have over 20 interconnected generators 4

Massachusetts Interconnection Standard In late 2002, the MA DTE directed the investor owned utilities to commence a collaborative process to propose unified interconnection standards, policies, and procedures for distributed generation. In 2009, DPU approved tariff that included net metering provisions. In the summer of 2012, DPU convened a Distributed Generation Working Group (DGWG) to recommend improvements to the MA DG Tariff. The DGWG, comprised of utility, state and DG community stakeholders, reached consensus on all but one issue and the DPU approved the revised tariff on 3/20/13 and went into effect May 1, This interconnection standard covers all forms of generation operating in parallel with the grid (it does not apply to emergency generation). 5

What is the Interconnection Process? Process of getting an interconnection agreement from your local utility (or distribution company) to connect a distributed generation system to their distribution system. This process is used by the four investor owned utilities (IOU) in Massachusetts (NSTAR, National Grid, Unitil and Western Mass Electric) Municipally-owned utilities are not required to follow this process, and may follow a different criteria. The process is used to make sure interconnecting DG systems are integrated into the distribution system responsibly with respect to impacts on reliability, power quality and safety Can not allow DG to affect neighbors on feeder 6

Importance of the Interconnection Process for CHP Following the interconnection process is important because a DG system changes the one-way power flow from the utility to customer, which can present dangers to utility workers if proper equipment is not installed While robust and capable of handling minor disturbances, the quality of grid power is extremely important. The interconnection process ensures the DG meets safety, reliability, & power quality requirements with regard to: Islanding Transient Voltage Conditions Noise and Harmonics Frequency Voltage Level Machine Reactive Capability It is essential that each interconnection get an interconnection agreement with the utility before installing any generation. You are proceeding at your own risk if you choose to install a system without utility approval. 7

Pre-Application Report Contact Person: Mailing Address: City: Telephone ; Address Alternative Contact Information (e.g., system installation contractor or coordinating Facility Information: Proposed Facility Location (street address with cross streets, including town, and a Google Map still picture and GPS coordinates): Generation Type: Size (AC kW): Single or Three Phase Generator Configuration: Stand-alone (no on-site load, not including parasitic load)? If there is existing service at the Proposed Facility site, provide: – Interconnecting Customer Account Number – site minimum and maximum (if available) current or proposed electric loads Minimum kW: Maximum kW: Is new service or service upgrade needed? Circuit voltage at the substation; Circuit name; Circuit voltage at proposed Facility; Whether Single or three phase is available near site; If single phase – distance from three phase service; Aggregate connected Facilities (kW) on circuit; Submitted complete applications of Facilities (kW) on circuit that have not yet been interconnected; Whether the Interconnecting Customer is served by an area network, a spot network, or radial system; Identification of feeders within ¼ mile of the proposed interconnection site through a snap-shot of GIS map or other means; and Other potential system constraints or critical items that may impact the proposed Facility. Customer needs to provide: Utility to provide:

9 Everything starts with the Application A complete complex application package includes: – All appropriate sections of 4-page application completely filled out. Customer will likely need assistance from vendor/engineer. – Copy of Pre-Application Report – Application fee $4.50/KW ($300 minimum and $7,500 maximum). This fee covers the initial review. (Proposed change in 2012 raises these costs) – Stamped electric one-line diagram, preferably showing relay controls (one copy) (Stamped by Massachusetts Electrical PE) – Site diagram (one copy) – One copy of any supplemental information (if electronic – single copy acceptable) – Identify electric customer and owner of proposed generation – Schedule Z if planning to Net Meter Errors or problems with application will slow down the process and “stop the clock” Send Electronic copy of all documents preferred if possible – Easier to distribute, saves paper, and is faster. However, submit first page of application with application fee.

Applies to: Single phase customers with listed single-phase inverter based systems >15 kW on a radial feed Three phase customers with listed three-phase inverter based systems >25kW on a radial feed. Maximum size is based on review of screens Does not Apply to: Non-listed inverters or other generators (induction / synchronous / asynchronous) Aggregate generation capacity of listed inverters that exceed the above-mentioned limits Expedited Review Path 10

Expedited Review Path Typically little or no (utility) system modifications required. If meter only – usually no charges passed to customer Application fee plus any Supplemental Review charges up to 30 hours of engineering $150/hr (if needed) Relay control system must be well defined to make supplemental review easier. Witness test fee of up to $300 plus travel is required. Table 1 of Section 3 in the Interconnection Tariff 11 Expedited Eligible Facilities Listed DG Acknowledge Receipt of Application (Note 2) (3 days) Review Application for Completeness 10 days Complete Review of All Screens 25 days Complete Supplemental Review (if needed) (Note 3) 20 days or Standard Process Send Executable Agreement (Note 4) 10 days Construction Schedule By Mutual Agreement Total Maximum Days (Note 5) 40/60 days (Note 6) Notice/ Witness Test < 1 day with 10 day notice or by mutual agreement

12 Supplemental Review If one or more Screens are not passed, the Company will provide a Supplemental Review Agreement. Threshold is whether project is less than 67% of minimum load on the feeder – Then other screens review voltage quality, reliability and safety to reduce the potential need for impact studies. – DPU order allowed for the 67% screen, but requires utilities to document how the use of a 100% screen would change the screening process Customer signs agreement and pays fee for additional engineering time (max fee is now $4,500). The Supplemental Review may be able to determine what impacts the generation system will have and what (if any) modifications are required. If so - an interconnection agreement will be sent to customer detailing: – System modification requirements, reasoning, and costs for these modifications – Specifics on protection requirements as necessary If Supplemental Review cannot determine requirements, an Impact Study Agreement (or equal) will be sent to the customer. (You shift to the Standard Process.)

Applies to: Non-listed inverters or other generators: Induction Synchronous Asynchronous Other large MW and Multi MW Projects Renewable DG Customers / Developers Standard Review Path 13

Standard Review Path Table 1 of Section 3 in the Interconnection Tariff After initial review and/or supplemental review, customer may need to enter Standard Process Customer can request Standard Process Appropriate study agreement sent for signature and payment Studies could include: – Impact Study: Determine the impact of the new generator on potentially affected systems, including EPS, other customers and other generators – Detailed Facility Study: Determine utility system modifications required and cost ISO notification and possibly Transmission Study if over 1 MW After studies – interconnection agreement sent for signature Witness test fee is actual cost. 14 Standard Eligible Facilities Any DG Acknowledge Receipt of Application (Note 2) (3 days) Review Application for Completeness 10 days Complete Standard Process Initial Review 20 days Send Follow-on Studies Cost/Agreement 5 days Complete Impact Study (if needed) 55 days Complete Detailed Study (if needed) 30 days Send Executable Agreement (Note 3) 15 days Construction Schedule By Mutual Agreement Total Maximum Days (Note 4) 125/150 days (Note 5) Notice/ Witness Test 10 days or by mutual agreement

15 MA – Revised Interconnection Tariff 1 st payment of 25% of estimate is only required within 120 business days of signing an ISA – Estimates are only good for 60 business days and we have the right to re-estimate if customer payment is not received before then – Company is not obligated to order equipment without receiving “adequate payment” as defined in customer’s ISA – Company not required to begin construction prior to receipt of full payment – If payment is not made within the applicable timeframe, the Company shall require the Customer to reapply for interconnection. Increased study times for large projects – Those that require modification at substation Instead of 55 business days for an Impact Study, now have 75 (2013 and 2014), then to 70 (2015), and then 60 (2016) – Projects > $200,000 estimated costs (not including on-site work, metering, recloser, riser pole, etc.) Instead of 30 business day for a Detailed Study, now have 75 (2013 and 2014), then to 70 (2015), and then 60 (2016) – Projects > $1 million, all study timelines are by mutual agreement Require more detailed reporting on project status – For both studies and construction timelines – ISA must include a mutually agreed upon timeline for construction – DPU has asked DG WG to investigate an incentive/penalty mechanism to ensure timeline compliance

16 Timeline Compliance Regulatory obligation for both the distribution company and the customer – Study times are suspended until such time as company receives the requested info from customer – if an applicant requests additional time at or near a milestone, the Company will get additional time to achieve that milestone – if an applicant requests a significant project change -- as determined by the distribution company -- the applicant will be required to submit a new interconnection application – at any time, an applicant may request a review of time-frame compliance by the distribution company, and the distribution company must respond within ten business days – There is a process to remove customers from the “queue” if they don’t abide by the timelines or extensions – Customer can request refund of application fee if the Company does not comply with timeline(s)

Responsibility of Costs Interconnecting customer responsible for: Application Fee Expedited and Standard: $4.50/kW ($300 min and $7,500 max Costs of impact and detailed studies if required Grid modification requirements – can include ongoing charges Witness Test Fee Costs associated with design, construction and installation of the facility and all associated interconnection equipment on the customer’s side of the meter Not all projects will require impact or detailed studies or EPS upgrades 17

18 Third Party Ownership Application must include information for both generation owner (interconnecting Customer) and electric or retail customer (Customer) Utility will correspond with owner, customer and installer – Listing addresses for all parties on application makes communication easier and faster Utility will enter into agreement with our electric customer (Attachment G of tariff) *Note: Any Ownership change would require updated documentation submitted to the Utility Company

19 Common Application Mistakes Number of inverters being used not indicated Utility account or meter number not included or incorrect Address of facility not correct Name on application differs from name on utility account Application not signed Ownership of property not identified Not identifying third party ownership of generator

20 Common process delays New construction or service upgrade Host/Owner misidentification Changing inverter or other equipment Not supplying electrical permit Certificate of Completion (CoC) signed and dated before date given approval to install

21 Behind the scenes at utility… Review and replacement of metering, modifications to billing Modifications to protection systems as required (e.g. replace or install fusing, install switch, modify breaker/recloser set- points, transfer trip, etc.) Larger generators require review by NEPOOL reliability committee and registration with ISO-NE Adding generation asset to geographic information systems, maps, system one-lines, dispatch systems, etc. Publish internal special operating guidelines for utility field personnel on larger generators. Set up future testing for relay protection, meter calibration, insurance tracking, etc.

Many Stakeholders Involved Utility Application analyst – processes application and contracts Lead Engineer for reviews/studies Relay Engineering Distribution Planning Distribution Dispatch Distribution Design Engineering Meter Operations Meter Engineering Meter Data Services Relay Telecom Operations Inspection team Customer Service / Billing Legal… Interconnecting Customer Customer Equipment vendor Lead contractor Electrician Electrical Engineer (PE) Relay Engineer Relay testing firm Legal ISO-NE (If necessary) 22

23 Interconnection Summary and Recommendations Submit your interconnection application with National Grid early, during conception phase before committing to buy no matter how simple or small the DG might be. You can always request general utility information about a specific location from your utility Large interconnection application take longer to study Stand alone (no load behind the meter) interconnection application take longer to study Interconnection timeframes do not apply to Electric Power System construction if required.

24 Summary and Recommendations continued The Interconnection Standard is a wealth of information – get to know it Time frames are standard working days and do not include delays due to missing information or force majeure events Interconnection expenses such as application fees, required studies, potential system modifications and witness tests should be budgeted into each project Consider hiring an engineer to help with interconnection process ISO-NE notification not included in time frame Interconnection applications have increased significantly in the past few years – APPLY EARLY!!!

25 Compensation for excess CHP generation If the customer will never export power – no concern If under 60 kWs, customer can net usage over billing period – Paid average clearing price for load zone for excess If customer will export power – they can sell their exported power to the market through a registered market participant. – Customer will need a Qualifying Facility (QF) certificate from FERC for the generator, to “sell” to local utility (Power Purchase Schedule) Receive hourly clearing price for load zone for excess – Customer can work with any registered market participants to sell power – Customer must pay for all power they use. – Energy is netted for each hour, not over the billing period FERC QF page:

If project is large enough (>6 -10 MWs), will need to interconnect to transmission system through Small Generator Interconnection Procedures (SGIP) Need to apply to the New England Independent System Operator (ISO-NE) If you will be selling your power to a third party, or bidding in capacity to the Forward Capacity Market (FCM) you may have to apply through ISO-NE If circuit is already “FERC Jurisdictional” and project is selling to a third party, it will need to apply to ISO-NE. If another generator is selling to the wholesale market, then the circuit is FERC jurisdictional State vs. ISO-NE Process 26

27 Interconnection Contacts & Tariff Links National Grid Phone: Alex Kuriakose | (781) , Bob Moran | (508) W. ‘Adam’ Smith | (781) , Vishal Ahirrao | (781) Sean Diamond | (781) , Chandra Bilsky | (401) Kevin G. Kelly | (978) NSTAR Joseph Feraci | (781) Paul Kelley | (781) Unitil Tim Noonis | resources/renewable-energy-generation resources/renewable-energy-generation WMECo Phone:

28 Other Information Resources MA DG and Interconnection Website: Net Metering Basics: Home/net-metering-in-ma Home/net-metering-in-ma Interconnection Guide for Distributed Generation (Mass-CEC): InterconnectionGuidetoMA_Final%281 %29.pdf InterconnectionGuidetoMA_Final%281 %29.pdf 28

Appendix Technical Aspects of Integrating DG with the Utility Distribution EPS 29

What are the local rules that apply to DG interconnections?  National Grid ESB 756 Parallel Generation Requirements  Originates from the ESB 750 Series and applicable Company tariffs in each state jurisdiction  ESB 756 main document  Appendices to ESB 756 for Jurisdictional Requirements Some key factors that influence the revision/update of Electric Service Requirements are:  Government  DPU (Massachusetts), PSC (NY), and PUC (one each for NH & RI)  FERC  Federal, State, and Local Laws MA Court Rules: Solar PV Installations are Electrical. PHYSICAL INSTALLATION of PV Systems Must Be Done by LICENSED ELECTRICIANS. [July 2012 ruling by Suffolk Superior Court]  Company tariffs  Company policies & practices  National codes Interconnection Standards: Local Rules – National Grid Each utility has their requirements pursuant to the regulations that govern them as varying from state-to- state based on the NESC. 30

Key Points for Electric Service Requirements:  Require some means of disconnect and main overcurrent protection, i.e., service equipment.  Billing meters secure.  Interface points clear to avoid potential operating and safety problems. Interconnection Standards: (cont’d) National Grid ESB 750 Series Key Points for Parallel Generation Requirements:  Company determines the interconnect voltage and method of interconnection.  Prior notification to and approval by the Company is required for any generation to be installed or operated in parallel with the Company EPS. 31

 Technical Process End-to-End (Study to Energization/Synchronization) with National Grid  Technical Submittals for Utility Review  Potential Impacts of Parallel Generation on Distribution Electrical Power Systems (EPS)  Limits on National Grid Distribution EPS  Radial Systems  Network Systems  Service Connections of Small Net Metered DGs < 600V  Typical Distribution EPS Upgrade Costs for Complex DG Installations Technical Issues: 32

1. Identify the project, Company’s electric service order (ESO) number, location and submitter’s name and address. 2. Indicate standard and any non- standard system voltages, number of phases, and frequency of the incoming circuit. Indicate wye and delta systems; show whether grounded or ungrounded. 3. Identify cable, conductors and conduit, the type and number including Point of Common Coupling. (The Company is interested in how the power is getting from the service point to the protective equipment.) Technical Issues: Technical Submittals for Utility Review Recommended Guidelines for Residential and Commercial Single-line Diagram Submittals (for example, see Exhibit 5 & Figures 1 & 2 in ESB 756 Appendix C) 33

 Typical Planning Limits for DG Connection to Radial Distribution Feeder DG installations are classified into two types - those interconnecting to the National Grid system on a dedicated radial feeder and those interconnecting on a non-dedicated radial feeder. Technical Issues: (cont’d) Limits on Distribution EPS - Radial 34

 Anti-Islanding Protection The Company’s position is that the interconnection of all parallel generators requires safeguards for synchronization and back-feed situations. A parallel generator is prohibited to energize a de-energized Company circuit. The Company uses three main “tests”; any determine if anti-islanding protection is required for exceeding minimum load issue or a protection issue or operating concern: 1.“Feeder Load versus Generation Test” 2.“Fault Sensitivity Test” 3.“Feeder Selectivity Test” Tips DG Customer’s protective device coordination study demonstrates generation voltage and/or frequency protection will trip within 2.00 seconds for the loss of the utility source. Type-tested inverter-based parallel generation operated in regulated current mode, transient overvoltage protection is required upon detection of an island. When DTT is specified for a parallel generation project, the Company will determine the requirements and responsibilities for equipment, installation, and communications media in the interconnection study. Technical Issues: Anti-Islanding on Distribution EPS - Radial 35

 Unlike radial distribution systems that deliver power to each customer in a single path from source to load, underground secondary area network systems deliver power to each customer through a complex and integrated system of multiple transformers and underground cables that are connected and operate in parallel.  Area Networks consist of one or more primary circuits from one or more substations or transmission supply points arranged such that they collectively feed secondary circuits serving one (a spot network) or more (an area network) electric customers. Technical Issues: Limits on Distribution EPS - Network 36

Technical Issues: (cont’d) Limits on Distribution EPS - Network 37 Area Networks consist of one or more primary circuits from one or more substations or transmission supply points arranged such that they collectively feed secondary circuits serving one (a spot network) or more (an area network) Interconnecting Customers. Portions of the following cities are served by area networks (customers in these areas should ask where the nearest radial system is located for possible tie-in): WMECoUnitilNational GridNSTAR Greenfield Pittsfield Springfield West Springfield FitchburgBrockton Lynn Worcester Boston New Bedford Cambridge (For National Grid, see Exhibit 3 in ESB 756 Appendix B, or C, or D.)

 The connection of customer DG facilities on networks is an emerging topic, which (i) poses some issues for the Company to maintain adequate voltage and worker safety and (ii) has the potential to cause the power flow on network feeders to shift (i.e., reverse) causing network protectors within the network grid to trip open. Technical Issues: (cont’d) Limits on Distribution EPS - Network  To ensure network safety and reliability additional information will be required for the Company’s engineering analysis such as: Electric demand profile showing minimum load during peak generation time, Expected generation profile shown for a 24-hour period and typical 7-day duration, and Customer’s complete electric service single-line diagram up to the service point supplied by the Company’s secondary network EPS. 38

Technical Issues: Upgrades and System Modifications Some Upper End Typical Utility Interconnection Costs & Duration Scheduling for Complex DG Installations Notes: 1) Distribution EPS relates to 15kV class system. 2) These are representative estimates only and are not inclusive of all costs [i.e. land rights, removal costs, taxes, etc.] which will vary from job to job and that they are presented here for budgetary purposes only. 39

Post ISA Coordination Witness Testing (overview) 1.) Relay Witness Testing National Grid Witnesses relays trip based on settings approved by NG Protection Engineer 2.) DTT Witness Testing Communication (RFL) to the Local Substation Typically Fiber or Lease line 3.) RTU Witness Testing (≥1MW) Provide Real time monitoring of Large DG at National Grid’s Regional Control Center. Ordering Correct (MPLS) communication circuit from Verizon Verizon Regional Account Teams consults with Verizon’s “Service Delivery” Department 40

41 Appendix Net Metering

42 Net Metering in Massachusetts December 2009 Net Metering Tariff Three Net Metering Classes – Class 1: Any generator up to 60 KW is eligible – Class 2: Agricultural, solar, or wind net metering facility over 60 KW but less than or equal to 1 MW (for municipal or government it’s “per unit) – Class 3: Agricultural, solar, or wind net metering facility over 1 MW but less than or equal to 2 MW (for municipal or government it’s “per unit”) Recent changes – limits projects to 2 MWs per parcel of land and a single meter – Must apply to the System of Assurance (SofA) at massaca.org for net metering services

43 Net Metering Tariff Eligible customers can apply by submitting a Schedule Z. Eligibility determined when approved within the SoA – Utility can not allow net metering without SofA approval Class 2 and Class 3 will need a production meter on generation. Net Metering is limited to 3% of each utility’s peak MW for private and 3% of peak for public projects – for NG-MA this total limit is 308 MWs. Contribution towards total 6% limit is posted on each utility’s web site and updated monthly – As of 4/16, NG-MA is at 94 MWs for the private and of 52 MW toward the public cap

Net Metering changes Three Factor Approach (order 11-11C) – Single parcel / single interconnection point / single meter Enacted to limit gaming and limits one meter per parcel of land with a limit of 2 MWs on the parcel for private entities – A governmental entity can have a total of 10 MWs of net-metered accounts throughout the state or on a parcel – No more 6 – 1 MW projects on a parcel – We can not provide more than one interconnection point (POI) In addition, if there’s an existing meter(s) on a parcel, then customer can’t request a meter just for the net metering facility, it must be behind an existing meter – Otherwise separate metered project could earn higher credits than if it was behind an existing meter 44

Net Metering and Interconnection Order Net Metering eligibility – The DPU ruled in the interconnection tariff order (10-75E) that “Early ISA’s” will NOT meet the executed ISA requirement for entrance into the System of Assurance, and will refer the matter to DPU for further investigation. – Until such time as the DPU reaches a resolution of the issue, Distribution Companies are directed to clearly mark Early ISAs on the title page and on the signature page with the words “Early ISA” for identification purposes.

46 Net Metering Credits Credit the following charges TierminmaxType Default Service kWH Dist- ribution kWH Trans- mission kWH Trans- ition kWH 1060 KW Agriculture Wind, PVXXXX 2>60 KW1 MW Agriculture Wind, PVXXXX 3>1 MW2 MW Agriculture Wind, PVXGov’t onlyXX Energy use is “netted” over the billing month –If there is net energy use – utility will bill customer for net use –If net energy export – export kWH * the following Renewable installations will be credited at near retail rate for excess kWH (minus conservation and renewable energy charges). Non-Renewable credited at average monthly clearing price ISO-NE Tariff allows credits to be allocated (with limitations) Customer still responsible for customer charges and demand charges, even if net export

47

48

49

50 Net Metering Production Reporting Net Metering Tariff requires reporting of generator’s kWH output. Class 1 Facilities to provide in writing by January 31 and September 30 Class 2 and Class 3 Facilities may participate in production tracking system (PTS). – Mass CEC provided PTS data to the utilities, still working through implementation issues – Utility will request data from Class 2 and 3 Facilities

51 Net Metering Summary If planning to Net Meter, submit Schedule Z with interconnection application Correctly fill out Schedule Z – Name must match electric account of Host Customer – Must be signed by Host Customer If allocating, verify name/address/account info of customer(s) – or will need to submit corrected form Production reporting is required. Over 60 kWs require registration as a settlement only generator (SOG) associated ISO OP 18 metering requirements