Taken from presentation by: Neal Babcock & Howard Alderson, P.E. Alderson Engineering, Inc. February 26, 2008
Typical Installation: 100 to +150 ft/ton; 15’ x 15’ to 20’ x 20’ spacing HDPE Piping
4,600 Tons 6,500 Tons
Underground soil/rock formation strongly affects the performance of the well field; –Sands and Clays; –Rock; Affects type of Grouting used.
Primary Loop Variable Flow Circulates around the Campus Secondary Loop #1 Variable Flow Circulates thru Borefield Secondary Loop #2 Variable Flow Circulates within a Building
Campus Distribution Loop: HDPE Pipe; 160 PSI Rated No Insulation Borehole Piping HDPE Pipe; 160 PSI Rated No Insulation Isolation Valves Butterfly; 150 PSI Rated Distribution Isolation Valves Butterfly/Ball Valves; 150 PSI Rated Borehole Grout Thermally Enhanced Bentonite; K=1.2