ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.

Slides:



Advertisements
Similar presentations
Sectional Assembly and Installation
Advertisements

ZTF Mechanical Walkthrough Matthew Hoff ZTF Technical Meeting 1.
J.P. Langston Brake Retrofit
SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Engineering Division 1 Integration and Pixel Mechanics Progress 27-April 2011 HFT Mechanics Meeting E Anderssen, LBNL.
RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
Fixturing operations for PXL 1 models: MSC.SLDASM MSC_fixtured.SLDASM rail_test_system.SLDASM 2/24/2010.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Design, Prototyping, and Production PST Progress Update September 2002.
ATLAS Frame PRR 1 W.O. Miller Feb US ATLAS Pixel Detector Global Supports PRR W.O. Miller, R. Smith, W.K. Miller, R. Baer HYTEC G. Gilchriese, E.
Vacuum Vessel Production Readiness Review
Old Main Group. Design Issues There are no changes to the overall Design It will remain the way it is The Attachment Issue is resolved Going to screw.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
ATLAS Pixel Detector October 2001 Pixel Week N. Hartman LBNL 1 PST Design Update PST CDR october 2001.
HFT PXL Mechanical July 2010 Howard Wieman LBNL 1.
M. Gilchriese Mechanics Labor and Disk Sectors US Pixel Meeting November 2001.
ATLAS Pixel Detector September 2002 A. Das LBNL 1 Pixel Support Tube Rails: Design and Prototyping September, Review.
APPENDIX A (RFI) FOR THE FABRICATION OF MULTIPLE STEEL REACTION STRUCTURES FOR NASA-MSFC STRUCTURAL TESTING Mike Roberts 12/2/09.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
ATLAS Pixel Detector July 2003 ETC ‘04 E. Anderssen LBNL BPSS and Service Panels Santa Cruz, CA E Anderssen LBNL.
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
ATLAS Pixel Detector Pixel Support Tube Interfaces LBNL Internal PST Review E. Anderssen, LBNL.
FEBRUARY 2003 Pixel Support Tube A. Smith LBNL 1 ATLAS Pixel Support Tube PRR: Parts Pixel Support Tube Production Readiness Review Parts Overview Alexis.
Substrate-Paddle-Base Peter Cooke. Peter Cooke 28 Feb - 1 March VELO PRR2 Substrate- Paddle-Base Substrate Production Paddle – Base – Feet Component.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
Design Progress Allen Ellis 18-September
ATLAS Pixel Detector June 2002 PST FDR N. Hartman LBNL 1 Pixel Support Tube: Design and Prototyping PST Final Design Review June 2002.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
ATLAS Pixel Detector Project N. Hartman LBNL 1 Alexis Smith Intern Progress Report Neal Hartman, March 25, 2003.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
M. Gilchriese Overview of Production Plan for Pixel Global Support and Disk Support Rings M. G. D. Gilchriese Lawrence Berkeley National Laboratory February.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
FVTX Review, November 17th, FVTX Mechanical Status: WBS 1.6 Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
M. Gilchriese Disk Sector Production Pixel Local Supports Production Readiness Review.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
1 Status of Vacuum Process Facilities at SSL 16 October 2009 Sharon R Jelinsky Space Sciences Laboratory, UC Berkeley.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
ATLAS Pixel Detector Pixel Support Tube and Related November 9, 2001 Pixel Day E. Anderssen, LBNL.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
LARP Collaboration Meeting Racetrack Coil Fabrication
ATLAS Pixel Detector July 2003 Insertion Device Costs A. Smith, LBNL 1 Insertion Device Costs Overview US Pixel Meeting July 9, 2003.
ATLAS Pixel Detector Pixel Support Tube Interfaces Pixel Support Tube PRR CERN, Geneve E. Anderssen, LBNL.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.3 Fab & Assy Plans 1 GLAST Large Area Telescope:
VTX Half LAYER 4 LAYER 3 LAYER 1 LAYER 2 EACH LAYER’S BARRELL MOUNT NEEDS TO BE REFERENCED TO KINEMATIC MOUNTS AND IT’S MOUNTED LADDERS.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
STEP 1: ASSEMBLE INSERT PLATES 1.Assemble insert plates by press fitting roller bearing and adapter plate into assembly 1.1 Prep all mating surfaces to.
QXF Coil Fabrication & Tooling Reaction / Impregnation
Procurement Status Miao Yu 11/19/2013.
BSS Prep work at CERN and Acceptance of Parts
Far Detector Activities Late 2017 – Early 2018
Preliminary PXL support models with assembly fixtures
Presentation transcript:

ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003

ATLAS Pixel Detector February 2003 N. Hartman LBNL 2 Overview Assembly Breakdown Structure (ABS) Assembly Processes and steps –Assembly flow –Parts required –Tooling required Production Information –Tooling status –Production plan Resources milestones –Schedule

ATLAS Pixel Detector February 2003 N. Hartman LBNL 3 Assembly breakdown structure (ABS) Barrel PST assembly shown; b.s. = barrel shell.

ATLAS Pixel Detector February 2003 N. Hartman LBNL 4 Assembly Steps and Procedures

ATLAS Pixel Detector February 2003 N. Hartman LBNL 5 Assembly Flow – How is the PST Assembled? Backing Ring Flange Face Flange Asm Barrel Shell Barrel Shell with flanges barrel shell structural barrel shell w/ mount pads barrel shell w/ SCT Mounts 5 3 Hoop Element Hoop Stiffener Flat Rail V-Rail Mount Pad Insulator SCT Mount Block Asm SCT Mount Block

ATLAS Pixel Detector February 2003 N. Hartman LBNL 6 STEP 1 – Flanges Assembled Flange Cross Section Single piece skirt and face (L shape) Backing Ring Process –Flange masked –Adhesive applied (bondline controlled with glass beads) –Backing ring weighted with caul plate –Assembly drilled with hole jig Tooling required –Caul plate (Fabricated) –Drill jig (Fabricated) QA Steps –Weigh parts before and after for resin content –Inspect datum hole positions after machining Backing ring Flange Face

ATLAS Pixel Detector February 2003 N. Hartman LBNL 7 Bond Jig Details Accurate holes on horizontal diameter Of flange provide references for all Bond operations. Bars provide length Reference only (invar) Gussets provide perpendicularity

ATLAS Pixel Detector February 2003 N. Hartman LBNL 8 STEP 1a – Flanges Bonded to Shell Process –Flange and jig masked –Shell centered in bond gap with shims –Flange sealed to bond jig –Adhesive applied behind flange –Adhesive pulled through joint with vacuum (from front) Tooling required –Bond Jig (Fabricated for prototype length) –Barrel and Forward Length Spacer Bars (needed) QA Steps –Remove from jig and weigh (resin control) –Inspect parallelism and flatness of flanges after bonding

ATLAS Pixel Detector February 2003 N. Hartman LBNL 9 STEP 2 – Hoop Stiffeners and Rails Bonded to Shell Process –Hoop Stiffeners –Applied before rails –Shell masked –Hoops assembled in place, as single bonded units, 3 parts at a time –Glass beads used to control bond line –Compression strap used to fixture while curing –Rails –Rails are affixed to ladder structure that runs through PST shell (with vacuum) and references to pins on flange plate –Adhesive applied to shell –Rail tool lowered into place Tooling required –None for stiffeners (self-fixturing) –Vacuum rail jig attachment (needed) QA Steps –Remove from jig and weigh (resin control) –Inspect positions of rails at flange ends (to ensure alignment when PST sections are mated)

ATLAS Pixel Detector February 2003 N. Hartman LBNL 10 STEP 3 – Mount Pads Bonded to Shell/Flanges Process –Machined mount pads affixed to bond jig extensions (referenced to accurate pins on flange plate) –Shell and mount pad masked –Adhesive applied to mount pad (bondline controlled by fixture) –Mount pad/jig extension moved into place Tooling required –Bond jig extensions (fabricated) QA Steps –Remove from jig and weigh (resin control)

ATLAS Pixel Detector February 2003 N. Hartman LBNL 11 SCT mistress gauge blocks register to PST Interface penetrations Carbon fiber tooling bar Frame is bonded to them and supported in SCT barrel while adhesive cures Frame Gauge blocks STEP 4 – Mount Block Locations Transferred from SCT to Mistress Gauge

ATLAS Pixel Detector February 2003 N. Hartman LBNL 12 Blocks machined to Surveyed position of PST mounts (relative to IP_Nominal) Balls register Mistress gauge in proper orientation Bond in SCT_Interface Transfer Feature STEP 4a – Mount Block Locations Transferred from Mistress Gauge to PST Bond Jig

ATLAS Pixel Detector February 2003 N. Hartman LBNL 13 STEP 4b – Mount Blocks Bonded to Insulators Process –Both parts masked –Adhesive applied to mount block –Glass beads used to control bondline Tooling required –None, self-fixturing QA Steps –Weigh (resin control) –Measure thickness Fiberglass Insulative shim Mount block

ATLAS Pixel Detector February 2003 N. Hartman LBNL 14 STEP 4c – Mount Block Assy’s Bonded to Shell/flanges Process –Inside of mount pad and mount block masked –Mount block inserted through mount pad, bolted to jig –Adhesive injected between mount pad and mount block bond surfaces Tooling required –Bond Jig attachment pieces (Needed) –Mount block interfaces bonded into jig attachment with SCT mistress gauge in place (needed) QA Steps –Remove from jig and weigh (resin control) –Survey positions of mount locations to SCT Attachment surface to jig Backside of bond surface

ATLAS Pixel Detector February 2003 N. Hartman LBNL 15 STEP 5 – Pixel Mount Blocks Bonded to PST Pixel Mount Ramp Process –Outside of mount pad and pixel mount block masked –Mount pad affixed to jig that transfers position from SCT mount block jig –Adhesive injected between Pixel mount block and mount pad Tooling required –SCT mount block tooling – used for both pixel and SCT mount blocks, as they are defined relative to each other (needed) QA Steps –Remove from jig and weigh (resin control) –Survey positions of mount locations (including planarity)

ATLAS Pixel Detector February 2003 N. Hartman LBNL 16 Sample Assembly Follower Raw material data (out time, date, remaining mass) are kept in log book at freezer.

ATLAS Pixel Detector February 2003 N. Hartman LBNL 17 Production Planning

ATLAS Pixel Detector February 2003 N. Hartman LBNL 18 Status of Tooling Items Existing –Flange Tools Face piece Backing ring Assembly (bonding) Machining fixtures Flange bond plates to PST –Mount Pad Layup tool Machining fixture Mount pad bond parts to PST –Rails Full length tool Needed –Mandrel (Procure) Cylinder Cart Stand –Mount bonding (In house) SCT Mistress gauge Bond jig attachments Pixel mount bond parts –Rails (In house) Bonding tool (vac fixture) –Hoop Stiffeners (In house) Layup tool Main Bond Jig Parts are already fabricated

ATLAS Pixel Detector February 2003 N. Hartman LBNL 19 Procurements/Responsibilities Tooling –Only mandrel and carts/stands will be outsourced Engineering design by outside vendor – complete Awaiting quote for fabrication Estimated delivery is 8 weeks –All other tooling fabricated in-house Material –All material from Bryte technologies – ex1515 cyanate ester resin Usual delivery time is 3-4 weeks Material to be ordered by March 14 –Heater panels from outside vendor Composite Parts –All parts made in-house, by LBNL technical staff

ATLAS Pixel Detector February 2003 N. Hartman LBNL 20 Mandrel and Autoclave Carts Production Mandrel and cart have been designed and quoted by outside vendor - ~32K USD

ATLAS Pixel Detector February 2003 N. Hartman LBNL 21 Production Resources Manpower –3 technicians now trained in composites –Schedule assumes ½ FTE technician over production period Facilities –Autoclave (1.5 m id x 3 m long) –CNC ultra high- precision machining –Coordinate measuring machine –Cold storage (-40 Celsius, 3 m x 5 m) –Dedicated Layup facility (10 m x 10 m)

ATLAS Pixel Detector February 2003 N. Hartman LBNL 22 Important Milestones Production Readiness Review –February 18, 2003 – CERN Full Size Mandrel and Material Ordered –March 1-14, 2003 Production Material Delivered –April 14, 2003 Mandrel Delivered –May 1, 2003 Production Begins –May 1, 2003 Barrel PST Completed –September 14, 2003 Forward PST’s Completed –June 1, 2004 Pixel System Dry-fit (PST, BP Support, service panels, pixel frame) –July, 2004 Fit-up with SCT (transfer jig bonded) –September, 2004 SCT/PST Installed –January, 2005

ATLAS Pixel Detector February 2003 N. Hartman LBNL 23 Full Schedule

ATLAS Pixel Detector February 2003 N. Hartman LBNL 24 Potential Risks Prototyping –Problems with rail riders – not yet designed (pixel and beampipe/services) Production –Delays or problems in mandrel machining –Delay in mount transfer from SCT –Problems in schedule or performance of pixel package dry fit