Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 25, 2012 EDUCATE ENGAGE EMPOWER 1
Agenda Completed Construction Projects LAC Building I (Bookstore) Current Construction Projects LAC Building A – Student Services Retrofit LAC Building I (Landscape) LAC Master Landscape LAC Veterans Stadium Lights PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit Upcoming Construction Projects LAC Math Technology Building PCC Building GG LAC Building C Retrofit Q & A 2
Completed Construction Projects 3 Building construction complete Move in complete Bookstore is open for business LAC Building I - Measure E 2008
Current Construction Projects LAC Building A – Student Services Retrofit Measure E Progress on sheeting the roof Interior wall framing in progress Subfloor and utility installation in progress Estimated completion date late fall 2012
Current Construction Projects LAC Building A – Student Services Retrofit Measure E Structural walls complete on new addition Roof structure to follow
Current Construction Projects 6 Exterior Landscape has started Privacy wall started, planting to follow Project expected to be complete in May 2012 LAC Building I Landscape - Measure E 2008
Current Construction Projects 7 Phase 1, South of Building A Bid opening date 5/22/2012 Construction to start in summer 2012 Passive Storm water retention system Low water use Plants and trees Pedestrian pathway alignment LAC Master Landscape - Measure E 2008
Current Construction Projects 8 Phase 2, North of Building A will bid Spring 2013 Construction to start in summer 2013 Active Storm water retention system Low water use Plants and trees Pedestrian pathway alignment LAC Master Landscape - Measure E 2008
9 Veteran’s Stadium Lighting Measure E 2008 Current Construction Projects Stadium lighting retrofit Awaiting final DSA approval Construction includes demo of old fixtures and installation of energy efficient fixtures.
Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E MDAB building remodel project Phase 1 of 2 currently under construction Exterior envelope 90% constructed Roof Membrane 100% complete
Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E South side exterior curtain wall Electrical distribution transformer complete Phase 1 Project to be completed Summer 2012
Upcoming Construction Projects PCC Building CC Retrofit - Measure E Building CC Fitness Center, offices and restrooms Demolition complete, exterior walls in progress Duration of project approximately 12 months Anticipated end of construction Fall 2012
Upcoming Construction Projects Math and Culinary Arts instructional program as well as Reprographics Contract awarded to Harper/Sillman Design Build Team Currently in design development phase (DD) Construction documents to DSA Fall of 2012 Anticipated start of construction 2013 LAC Math Technology Building – Measure E
Upcoming Construction Projects PCC Building GG - Measure E Design Build Entities (DBE) short listed to 5 Interviews with 5 short listed DBE teams complete in January 3 Teams selected for proposals, Balfour Beatty, C.W. Driver, Bernards Estimated start of construction December 2013
Upcoming Construction Projects LAC Building C Retrofit - Measure E Hired Architect to do design work Program phase is currently ongoing Work includes modernization of structure, classrooms spaces, and office areas
l i b e r a l a r t s Liberal Arts Campus Site Plan
p a c i f i c c o a s t Pacific Coast Campus Site Plan
QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 18