Carol Chessmore Oncor 2013 DWG Vice Chair 2014 DWG Chair - Pending ROS Approval January 9, 2014 ERCOT ROS Meeting Austin, TX.

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Audit & Compliance Tips Jagan Mandavilli Senior Compliance Engineer.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
PSS/E Version 33 Dynamic Conversion
1 The Tres Amigas SuperStation VLPGO November 2011.
PROJECT NO PUCT STAFF WORKSHOP 11/19/14 Julia Harvey Kristi Denney Kevin Mathis Jasmin Thevaril.
Integration of Variable Generation Task Force Preliminary Conclusions and Actions.
April 23 rd OWG UFLS Survey & Power Factor Review.
Engineering a sustainable future 1 ERCOT Voltage Ride-Through Study Workshop June 26 th, 2009.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Lead from the front Texas Nodal 1 Registration Market Call Mar 13, 2009.
ERCOT Planning WMS 10/20/2010 Target Reserve Margin and Effective Load Carrying Capability of Installed Wind Capacity for the ERCOT System – Methodology.
SPWG SHORT CIRCUIT CASE BUILDING AND DEVELOPMENT July 17, 2014 Qiuli Yu and Jay Teixeira ERCOT.
Problem Areas Updates Penalties FRCC Compliance Workshop September / October
1 Planning the CREZ 345 kV System for Multi-contingencies CREZ Technical Conference January 26, 2010 Bernie Pasternack AEP Service Corporation.
COMPLIANCE ROLLOUT Vann Weldon Compliance Training Administrator March 23, 2005 NERC FUNCTIONAL MODEL REVIEW.
COMPLIANCE UPDATE ERCOT ROS Meeting April 9, 2002.
NERC Project S ystem Protection Coordination - PRC-027​ Presentation to the NSRS Conference Call April 20, 2015 Sam Francis Oncor Electric Delivery.
1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014.
Texas Regional Entity Report Mark Henry June 6, 2008.
1 Market Trials Outage Scheduling Weekly Update June 11, 2010.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
Steady-State Working Group: Resource Modeling Discussion Wes Woitt September 27 th, 2011.
NDSWG Report June 16, NDSWG Report Regular meeting held May 16 in Taylor Telemetry / State Estimator Update Naming Convention Electrical Bus Designation.
Texas Regional Entity ROS Presentation January 15, 2009 T EXAS RE ROS P RESENTATION J ANUARY 2009.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com MOD GENERATOR TESTING REQUIREMENTS RESOURCE PLANNERS LeeAnne Uhler, Regulatory.
October 29, 2012 RARF Workshop 2 Introduction to ERCOT Modeling Process Jay Teixeira Manager, Model Administration.
February 3, 2011 TAC ERCOT Planning Go-Live Update Jay Teixeira Manager, Model Administration.
RAWG Agenda Item LAR Data WECC Staff. Data Elements Generator information – Existing – Changes Monthly Peak Demand and Energy (actual year and.
ERCOT ROS Planning Working Group (PLWG) Scope Approved at ROS Meeting.
DWG Procedural Manual: Wind Model Requirements DWG Request to ROS August 11, 2006.
Nodal Planning Model Process and Data Set A case use June 28, 2010 Planning Working Group.
Tracy Rolstad TSS Chair TSS Chair Report July 2014 Salt Lake City, UT 1.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
PLWG Report to ROS September 4, PGRR039 PGRR requires Interconnecting Entities (IEs) to provide information for ERCOT’s resource adequacy reports,
ERCOT DYNAMICS WORKING GROUP Report to ROS August 16, 2007 Vance Beauregard, American Electric Power.
ROS Report Bill Hatfield 2014 ROS Chair Technical Advisory Committee (TAC) Meeting ERCOT Public June 26, 2014 TAC Meeting.
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transition Plan Network Operations Model Change Requests 5/26/2010.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
1/14/10ERCOT ROS / CREZ OGRR1 Why is CREZ Unique? 15 GW of intermittent generation when ERCOT load is less than 30 GW 5000 miles of 345 kV circuits with.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
PLWG Report to RPG January 21, 2014 Presented by John Moore, PLWG Chair.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
1 The Tres Amigas SuperStation Low Carbon Summit October 22, 2011.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
ERCOT SYSTEM PLANNING Dynamic Model Data Management.
Nodal Planning Go Live Austin, TX February 3, 2011
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Freeport Area Master Plan Project -
Western Electricity Coordinating Council
PLWG Review 6.9 and the Interconnection process
Southern Cross Directives Planning Items
Oncor Electric Delivery Company LLC
Phil O’Donnell, Manager Operations and Planning Audits
Presenter: Peter Heidrich, FRCC – BES Drafting Team Chair
Jonathan young ColumbiaGrid
Phil O’Donnell, Manager Operations and Planning Audits
System Review Work Group Update to TSS
Presentation transcript:

Carol Chessmore Oncor 2013 DWG Vice Chair 2014 DWG Chair - Pending ROS Approval January 9, 2014 ERCOT ROS Meeting Austin, TX

 Brings Planning Guide consistent with approved procedures  ERCOT Staff prepare Dynamic Flat Start Cases  ROS Approved in July 11, 2013 as part of DWG Procedure Manual Revision 8  Supports ERCOT as the “One Stop Shop” for data collection and study cases  Supports consistency with RARF, SSWG and SPWG data preparation  DWG and PLWG support the Revision 2 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 DWG Manual Revision 8 - Approved by ROS on July 11, 2013 ◦ After January 1 st, 2015, ERCOT shall prepare all the flat start cases  PGRR 33 revision to Planning Guide section ◦ (1) In order to maintain simulation-ready base cases and associated dynamics data files for use in dynamic simulations, the DWG ERCOT, in consultation with ERCOT the DWG, shall perform dynamic simulations, called flat-start simulations, as described in the Dynamics Working Group Procedure Procedural Manual 3 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Planning Authority (Planning Coordinator in new standard) ◦ The responsible entity that coordinates and integrates transmission facility and service plans, resource plans, and protection systems ◦ ERCOT is the registered Planning Authority (PA)  Resource Planner ◦ The entity that develops a long-term (generally one year and beyond) plan for the resource adequacy of specific loads (customer demand and energy requirements) within a Planning Authority Area. ◦ ERCOT is the registered Resource Planner (RP)  Transmission Planner ◦ The entity that develops a long-term (generally one year and beyond) plan for the reliability (adequacy) of the interconnected bulk electric transmission systems within its portion of the Planning Authority Area. ◦ TSPs such as Oncor, CNP, AEP, LCRA, etc are registered Transmission Planners (TPs) 4 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 ERCOT is the Appropriate Entity for the Flat Start Coordinator  Precedent  ERCOT inputs Generator data into the SSWG case  ERCOT has been the DWG Flat Start Coordinator in the past  ERCOT has Experienced Dynamic staff  Flat Start Case Building requires advanced skills and knowledge of a wide variety of models both Conventional and Renewable  Some TSPs do not have Wind generators or other renewables in their area and are unfamiliar with Renewable Generator models  Improved Data and Process Consistency  ERCOT is used to looking across the whole system  ERCOT has access to the Dynamic portion of the RARF. TSPs do not have full access to the Dynamic datasheets attached to the RARF 5 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 ERCOT is the Appropriate Entity for the Flat Start Coordinator (Continued)  Improved Communication  Close the loop between Flat Start Model Adjustments and the RARF Model Submission  As ERCOT Flat Start Coordinator, ERCOT communicates better with generators since they are more aware of common model issues  ERCOT has a built-in system (website posting) for distributing large files.  Outside companies as Flat Start Coordinator have to give the package (100Mb) to ERCOT to post.  Most TSPs don’t have FTP sites and file limits may force the Pass Case package to be chopped into pieces.  FTP site to FTP site communication brings up security and IT issues 6 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 ERCOT is the Appropriate Entity for the Flat Start Coordinator (Continued)  Improved Compliance with NERC Standards  Documented communication between ERCOT, TSPs, and Generators on Dynamic Models  If ERCOT is the Coordinator, TSPs and Generators receive direct confirmation that data submittal was received by ERCOT  TSPs and Generators have direct confirmation that ERCOT is aware of tuning that needed to be done on Dynamic models  ERCOT manages the RARF process so any needed changes shown by the Flat Start process can be followed up by ERCOT directly with the Generator 7 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 TSPs take turns so 3 TSPs for 3 Flat Starts per year ◦ Oncor, CNP, AEP, LCRA, CPS, Austin Energy, and STEC actively participate in DWG ◦ However, if one TSP is required to do it, then all TSPs (even non-active DWG members) need to serve a term as coordinator  Costs quickly balloon under this scenario  Personnel Requirements per TSP ◦ Each TSP needs to maintain a person who is experienced enough to troubleshoot both inside and outside its Area ◦ Even if a TSP does not perform a Flat Start that year, the TSP needs to maintain a person with the skill set to perform a DWG Flat Start ◦ At present, TSPs do not have the long term resources to plan for the resources/budget/schedule needed to perform the flat start case ◦ May require each TSP to add a Third of a Full Time Employee (FTE) ◦ Possibility of delays in publishing the case and performing studies  Summary ◦ Third of FTE per TSP with a Total of 2+ FTE for TSPs 8 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Impact ◦ $45k per TSP to support one Flat Start per year  Assuming the Coordinator is experienced with the ERCOT system and Wind generator models and other renewable models ◦ $50k per TSP to support one Flat Start  For Coordinators unfamiliar with ERCOT  TSPs lacking Wind generators and other renewables in their area, ◦ Experienced  $45k * 6 TSPs = $270k per year  $45k * 4 TSPs = $180k per year ◦ Inexperienced  $50k * 6 TSPs = $300k per year  $50k * 4 TSPs = $200k per year ◦ As more TSPs begin to participate to take their turn as coordinator, costs escalate above $300k per year  $180k-$300k+ per year for TSPs to support DWG Flat Starts 9 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

ERCOT as the Coordinator TSPs as the Coordinator  ERCOT needs to maintain one person who is experienced enough to troubleshoot across the ERCOT system  ERCOT Impact Analysis ◦ Half of an FTE ◦ $120k-$130k to support 3 Flat Starts per year  Cost savings ◦ $60k-$170k+ per year  Each TSP needs to maintain a person who is experienced enough to troubleshoot both inside and outside their Area  TSP Impact Analysis ◦ Third of an FTE per TSP, Total 2 FTE for 6 TSPs ◦ $45k-$50k per TSP per year $180k-$300k+ per year for TSPs to support all 3 Flat Starts 10 of 22 ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 DWG and PLWG support PGRR 33  ERCOT is the NERC Planning Coordinator and NERC Resource Planner so ERCOT is the Appropriate Entity to be the Flat Start Coordinator  Cost Savings, Improved Efficiency, Reduced Delays from reducing pool of Flat Start Coordinators from 6+ Entities to One Entity  Having a single entity as the Flat Start Coordinator leads to ◦ Improved Consistency of the Flat Start process and Dynamic models ◦ Improved Communication between ERCOT, Generators and TSPs ◦ Improved Compliance with NERC standards 11 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

Flat Start Case Building Details

 Needed by both ERCOT and TSPs  New and Existing Dynamic Data Submissions are tested in the Dynamics Case. ◦ Issues can be seen that are not caught earlier since generators are interacting together in the system  A Stable No Disturbance Case with a good initialization is required for both ERCOT and TSPs to perform Dynamic Analysis studies on the transmission system  Dynamic Analysis studies are required by NERC standards and the ERCOT Planning Guide  Dynamic Analysis can lead to projects that help stabilize the Transmission Grid around Generators ◦ Example: CREZ Reactive Study resulted in SVCs and Reactors ◦ Example: Parkdale and Renner SVCs in the DFW Area ◦ Example: ERCOT Panhandle Study  VSAT and TSAT - used by ERCOT Operations ◦ ERCOT maintains VSAT and TSAT models ◦ ERCOT uses PSSE models as a basis for VSAT and TSAT models 13 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Standard TPL System Performance Under Normal Conditions ◦ B. R1. The Planning Authority and Transmission Planner shall each demonstrate through a valid assessment that its portion of the interconnected transmission system is planned such that, with all transmission facilities in service and with normal (pre-contingency) operating procedures in effect, the Network can be operated to supply projected customer demands and projected Firm (non- recallable reserved) Transmission Services at all Demand levels over the range of forecast system demands,  The following standards require a Base Case or Flat Start Dynamic Case (No Contingency case) in order for analysis to be completed. ◦ Standard TPL-002-0b: Loss of a Single BES Element (Category B) ◦ Standard TPL-003-0b : Loss of Two or More BES Elements (Category C) ◦ Standard TPL-004-0a: Extreme BES Events (Category D 14 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Approved by ROS on July 11, 2013  Schedule for Dynamic Data Updates and Flat Start Cases ◦ Each February, the DWG shall prepare a schedule for updating dynamics data and preparing the DWG flat start cases ◦ The DWG shall prepare the following flat start cases based on the following SSWG steady state cases:  Dataset A summer on-peak  A future year Dataset B summer on-peak case  The future year Dataset B high wind low load case ◦ The DWG may choose to flat start additional cases ◦ After January 1 st, 2015, ERCOT shall prepare all the flat start cases 15 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Does not include CREZ Reactive Study Flat Starts ◦ CY2011 – ERCOT Staff ◦ FY2013 – ERCOT Staff  2011 ◦ CY2011 – ERCOT Staff ◦ FY2015 – ERCOT Staff  2012 ◦ CY2012 – ERCOT Staff ◦ FY2017- TSP prepared (AEP)  Added HWLL Flat Start requirement ◦ CY2013 – ERCOT Staff ◦ HWLL2016 – ERCOT Staff ◦ FY2018 – TSP prepared (Austin Energy) 16 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 2014 ◦ CY2014 – TSP Prepared (LCRA) ◦ HWLL2017 – TSP Prepared (AEP) ◦ FY2019 – TSP Prepared (Oncor)  2015 ◦ CY2015 – TSP Prepared (CNP) ◦ HWLL2018 – ERCOT Staff (With PGRR33 Approval) ◦ FY2020 –ERCOT Staff (With PGRR33 Approval) 17 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

18 of 22  Stable No Disturbance Base Case ◦ A Stable Base Case is indicated by flat lines on time plots since there is no changes that force the generator control systems to respond. ◦ With a Contingency, a nearby generator would initially oscillate as it responds to the disturbance. Then it would damp down to a new stable steady value ◦ With poor or inconsistent data, generators oscillate without disturbance or go completely unstable Unstable CaseStable Case ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

Steady State Study Dynamic Study  Time is not considered  Uses Simple Generator Model ◦ Pmax, Pmin, Qmax, Qmin  Does not use fault impedance data  Uses Matrix Math ◦ No Initialization ◦ Less sensitive to Parameter Changes  Adds time as a parameter  Adds Generator Component data ◦ Turbine, Governor, Exciter, Power System Stabilizer, Over Excitation Limiter, etc  Uses Fault Impedance data to model a fault condition  Uses Differential Equations ◦ Initialization ◦ Sensitive to Parameter Changes 19 of 22 ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

Pass Case Posted for Review by DWG and ERCOT 20 of 22 DWG Conventional Gen RARF Models Renewable Gen RARF Models Flat Start Coordinator TSP Final Case Package Pass Case Package (100MB) TSP ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Uses a SSWG seed case  Adds dynamic models for Generator Components ◦ Turbine, Governor, Exciter, Power System Stabilizer, Over Excitation Limiter, etc ◦ TSPs do not directly see the PSSE datasheets in the RARF ◦ ERCOT disseminates generator updates to TSPs  Combined Cycle Dispatch ◦ adjusted with Historical Dispatch Data using a Python program to match Steam Turbine Governor Models  Adds collector systems for Wind Generators  User Defined Model data is compiled into a form that PSSE can use for simulation 21 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33

 Each Case has to be individually tuned to that Generation Dispatch, Load Level, and Topology  Process is iterative and time consuming  Because Dynamic Analysis uses a Differential Equation Solution Process, the analysis is sensitive to changes in parameter data  Changes in Generation Dispatch, Zsource, voltage tuning, are made to obtain a Stable No Disturbance Case with a good initialization (no out of limit messages)  If the case does not initialize well, then the simulation stops until the case is tuned to obtain a good initialization. Problems with initialization can be because of missing data or Dynamic Data that does not match Steady State Data  A case that initializes but has errors might have Dispatches that force the generator to its dynamic limit and/or over its dynamic limit. Parameters are adjusted to get a match between the Steady State and Dynamic data 22 of 22ERCOT ROS Meeting 01/09/2014 DWG Carol Chessmore PGRR 33