G2P Target installation and Beyond. Schedule Pivot before.

Slides:



Advertisements
Similar presentations
The Big Family Readiness Review 1 st Run Period: Threshold Pion Production 2 nd Run Period: Transversity & d2n 3 rd Run Period: A y & 3 He(e,ed)
Advertisements

Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Jixie Zhang Javier Gomez Oleksandr Glamazdin Roman Pomatsalyuk Vadym Vereshchaka Hall A Collabortion Meeting, Dec 2012 Hall A Moller Polarimeter 12 GeV.
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
G2p/GEp Beamline Tim Michalski Project Lead. Overview Facilitate the design, procurement, and build of the beamline – up to the target chamber g2p/GEp.
Vacuum & Cooling Systems Updates F. Makahleh On behave of Vacuum & Cooling Group TAC 2013, F. Makahleh, Vacuum & Cooling 1.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
1 Hall A Update Thia Keppel APEX Collaboration Meeting April 2015.
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
MICE CM February 08Jean-Sébastien GraulichSlide 1 Detector DAQ Hardware Status o Introduction o Preliminary list o Plan for action o Summary Jean-Sebastien.
Improved beam line for Hall A layouts, present and proposed optics in altered region benefits of proposed layout costs of proposed layout conclusions.
05/30/08J. Dunne -- SANE Collaboration Meeting 1 Beamline Status Upstream beamline –Chicane –SEM –Rasters –Girder Downstream beamline –Helium bag –Extension.
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
Ion Source Update. We now have 2 running sources Source B has been running since the first part of June Both sources have been modified extensively since.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
S PIN A SYMMETRIES ON THE N UCLEON E XPERIMENT ( E07-003) Anusha Liyanage Experiment Nuclear Physics Group Meeting Hampton University May 11, 2009.
UVA Polarized Target In Hall A Pictures and Cost Paul Brindza Dec 17, 2009.
09/13/20111 Status of high intensity polarized electron gun project at MIT-Bates Evgeni Tsentalovich MIT.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Instrumentation and Controls Test Plan Review 17 th February 2012 Roy Preece (STFC RAL)
Experiment beam line installation (9/4/2014) SystemThus FarTo Do Vacuum~ Torr, IP’s on, Vac interlock checkNone Fast valveValve + CCG installed,
G2p/GEp Beamline Tim Michalski Project Lead. Beamline Overview Slow Raster Tungsten Calorimeter Upside Down Girder (correctors, BCM, superharp) FZ1 Magnet.
G2p/gep Beamline Project Overview Tim Michalski Project Lead.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
HPS T EST R UN C ONTINGENCY P LAN S. Stepanyan JLAB.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
ILC MDI workshop January 6-8, 2004 PEP-II IR M. Sullivan 1 Interaction Region of PEP-II M. Sullivan for the ILC MDI workshop January 6-8, 2005.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
PREX Mtg, July 2008R. Michaels, JLAB Warm Septum : Status Septum Team: Kees deJager, Paul Brindza, Javier Gomez, John Lerose, Al Gavalya, & me New Design.
SANE Collaboration ( E07-003) Anusha Liyanage Hampton University January 12, 2010 Measurement Of the Proton Form Factor Ratio at High Q 2 by Using The.
PHENIX Safety Review Overview of the PHENIX Hadron Blind Detector Craig Woody BNL September 15, 2005.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Run Coordnator Report 2012/04/ /04/10 Jixie Zhang
Installation of the T600 at Fermilab CSN2, September 22,
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
G2P Installation Readiness. Fast raster & Calorimeter.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Danilo Domenici – LNF. Detector Upgrades Overview CSN1 - 4 Maggio 132 Inner Tracker QCAL CCAL.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
SANE Magnet Review ● Repaired polarized target magnet was successfully energized and put in persistent mode on 12/18/08 after the review, following the.
HMS Status Steven Lassiter Jan 20, 2017.
RF Systems and Controls for the LERF CM Tests
Beam Loss Monitors and Ion Chambers for protecting Hall Equipment Tommy Michaelides (SSG) Stay Treat 2016.
SHMS Cryogenics and Q2(Q3Dipole) Cool Down
Hall A Infrastructure and the Moller Parity Experiment “AMPEX”
Cryomodule Assembly Plan
Hall C SHMS & Configuration Status
NPS Status Feb 01, 2019 Paulo M & Steven L.
Hall C SHMS & Configuration Status
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

G2P Target installation and Beyond

Schedule

Pivot before

Pivot bearing area

Pivot with Septum support

Pivot with support and platform

Platform with Septum

Platform with septum and dump

Platform with upper deck

Platform with access platforms and stairs

Fully assembled

Installed

Ep before Coming out

Slow raster Going in

Upside down girder before Coming out

Upside down girder after Going In

Long girder before Coming out

Chicane after Going in

Chicane power supply and equipment area

Septum status Final assembly and magnetic field testing

Spectrometer power supply list Q1 regulation modules, opto couplers, right SCRs and coolant lines install SCR temp monitors, install control board extension cables Q2/Q3 Opto couplers, retro fit new SCR banks, Right Q3 transistor replacement, install SCR temp monitors Dipoles Replace SCRs, lead voltage polarity change upgrade, test spare ZFCT, troubleshoot lead voltage protection circuit, Flush cooling system, install new lead flow meter controllers, install SCR temp monitors

Detectors Both HRS will be used for electron detections. We will need for both arms to have : VDCs, S1/S2, Gas Cherenkov and Lead-glass Shower/Per-shower (pion rejectors). In addition, we plan to have a simple 3rd arm: A small dE (thin scientillators, ~5mm) and E (Thick scinetillators, ~5 cm) detectors. It will be used for monitoring the product of the beam and target polarization by monitoring the elastic asymmetries.

Cryo system Warm up both spectrometers Pump all magnets pump all cryo lines Replace Q1 JT valve heads with JLab valves Replace dipole LN2 probes Replace magnet pressure gauges Repair left Q1 leads Replace left Q1 vacuum seals Replace all Q1 110 vac plugs due to radiation damage Calibrate Ln2 LL probes Calibrate weka valves Repair dipole He LL probe Replace ball valves on magnet cryo bypass lines Repair right Q2 LN2 valve Remove Moeller U tube from pivot Remove Y can from left Q1

LCW list with manifold pix Hard manifold to BB power supply to new regulator and distribution manifold to accommodate Big Box and the FZ magnet power supplies. New distribution manifold at the pivot to accommodate the FZ magnets and the resistor magnet

Power list New power distribution box to accommodate FZ power supplies and target vacuum cart

Engineering Division Interaction Interaction has been very good so far and I believe that we can maintain communication and coordination through the 7:45 and Wednesday meetings.

What we have done before Installation of the septum magnet system (less the 3 rd set of coils) The septum support stand has been used several times Target chamber used in Hall C Target used in Hall C and reworked and tested in the Target lab

Concerns Target operational readiness The effect of this is obvious. Lock down of experiment parameters We still seem to be changing the experiment parameters. LCW capacity due to 2 additional power supplies and 3 additional magnets We are adding another tap from the main line and 2 new manifolds on the old line but this needs to be looked at and we are working with Robin on this. We are also looking at boot pumps. Alignment support This will be a bottleneck for everybody even with the resource leveling that was done and will need to be watched closely. We will have major space constraints on the upper platform

Questions?