Project Management Project management is a systemized approach to: ◦ defining, ◦ organizing ◦ planning ◦ monitoring ◦ controlling projects.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

1 1 Slide © 2006 Thomson South-Western. All Rights Reserved. Slides prepared by JOHN LOUCKS St. Edwards University.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Operations Management Project Management Chapter 3 - Heizer.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 Project Scheduling CP - Chapter 10 Lecture 3. 2 Project Management  How is it different?  Limited time frame  Narrow focus, specific objectives 
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
MGMT 483 Week 8 Scheduling.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Development Scheduling and Probability of Completion.
1 Operations Management Lesson 5 Project Management.
PERT/CPM Models for Project Management
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
© 2007 Pearson Education Project Management Chapter 3.
TECHNIQUES FOR PLANNING & MANAGING PROJECTS.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management Chapter 2.
Project Management © Wiley 2007.
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Project Management 1.
© 2007 Pearson Education Project Management Chapter 3.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Network Planning Methods Example CPM : Saint Paul’s Hospital Network Planning Methods.
Chapter 6. Terminology AOA and AON diagrams Determining Project Duration, Critical Path Special.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. KR: Chapter.
Project Scheduling A. A. Elimam FinishStart. Project Scheduling Need to plan and control large/time consuming projects.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Fifth Edition © 1999 Addison Wesley Longman. All rights reserved. 時間管理補.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 4.
Managing Project Processes Managing Project Processes.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity.
Network Planning Methods Example PERT & CPM
LM733-PRODUCTION OPERATIONS MANAGEMENT
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network.  Gantt Chart  Project Network  Activity-on-arrow 
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation by R.B. Clough.
© 2005 Prentice Hall, Inc. Managing Projects Dr. Mohammad Hamsal.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning.
Software Project Scheduling By: Sohaib Ejaz Introduction A Gantt chart is a graphical representation of the duration of tasks against the progression.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Project Scheduling. Why Are Projects Late? an unrealistic deadline established by someone outside the software development group changing customer requirements.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
© 2007 Pearson Education Project Management. © 2007 Pearson Education Bechtel Group, INC.  Bechtel is a $16.3 billion-a-year construction contractor.
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Hospital Establishment
Project Management for Business
Projects: Critical Paths
Developing a Project Plan
Exercise – A small building.
Planning and Managing Projects
Presentation transcript:

Project Management Project management is a systemized approach to: ◦ defining, ◦ organizing ◦ planning ◦ monitoring ◦ controlling projects.

Projects A project is an interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources.

What are the characteristics of a successful project?

What are some questions that need to be addressed by any Project Management technique?

In order to answer these questions what information do I need?

Use this information to create a Network Diagram A Network Diagram visually displays the interrelated activities (processes) using nodes (circles) and arcs (arrows) that depict the relationships between activities. Two network planning methods (PERT & CPM) were originally distinctive, but today the differences are minor and will be jointly referred to as PERT/CPM. ◦ PERT (Program Evaluation and Review Technique) was utilized when activity times involved risk. ◦ CPM (Critical Path Method) was used when activity times were certain.

Network Diagram

Precedence Relationships  Precedence relationships determine a sequence for undertaking activities, and specify that any given activity cannot start until a preceding activity has been completed. In the AON approach, the nodes (circles) represent activities, and the arcs represent the precedence relationships between them. AON STU Activity On Node approach “S” precedes “T” which precedes “U”

Activity Relationships T U S T & U cannot begin until S has been completed. S T U S & T must be completed before U can be started.

Activity Relationships S T U V U & V can’t begin until S & T have been completed. S T U V U cannot begin until S & T have been completed. V cannot begin until T has been completed.

Activity Relationships STV U T & U cannot begin until S has been completed; V cannot begin until both T & U have been completed.

Purchasing New Software: First develop a list of activities A. Case for change B. Define Requirements C. Prioritize Requirements D. RFP E. Benchmarking F. Evaluate Proposals G. Select Software Vendor H. Build Applications I. Test Applications J. Document K. Train L. Deploy

The Sequence of Activities A. Case for change B. Define RequirementsA C. Prioritize RequirementsB D. RFPC E. BenchmarkingA F. Evaluate ProposalsD,E G. Select Software VendorF H. Build ApplicationsG I. Test ApplicationsH J. DocumentH K. TrainG L. DeployI,J,K

Project Activities, Sequence and Duration ACTIVITYORDERDURATION A. Case for change B. Define RequirementsA4 C. Prioritize RequirementsB2 D. RFPC1 E. BenchmarkingA3 F. Evaluate ProposalsD,E2 G. Select Software VendorF1 H. Build ApplicationsG12 I. Test ApplicationsH8 J. DocumentH6 K. TrainG5 L. DeployI,J,K3

To come up with a project schedule, find: Earliest Start Time (ES) is the latest earliest finish time of the immediately preceding activities. Earliest Finish Time (EF) is an activity’s earliest start time plus its estimated duration. Latest Start Time (LS) is the latest finish time minus the activity’s estimated duration. Latest Finish Time (LF) is the earliest latest start time of the activities that immediately follow. For simplicity, all projects start at time zero.

Earliest & Latest Starting Time for Each Activity Activity DurationEarliest Start Latest Start A200 B422 C266 D188 E326 F299 G11111 H I82424 J62426 K51227 L33232

Earliest & Latest Finish Time for Each Activity Activity DurationEarliest Finish Latest Finish A2 22 B466 C288 D199 E359 F21111 G11212 H I83232 J63032 K51732 L33535

St. John’s Hospital Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff. BSelect site and do site survey. CSelect equipment. DPrepare final construction plans and layout. EBring utilities to the site. FInterview applicants and fill positions in nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment. HConstruct the hospital. IDevelop an information system. JInstall the equipment. KTrain nurses and support staff.

Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CSampson HConstruct the hospital.DCasey IDevelop an information system.AMurphy JInstall the equipment.E,G,HPike KTrain nurses and support staff.F,I,JAshton St. John’s Hospital

Activity Times A = 12 Wks B = 9 Wks C = 10 Wks D = 10 Wks E = 24 Wks F = 10 Wks G = 35 Wks H = 40 Wks I = 15 Wks J = 4 Wks K = 6 Wks A — B— CA DB EB FA GC HD IA JE,G,H KF,I,J Immediate Predecessor

What AON Nodes look like Latest Finish Latest Start Activity Activity Duration Slack The earliest you can complete an activity -- determined by adding the activity time to the earliest start time. The latest you can finish an activity without delaying the project completion date. It is the same as the Latest Start time of the next activity. If there are two or more subsequent activities, this time is the same as the earliest of those “Latest Start” times. Determined by the earliest finish time of the precedent activity. If there are two or more precedent activities, this time is the same as precedent activity with the latest “Earliest Finish” time. This is the Latest Finish time minus the activity time. Slack is the difference, if any, between the earliest start and latest start times (or the earliest finish and latest finish times). S = LS – ES or S = LF– EF © 2007 Pearson Education Earliest Start Earliest Finish

Earliest Start and Earliest Finish Times K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 I 15 Finish Start A 12 F 10 © 2007 Pearson Education Earliest start time Earliest finish time

Earliest Start and Earliest Finish Times © 2007 Pearson Education Critical Path The Critical Path takes 69 weeks K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 I 15 Finish Start A 12 F

K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 I 15 Finish Start A 12 F Latest Start and Latest Finish Times © 2007 Pearson Education Latest finish time Latest start time

© 2007 Pearson Education

Activity Slack Analysis Node DurationESLS Slack A12022 B9000 C D10990 E F G H I J K663630

Project Schedule A Gantt Chart is a project schedule, usually created by the project manager using computer software, that superimposes project activities, with their precedence relationships and estimated duration times, on a time line. ◦ Activity slack is useful because it highlights activities that need close attention. Free slack is the amount of time an activity’s earliest finish time can be delayed without delaying the earliest start time of any activity that immediately follows. ◦ Activities on the critical path have zero slack and cannot be delayed without delaying the project completion.

Gantt Chart for St John’s Hospital

Number of workers assuming all activities are started at earliest time & require one worker each

Number of workers assuming all activities are started at earliest time except F starts after E & I starts latest possible time. Each activity requires one worker still