PERT/CPM Models for Project Management

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Project Scheduling: PERT-CPM
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Project Management and scheduling Objectives of project scheduling Network analysis Scheduling techniques.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
pert and cpm ch 9 Learning objectives:
1 Spreadsheet Modeling & Decision Analysis: A Practical Introduction to Management Science, 3e by Cliff Ragsdale.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Stochastic Modeling & Simulation Lecture 6: Intro to Project Management – CPM.
MGMT 483 Week 8 Scheduling.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Management with PERT/CPM
1 7.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Tasks are called “activities.” –Estimated.
Network Optimization Models
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
1 Material Management Class Note # 5-A ( in review ) Project Scheduling & Management Prof. Yuan-Shyi Peter Chiu Feb
Roberta Russell & Bernard W. Taylor, III
Project Management © Wiley 2007.
Project Management Chapter 17.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., Table of Contents Chapter 8 (PERT/CPM Models for Project Management) A Case Study: The Reliable.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Network Planning Methods Example PERT & CPM
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 Material Management Class Note # 6 Project Scheduling & Management Prof. Yuan-Shyi Peter Chiu Feb
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
6/10/01Network Problems: DJK1 Network Problems Chapters 9 and 10.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
1 TCOM 5143 Lecture 11 Project Management. 2 What’s Project Management? Project management involves planning and scheduling the different activities of.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
UNIT II Scheduling Procedures & Techniques FLOAT
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Project Scheduling Lecture # 1.
Project Planning & Scheduling
Project Management for Business
Project Management and scheduling
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Decision making and Organization Management
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Presentation transcript:

PERT/CPM Models for Project Management Chapter 16: Hillier and Hillier

Agenda What is Project Management Discuss PERT/CPM Motivating Case Study: The Reliable Construction Company Ways of Finding the Critical Path Considering Time-Cost Trade-Offs

What is Project Management Project management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end. There are two management science techniques that are used for project management: Program and Evaluation Review Technique (PERT) Critical Path Method (CPM)

PERT/CPM PERT PERT was designed to examine projects from the standpoint of uncertainty. CPM CPM was designed to examine projects from the standpoint of costs. PERT and CPM techniques have been combined over time. PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.

The Reliable Construction Company Reliable has just secured a contract to construct a new plant for a major manufacturer. The contract is for $5.4 million to cover all costs and any profits. The plant must be finished in a year. A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks. A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.

Needed Terminology Activity Start Node Finish Node A distinct task that needs to be performed as part of the project. Start Node This is a node that represents the beginning of the project. Finish Node This node represents the end of the project.

Needed Terminology Cont. Immediate Predecessor These are activities that must be completed by no later than the start time of the given activity. Immediate Successor Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.

Immediate Predecessors Estimated Duration (Weeks) Activity List for Reliable Construction Activity Activity Description Immediate Predecessors Estimated Duration (Weeks) A Excavate — 2 B Lay the foundation 4 C Put up the rough wall 10 D Put up the roof 6 E Install the exterior plumbing F Install the interior plumbing 5 G Put up the exterior siding 7 H Do the exterior painting E, G 9 I Do the electrical work J Put up the wallboard F, I 8 K Install the flooring L Do the interior painting M Install the exterior fixtures N Install the interior fixtures K, L

Questions Needed to be Answered How can the project be displayed graphically? How much time is required to finish the project if no delays occur? When is earliest start and finish times for each activity if no delays occur? What activities are critical bottleneck activities where delays must be avoided to finish the project on time?

Questions Needed to be Answered Cont. For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time? What is the probability of completing the project by the deadline? What is the least amount of money needed to expedite the project to obtain the bonus? How should costs be monitored to keep the project within budget?

Project Network A project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish. Three pieces of information needed: Activity information Precedence relationship Time information

Project Network Cont. Two types of project networks Activity-on-Arc (AOA) On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors. Activity-on-Node (AON) On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.

Microsoft Project Visual Diagram: Gantt Chart

Scheduling Using PERT/CPM A path through a project network is a route that follows a set of arcs from the start node to the finish node. The length of a path is defined as the sum of the durations of the activities of the path. What are the paths and their corresponding lengths for Reliable?

Critical Path This is the path that has the longest length through the project. The shortest time that a project can conceivably be finished is the critical path. Why?

More Terminology Earliest start time of an activity (ES) The time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) The time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) The latest possible time that an activity can start without delaying the project.

More Terminology Cont. Latest finish time of an activity (LF) The latest possible time that an activity can be completed without delaying the project. Forward pass The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.

More Terminology Cont. Backward pass Slack for an activity The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time.

More Terminology Cont. Earliest start time rule The earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors. Latest finish time rule The latest finish time is equal to the smallest of the latest start times of its immediate successors.

Procedure for Obtaining Earliest Times Step 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0. Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity. Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.

Procedure for Obtaining Earliest Times Cont. Step 4: Apply step 2 to calculate EF. Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.

Procedure for Obtaining Latest Times Step 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node. Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.

Procedure for Obtaining Latest Times Cont. Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule. Step 4: Apply step 2 to calculate its LS. Step 5: Repeat step 3 until LF and LS have been obtained for all activities.

Ways of Finding the Critical Path Examine all the paths and find the path with the maximum length. Calculate the slack for an activity. If the slack is zero, it is on the critical path. If the slack is positive, it is not on the critical path.

Time-Cost Trade-Offs Reliable had an incentive bonus of $150,000 to finish the project in 40 weeks. Is it worth while for Reliable to speed-up the project?

Crashing Crashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value. Crashing a project refers to crashing a number of activities to reduce the duration of the project.

CPM Method of Time-Cost Trade-Offs This is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value. This assumes that there is a trade-off between time and cost that has an inverse relationship.

More Terminology Normal Point is the time and cost of an activity when it is performed in a normal way. Crash point show the time and cost when the activity is fully crashed.

Graph of Normal and Crash Points

Marginal Cost Analysis It is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level. This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.

Maximum Reduction in Time (weeks) Crash Cost per Week Saved Activity Normal Crash A 2 1 $180,000 $280,000 $100,000 B 4 320,000 420,000 50,000 C 10 7 620,000 860,000 3 80,000 D 6 260,000 340,000 40,000 E 410,000 570,000 160,000 F 5 180,000 G 900,000 1,020,000 H 9 200,000 380,000 60,000 I 210,000 270,000 30,000 J 8 430,000 490,000 K L 250,000 350,000 M 100,000 N 330,000 510,000

Marginal Cost Analysis Cont. Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost. Next, calculate the effect that the crash has on each path. Note: Crashing can potentially cause another path to become a critical path.

Solving Crashing Problems Using LP There are three decisions to be made: The start time of each activity The reduction in each activity due to crashing The finish time of the project LP model will be examined in class.