Basics Of PERT/CPM PERT=Project Evaluation Review Technique CPM = Critical Path Method.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák.
Project Management and scheduling Objectives of project scheduling Network analysis Scheduling techniques.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
Advanced Project Management - CPH
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Chapter 10: Project Schedule Planning
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Critical Path and Gantt
Eleanor Roosevelt High School
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
1 Operations Management Lesson 5 Project Management.
PERT/CPM Models for Project Management
Network planning Learning objectives After these lectures you should be able to: - Produce and analyse activities networks - Calculate earliest and latest.
Chapter 10 Project Scheduling: PERT/CPM
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
15C Backward scanning and crashing
Project Management. What is a Project? One Time Effort Identifiable Start/End Points Specific Objectives Multiple Tasks Resources from Across the Organization.
Importance of Project Schedules
Projmgmt-1/14 DePaul University Project Management I - Realistic Scheduling Instructor: David A. Lash.
Planning of Barus & Holley Addition Procurement215 Site Preparation60 Pour Foundation31SP Erect Steel15P, PF Roof, Ext. Wall40ES Fabricate Glass50ES Int.
Project Management Chapter 3 BUSI 2106 – Operations Management.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Software Project Management Task Estimating and Scheduling
ENGM91 ACTIVITY PLANNING Unit 2
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 7 Project Manager’s Toolkit for Time Management.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
1 DELIVERABLES OF DESIGN REVIEW 1 Statement of problem/need Customer needs Product Design Specifications (PDS) Design targets Project plan TOOLS USED TO.
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network.  Gantt Chart  Project Network  Activity-on-arrow 
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
ENGM 631 Optimization Ch. 10: PERT/CPM. Great Pyriamid of Cheops (2,500 B.C.) 42,300,000 Stone Blocks 440 Stories 4Accuracy of 0.04 inch 413 acres level.
1 TCOM 5143 Lecture 11 Project Management. 2 What’s Project Management? Project management involves planning and scheduling the different activities of.
PROJECT MANAGEMENT ENCE-7323 TO 763-N CLASS 3 September 17, 2001 Carl E. Edlund
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management Project Controlling
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Chapter 5: Project Time Management Doddy Prayogo, Ph.D.
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Most commonly used methods for project management.
Project Management and scheduling
معرفي روش هاي برنامه ريزي شبكه و محاسبات زمان
Activity on Arrow Project Management.
Time Planning and Control Precedence Diagram
ENM448-Project Planning and Management
Critical Path Analysis
תזמון פרויקטים.
PERT - The Program Evaluation and Review Technique
PERT=Project Evaluation Review Technique CPM = Critical Path Method
Management & Project Control - Present by Dr.Amir.A.Shojaie
Project Management (lecture)
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Slides Prepared by JOHN LOUCKS
Exercise – A small building.
Project Management (lecture)
Importance of Project Schedules
Time Planning and Control Precedence Diagram
Presentation transcript:

Basics Of PERT/CPM PERT=Project Evaluation Review Technique CPM = Critical Path Method

Why PERT/CPM? Prediction of deliverables Planning resource requirements Controlling resource allocation Internal program review External program review Performance evaluation Uniform wide acceptance

The CPM Diagram “Tasks” are Arrows“Events” are Circles “Dummy Tasks” are Dashed Arrows “Critical Tasks” are Thick Arrows

Starting Point: Task Primary Properties Crash Limit Prerequisite task set (may be empty) Optimal Staffing Duration at Optimal Staffing Level Fixed and Variable costs

If a task seems too complex or involved to easily determine primary properties... Break the task up into simpler tasks... Or create a CPM sub-project.

We will use PERT/CPM Analysis to determine Task Secondary properties: Tail Event and Head Event Earliest Start, Earliest Complete Latest Start, Latest Complete Critical / Non-Critical Status Total Float, Free Float Scheduled Start, Scheduled Complete Actual Staffing, Duration, and Variable Costs

We will then use Task Secondary Properties to generate Project Management Tools: Gantt Chart (Project Schedule) Manpower Chart Expenditure Curves Project Completion (PC)

Generate Initial CPM Diagram Must strictly enforce all prerequisite relationships. Number of events is initially unknown Critical path is initially unknown Iterative Process Try to minimize number of Dummy Tasks

CPM Hint #1 Add or remove events at your pleasure. Do not number events until last.

CPM Hint #2 The initial event is the Tail Event for all tasks which have empty prerequisite sets (Initial Tasks). The Final Event is the Head Event for all tasks which are not members of any prerequisite set (Final Tasks).

CPM Hint #3 Tasks which have identical prerequisite sets have the same Tail Event

CPM Hint #4 Starting with the Final Tasks, work backwards, enforcing the smallest prerequisite sets first. Use Dummy Tasks to enforce any prerequisites in large sets which have already been enforced in a smaller set.

Finish CPM Diagram Remove all redundant Dummy Tasks Remove all redundant Events Number all remaining events Not really finished.. haven’t identified critical tasks yet.

Generate PERT Chart: Enter Data for Each Task Task Symbol Tail Event Head Event Task Duration (TD)

Forward Pass: Determine Earliest Start (ES) and Earliest Complete (EC) for each Task For all Initial Tasks, ES = 0 Once ES is Determined, EC equals ES plus TD. The ES for all tasks with tail [i] is equal to the largest value of EC for all tasks with head [i]. PC is the largest value of EC for all Final Tasks.

Backward Pass: Determine Latest Start (LS) and Latest Complete (LC) for each Task For all Final Tasks, LC = PC Once LC is Determined, LS equals LC minus TD. The LC for all tasks with head [j], is equal to the smallest value of LS for all tasks with tail [j]. At least one Initial Task must have LS = 0; none may be negative.

Determine Total Float (TF): Allowable delay in start of task which will not delay Project Completion For task with tail [i] and head [j], TF[i,j] = (LC[j] – ES[i]) – TD[i,j] =LS[i,j] – ES[i] ES[i] is earliest start for all tasks with tail [i]. LC[j] is latest complete for all tasks with head [j]. LS[i,j] is latest start for task with tail [i] and head [j].

Determine Free Float (FF): Allowable delay in start of task which will not delay start of any other task. For task with tail [i] and head [j], FF[i,j] = ES[j] - ES[i] - TD[i, j] = ES[j] - EC[i,j]

Determine Critical Path All Tasks with zero Total Float are Critical. Any delay in these Tasks will delay Project Completion. Darken these Tasks to finish CPM Diagram.