1 Project S cheduling Converts action plan into operating time table Fundamental basis for monitoring and controlling project Scheduling more important.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Associate Professor MIS Department UNLV
Chapter 17 Project Management McGraw-Hill/Irwin
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
Project Scheduling / Time Study
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
Project Scheduling: Gantt/Pert Charts
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
Chapter 8 Project Scheduling
Developing a Project Plan
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Management: A Managerial Approach
Project Management A Managerial Approach
Chapter 10 Project Scheduling: PERT/CPM
Operations and Supply Chain Management, 8th Edition
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Management Techniques.
BA 333 Operations Management
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Roberta Russell & Bernard W. Taylor, III
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Operations Management Project Management
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Scheduling: PERT/CPM
ENGM91 ACTIVITY PLANNING Unit 2
Project Management: A Managerial Approach
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Project Scheduling Project Management 517 Chapter 8 Prof. M. Anvari
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management (專案管理)
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PERT and CPM.
PROJECT MANAGEMENT Approaches
PROJECT MANAGEMENT Approaches By- Rahul Jain. Plan your work first…..then work your plan.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
1 TCOM 5143 Lecture 11 Project Management. 2 What’s Project Management? Project management involves planning and scheduling the different activities of.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Chapter 16 – Project Management
PROJECT MANAGEMENT.
Project Management (專案管理)
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
PROJECT MANAGEMENT WITH CPM/PERT.
Project Planning and Budgeting
PLANNING ENGINEERING AND PROJECT MANAGEMENT
CHAPTER 8: SCHEDULING (PENJADUALAN)
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
Presentation transcript:

1 Project S cheduling Converts action plan into operating time table Fundamental basis for monitoring and controlling project Scheduling more important in projects than in production,because unique nature Sometimes customer specified/approved requirement - example JKR projects Based on Work Breakdown Structure (WBS)

2 Network Techniques : PERT and CPM PERT:Program Evaluation and Review Technique - developed by the US Navy with Booz Hamilton Lockheed on the Polaris Missile/Submarine program 1958 CPM: Critical Path Method developed by DuPont for Chemical Plant Shutdown Project - about same time as PERT Both use same calculations, almost similar - main difference is probabilistic and deterministic in time estimation Gantt Chart - also used in scheduling

3 Network Network of activities and event relationships that graphically portray the sequential relations between tasks in the project Clearly identify tasks that must PRECEDE or follow other tasks Powerful tool for planning and controlling project

4 Benefits of a network Consistent framework for planning, scheduling, monitoring and control the project Illustrates interdependence of all tasks, work packages, work elements Show the times when specific resources must be made available Helps ensure proper communication between departments Determines project completion time

5 Benefits of a network Identifies critical activities, if delayed, WILL delay project Also identifies activities that have slack - can delay without affect Determines dates on which tasks can be started, or must be started if project is to stay on schedule Shows which tasks must be coordinated to avoid resource or timing conflicts Shows which tasks may run in parallel to meet project completion date

6 Network example1

7 Network example2

8 DEFINITION OF TERMS USED IN A NETWORK Activity:task (s) required by project, uses up resource and consumes time Event:Result of completing one or more activities, identifiable end state, occur at particular time Network:Combination of all activities and events ACTIVITY PRECEEDINGSUCCESSOR EVENT

9 A simple example Consider the list of four activities for making a simple product: ActivityDescriptionImmediate predecessors A Buy Plastic Body - B Design Component - C Make Component B D Assemble product A,C The immediate predecessors for a particular activity are the activities that, when completed, enable the start of the activity in question.

10 Sequence of activities We can start work on activities A and B anytime, since neither of these activities depends upon the completion of prior activities. Activity C cannot be started until activity B has been completed, and activity D cannot be started until both activities A and C have been completed. The graphical representation (next slide) is referred to as the PERT/CPM network for project.

11 Network of four activities A B C D Arcs indicate project activities Nodes correspond to the beginning and ending of activities

12 A Comparison of AON and AOA Network Conventions

13 Another example Develop the network for a project with following activities and immediate predecessors: Activity Immediate predecessors A- B- CB DA, C EC FC GD,E,F First, attempt for the first five (A,B,C,D,E) activities

14 Network of first five activities A B C D 5 E We need to introduce a dummy activity

15 DUMMY- No Time or Resource, only helps LOGIC a Dummy RIGHT!!! WRONG!!! a b b Activity c not required for e a b c d e a b c d e WRONG!!! RIGHT!!! Network concurrent activities

ad b e c f ad b e fc WRONG!!! RIGHT!!! a precedes d. a and b precede e, b and c precede f (a does not precede f)

17 Network of seven activities A B C D 5 E 7 6 F G Note how the network correctly identifies D, E, and F as the immediate predecessors for activity G. Dummy activities can be used to identify precedence relationships correctly as well as to eliminate the possible confusion of two or more activities having the same starting and ending nodes.

18 Scheduling with activity time ActivityImmediateCompletion predecessors Time (week) A- 5 B- 6 CA 4 DA 3 EA 1 FE 4 GD,F14 HB,C12 IG,H 2 Total ……51 This information indicates that the total time required to complete activities is 51 weeks. However, we can see from the network that several of the activities can be conducted simultaneously (A and B, for example).

19 Network with activity time A 5 B 6 C 4 D3D3 E1E1 F4F4 G 14 H 12 I2I2 Each activity letter is written above and each activity time is written bellow the corresponding arc PATH: sequence of connected activities from the starting (1) to Finish (7). ADGI: =24;ACHI : =23 AEFGI: =26: BCHI: =20 CRITICAL PATH : Longest Path, Time taken to complete project (26)

20 Earliest start & earliest finish time We are interested in the longest path through the network, i.e., the critical path. Starting at the network ’ s origin (node 1) and using a starting time of 0, we compute an earliest start (ES) and earliest finish (EF) time for each activity in the network. The expression EF = ES + t can be used to find the earliest finish time for a given activity. For example, for activity A, ES = 0 and t = 5; thus the earliest finish time for activity A is EF = = 5

21 Arc with ES & EF time 1 2 A [0,5] 5 Activity ES = earliest start time EF = earliest finish time t = expected activity time

22 Network with ES & EF time A[0,5] 5 B[0,6] 6 C[5,9] 4 D[5,8] 3 E[5,6] 1 F[6,10] 4 G[10,24] 14 H[9,21] 12 I[24,26] 2 Earliest start time rule: The earliest start time for an activity leaving a particular node is equal to the largest of the earliest finish times for all activities entering the node.

23 ES, EF, LS, LF 2 3 C [5,9] 4 [8,12] Activity ES = earliest start time EF = earliest finish time LF = latest finish time LS = latest start time

24 Latest start & latest finish time To find the critical path we need a backward pass calculation. Starting at the completion point (node 7) and using a latest finish time (LF) of 26 for activity I, we trace back through the network computing a latest start (LS) and latest finish time for each activity. The expression LS = LF – t can be used to calculate latest start time for each activity. For example, for activity I, LF = 26 and t = 2, thus the latest start time for activity I is LS = 26 – 2 = 24

25 Network with LS & LF time A[0,5] 5[0,5] B[0,6] 6[6,12] C[5,9] 4[8,12] D[5,8] 3[7,10] E[5,6] 1[5,6] F[6,10] 4[6,10] G[10,24] 14[10,24] H[9,21] 12[12,24] I[24,26] 2[24,26] Latest finish time rule: The latest finish time for an activity entering a particular node is equal to the smallest of the latest start times for all activities leaving the node.

26 Slack or Free Time or Float Slack is the length of time an activity can be delayed without affecting the completion date for the entire project. For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3 weeks (start anywhere between weeks 5 and 8). ES 5 LS 8 EF 9 LF-EF = 12 –9 =3 LS-ES = 8 – 5 = 3 LF-ES-t = = 3 EF C [5,9] 4 [8,12]

27 Activity schedule for our example ActivityEarliest start (ES) Latest start (LS) Earliest finish (EF) Latest finish (LF) Slack (LS-ES) Critical path A00550Yes B C589 3 D E55660Yes F6610 0Yes G Yes H I 26 0Yes

28 IMPORTANT QUESTIONS What is the total time to complete the project? –26 weeks if the individual activities are completed on schedule. What are the scheduled start and completion times for each activity? –ES, EF, LS, LF are given for each activity. What activities are critical and must be completed as scheduled in order to keep the project on time? –Critical path activities: A, E, F, G, and I. How long can non-critical activities be delayed before they cause a delay in the project ’ s completion time –Slack time available for all activities are given.

29 Importance of Float (Slack) and Critical Path 1. Slack or Float shows how much allowance each activity has, i.e how long it can be delayed without affecting completion date of project 2. Critical path is a sequence of activities from start to finish with zero slack. Critical activities are activities on the critical path. 3. Critical path identifies the minimum time to complete project 4. If any activity on the critical path is shortened or extended, project time will be shortened or extended accordingly

30 Importance of Float (Slack) and Critical Path (cont) 5. So, a lot of effort should be put in trying to control activities along this path, so that project can meet due date. If any activity is lengthened, be aware that project will not meet deadline and some action needs to be taken 6. If can spend resources to speed up some activity, do so only for critical activities. 7. Don ’ t waste resources on non-critical activity, it will not shorten the project time. 8. If resources can be saved by lengthening some activities, do so for non-critical activities, up to limit of float. 9. Total Float belongs to the path

31 PERT For Dealing With Uncertainty So far, times can be estimated with relative certainty, confidence For many situations this is not possible, e.g Research, development, new products and projects etc. Use 3 time estimates m= most likely time estimate, mode. a = optimistic time estimate, b = pessimistic time estimate, and Expected Value (TE) = (a + 4m + b) /6 Variance (V) = ( ( b – a) / 6 ) 2 Std Deviation (  ) = SQRT (V)

32 Precedences And Project Activity Times Immediate Optimistic Most Likely PessimisticEXP Var S.Dev Activity PredecessorTime Time Time TEV  a b c da eb,c fb,c gb,c hc Ig,h jd,e

a (20,4) d (15,25) e (10,4) f (14,4) j (18,4) i (18,28.4) g (4,0) h (11,5.4) c (10,4) The complete network

34 Figure 8-13 The complete Network a (20,0) d (15,25) e (10,4) f (14,4) j (8,4) i (18,28.4) g (4,0) h (11,5.4) c (10,4) CRIT. TIME = 43 EF= a (20,4)

35 Critical Path Analysis (PERT) ActivityLSESSlacksCritical ? a000 b101Yes c404 d20 0 e25205Yes f29209 g21201 h14104 i25241 j35 0 Yes

36 Assume, PM promised to complete the project in the fifty days. What are the chances of meeting that deadline? Ccalculate Z, where Z = (D-S) /  V Example, D = 50; S(Scheduled date) = =43; V = (4+25+4) =33 Z = (50 – 43) / = 1.22 standard deviations. The probability value of Z = 1.22, is

37 What deadline are you 95% sure of meeting Z value associated with 0.95 is D = S (1.645) = = days Thus, there is a 95 percent chance of finishing the project by days.

38 Comparison Between CPM and PERT CPMPERT 1Uses network, calculate float or slack, identify critical path and activities, guides to monitor and controlling project Same as CPM 2Uses one value of activity timeRequires 3 estimates of activity time Calculates mean and variance of time 3Used where times can be estimated with confidence, familiar activities Used where times cannot be estimated with confidence. Unfamiliar or new activities 4Minimizing cost is more importantMeeting time target or estimating percent completion is more important 5Example: construction projects, building one off machines, ships, etc Example: Involving new activities or products, research and development etc

39 BENEFITS OFCPM / PERT NETWORK Consistent framework for planning, scheduling, monitoring, and controlling project. · Shows interdependence of all tasks, work packages, and work units. · Helps proper communications between departments and functions. · Determines expected project completion date. · Identifies so-called critical activities, which can delay the project completion time. · Identified activities with slacks that can be delayed for specified periods without penalty, or from which resources may be temporarily borrowed · Determines the dates on which tasks may be started or must be started if the project is to stay in schedule. · Shows which tasks must be coordinated to avoid resource or timing conflicts. · Shows which tasks may run in parallel to meet project completion date

40 Gantt Charts Since 1917; Useful for showing work versus time in form of bar charts e.g. Can draw directly or from CPM/PERT network

41 Modified PERT/CPM diagram from network e f a d b c dummy h Legend  Scheduled Start  Scheduled Finish  Actual Progress  Unavailable  Current Date  Milestone Scheduled  Milestone Achieved Days

42 GANTT CHART

43

44

45 Gantt Charts and CPM/PERT Networks Gantt Charts: Even though a lot of info, easy to read and, understand to monitor and follow progress. Not very good for logical constraints Should be used to COMPLEMENT networks, not replace

46

47

48

49

50

51