1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.

Slides:



Advertisements
Similar presentations
Chapter 10 Project Scheduling: PERT/CPM
Advertisements

Chapter 8 - Project Management Chapter Topics
Project Scheduling: PERT/CPM n Managers are often responsible for planning, scheduling and controlling projects that consist of numerous separate jobs.
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Project Management CPM/PERT Professor Ahmadi.
Project Scheduling: PERT/CPM
1 1 Slide © 2006 Thomson South-Western. All Rights Reserved. Slides prepared by JOHN LOUCKS St. Edwards University.
Chapter 13 Project Scheduling: PERT/CPM
Chapter 9 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
1 Project Scheduling CP - Chapter 10 Lecture 3. 2 Project Management  How is it different?  Limited time frame  Narrow focus, specific objectives 
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Tutorial 2 Project Management Activity Charts (PERT Charts)
1 1 Slide © 2011 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole.
EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
1 7.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Tasks are called “activities.” –Estimated.
Example: Frank’s Fine Floats
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
In the name of Allah the Most Gracious the Most Merciful.
Project Management Techniques.
1 Lecture 4 MGMT 650 Network Models – Shortest Path Project Scheduling Forecasting.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Network Planning Methods Example PERT & CPM
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management (專案管理)
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Dr. C. Lightner Fayetteville State University 1 Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Project Management Chapter 13 Sections 13.1, 13.2, and 13.3.
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
8-1 Example: Frank’s Fine Floats Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
PERT / CPM – Time-Cost Tradeoffs BSAD 30 Dave Novak Source: Anderson et al., 2015 Quantitative Methods for Business 13 th edition – some slides are directly.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management (專案管理)
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Planning & Scheduling
PROJECT MANAGEMENT WITH CPM/PERT.
Project Planning and Budgeting
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Presentation transcript:

1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known Activity Times Project Scheduling with Uncertain Activity Times Project Scheduling with Uncertain Activity Times Considering Time-Cost Trade-Offs Considering Time-Cost Trade-Offs

2 Slide © 2005 Thomson/South-Western PERT/CPM PERT PERT Program Evaluation and Review Technique Program Evaluation and Review Technique Developed by U.S. Navy for Polaris missile project Developed by U.S. Navy for Polaris missile project Developed to handle uncertain activity times Developed to handle uncertain activity times CPM CPM Critical Path Method Critical Path Method Developed by Du Pont & Remington Rand Developed by Du Pont & Remington Rand Developed for industrial projects for which activity times generally were known Developed for industrial projects for which activity times generally were known Today’s project management software packages have combined the best features of both approaches. Today’s project management software packages have combined the best features of both approaches.

3 Slide © 2005 Thomson/South-Western PERT/CPM PERT and CPM have been used to plan, schedule, and control a wide variety of projects: PERT and CPM have been used to plan, schedule, and control a wide variety of projects: R&D of new products and processes R&D of new products and processes Construction of buildings and highways Construction of buildings and highways Maintenance of large and complex equipment Maintenance of large and complex equipment Design and installation of new systems Design and installation of new systems

4 Slide © 2005 Thomson/South-Western PERT/CPM PERT/CPM is used to plan the scheduling of individual activities that make up a project. PERT/CPM is used to plan the scheduling of individual activities that make up a project. Projects may have as many as several thousand activities. Projects may have as many as several thousand activities. A complicating factor in carrying out the activities is that some activities depend on the completion of other activities before they can be started. A complicating factor in carrying out the activities is that some activities depend on the completion of other activities before they can be started.

5 Slide © 2005 Thomson/South-Western PERT/CPM Project managers rely on PERT/CPM to help them answer questions such as: Project managers rely on PERT/CPM to help them answer questions such as: What is the total time to complete the project? What is the total time to complete the project? What are the scheduled start and finish dates for each specific activity? What are the scheduled start and finish dates for each specific activity? Which activities are critical and must be completed exactly as scheduled to keep the project on schedule? Which activities are critical and must be completed exactly as scheduled to keep the project on schedule? How long can noncritical activities be delayed before they cause an increase in the project completion time? How long can noncritical activities be delayed before they cause an increase in the project completion time?

6 Slide © 2005 Thomson/South-Western Project Network A project network can be constructed to model the precedence of the activities. A project network can be constructed to model the precedence of the activities. The nodes of the network represent the activities. The nodes of the network represent the activities. The arcs of the network reflect the precedence relationships of the activities. The arcs of the network reflect the precedence relationships of the activities. A critical path for the network is a path consisting of activities with zero slack. A critical path for the network is a path consisting of activities with zero slack.

7 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build and want to use PERT/CPM to help them manage the project. The table on the next slide shows the activities that comprise the project. Each activity’s estimated completion time (in days) and immediate predecessors are listed as well. Frank wants to know the total time to complete the project, which activities are critical, and the earliest and latest start and finish dates for each activity.

8 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Immediate Completion Immediate Completion Activity Description Predecessors Time (days) Activity Description Predecessors Time (days) A Initial Paperwork A Initial Paperwork B Build Body A 3 B Build Body A 3 C Build Frame A 2 C Build Frame A 2 D Finish Body B 3 D Finish Body B 3 E Finish Frame C 7 E Finish Frame C 7 F Final Paperwork B,C 3 F Final Paperwork B,C 3 G Mount Body to Frame D,E 6 G Mount Body to Frame D,E 6 H Install Skirt on Frame C 2 H Install Skirt on Frame C 2

9 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Project Network Project Network Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E 7

10 Slide © 2005 Thomson/South-Western Earliest Start and Finish Times Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute: Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute: Earliest Start Time = the maximum of the earliest finish times of all activities immediately preceding activity i. (This is 0 for an activity with no predecessors.) Earliest Start Time = the maximum of the earliest finish times of all activities immediately preceding activity i. (This is 0 for an activity with no predecessors.) Earliest Finish Time = (Earliest Start Time) + (Time to complete activity i ). Earliest Finish Time = (Earliest Start Time) + (Time to complete activity i ). The project completion time is the maximum of the Earliest Finish Times at the Finish node.

11 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Earliest Start and Finish Times Earliest Start and Finish Times Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E

12 Slide © 2005 Thomson/South-Western Latest Start and Finish Times Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, i, compute: Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, i, compute: Latest Finish Time = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.) Latest Finish Time = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.) Latest Start Time = (Latest Finish Time) - (Time to complete activity i ). Latest Start Time = (Latest Finish Time) - (Time to complete activity i ).

13 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Latest Start and Finish Times Latest Start and Finish Times Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E

14 Slide © 2005 Thomson/South-Western Determining the Critical Path Step 3: Calculate the slack time for each activity by: Step 3: Calculate the slack time for each activity by: Slack = (Latest Start) - (Earliest Start), or Slack = (Latest Start) - (Earliest Start), or = (Latest Finish) - (Earliest Finish). = (Latest Finish) - (Earliest Finish).

15 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Activity Slack Time Activity Slack Time Activity ES EF LS LF Slack Activity ES EF LS LF Slack A (critical) A (critical) B B C (critical) C (critical) D D E (critical) E (critical) F F G (critical) G (critical) H H

16 Slide © 2005 Thomson/South-Western Determining the Critical Path Determining the Critical Path A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. Critical Path: A – C – E – G Critical Path: A – C – E – G The project completion time equals the maximum of the activities’ earliest finish times. The project completion time equals the maximum of the activities’ earliest finish times. Project Completion Time: 18 days Project Completion Time: 18 days Example: Frank’s Fine Floats

17 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Critical Path Critical Path Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E

18 Slide © 2005 Thomson/South-Western In the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. In the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. An activity’s mean completion time is: An activity’s mean completion time is: t = ( a + 4 m + b )/6 t = ( a + 4 m + b )/6 a = the optimistic completion time estimate a = the optimistic completion time estimate b = the pessimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate m = the most likely completion time estimate Uncertain Activity Times

19 Slide © 2005 Thomson/South-Western An activity’s completion time variance is: An activity’s completion time variance is:  2 = (( b - a )/6) 2  2 = (( b - a )/6) 2 a = the optimistic completion time estimate a = the optimistic completion time estimate b = the pessimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate m = the most likely completion time estimate Uncertain Activity Times

20 Slide © 2005 Thomson/South-Western Uncertain Activity Times In the three-time estimate approach, the critical path is determined as if the mean times for the activities were fixed times. In the three-time estimate approach, the critical path is determined as if the mean times for the activities were fixed times. The overall project completion time is assumed to have a normal distribution with mean equal to the sum of the means along the critical path and variance equal to the sum of the variances along the critical path. The overall project completion time is assumed to have a normal distribution with mean equal to the sum of the means along the critical path and variance equal to the sum of the variances along the critical path.

21 Slide © 2005 Thomson/South-Western Example: ABC Associates Consider the following project: Consider the following project: Immed. Optimistic Most Likely Pessimistic Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A A B B C A C A D A D A E A E A F B,C F B,C G B,C G B,C H E,F H E,F I E,F I E,F J D,H J D,H K G,I K G,I 3 5 7

22 Slide © 2005 Thomson/South-Western Example: ABC Associates Project Network Project Network

23 Slide © 2005 Thomson/South-Western Example: ABC Associates Activity Expected Times and Variances Activity Expected Times and Variances t = ( a + 4 m + b )/6  2 = (( b - a )/6) 2 t = ( a + 4 m + b )/6  2 = (( b - a )/6) 2 Activity Expected Time Variance A 6 4/9 A 6 4/9 B 4 4/9 B 4 4/9 C 3 0 C 3 0 D 5 1/9 D 5 1/9 E 1 1/36 E 1 1/36 F 4 1/9 F 4 1/9 G 2 4/9 G 2 4/9 H 6 1/9 H 6 1/9 I 5 1 I 5 1 J 3 1/9 J 3 1/9 K 5 4/9 K 5 4/9

24 Slide © 2005 Thomson/South-Western Example: ABC Associates Earliest/Latest Times and Slack Earliest/Latest Times and Slack Activity ES EF LS LF Slack A * A * B B C * C * D D E E F * F * G G H H I * I * J J K * K *

25 Slide © 2005 Thomson/South-Western Determining the Critical Path Determining the Critical Path A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. Critical Path: A – C – F – I – K Critical Path: A – C – F – I – K The project completion time equals the maximum of the activities’ earliest finish times. The project completion time equals the maximum of the activities’ earliest finish times. Project Completion Time: 23 hours Project Completion Time: 23 hours Example: ABC Associates

26 Slide © 2005 Thomson/South-Western Example: ABC Associates Critical Path (A-C-F-I-K) Critical Path (A-C-F-I-K)

27 Slide © 2005 Thomson/South-Western Probability the project will be completed within 24 hrs Probability the project will be completed within 24 hrs  2 =  2 A +  2 C +  2 F +  2 H +  2 K = 4/ / /9 = 4/ / /9 = 2 = 2  =  = z = ( )/  (24-23)/1.414 =.71 z = ( )/  (24-23)/1.414 =.71 From the Standard Normal Distribution table: From the Standard Normal Distribution table: P(z <.71) = =.7612 P(z <.71) = =.7612 Example: ABC Associates

28 Slide © 2005 Thomson/South-Western EarthMover is a manufacturer of road construction equipment including pavers, rollers, and graders. The company is faced with a new project, introducing a new line of loaders. Management is concerned that the project might take longer than 26 weeks to complete without crashing some activities. Example: EarthMover, Inc.

29 Slide © 2005 Thomson/South-Western Immediate Completion Immediate Completion Activity Description Predecessors Time (wks) Activity Description Predecessors Time (wks) A Study Feasibility A Study Feasibility B Purchase Building A 4 B Purchase Building A 4 C Hire Project Leader A 3 C Hire Project Leader A 3 D Select Advertising Staff B 6 D Select Advertising Staff B 6 E Purchase Materials B 3 E Purchase Materials B 3 F Hire Manufacturing Staff B,C 10 F Hire Manufacturing Staff B,C 10 G Manufacture Prototype E,F 2 G Manufacture Prototype E,F 2 H Produce First 50 Units G 6 H Produce First 50 Units G 6 I Advertise Product D,G 8 I Advertise Product D,G 8 Example: EarthMover, Inc.

30 Slide © 2005 Thomson/South-Western PERT Network PERT Network Example: EarthMover, Inc

31 Slide © 2005 Thomson/South-Western Earliest/Latest Times Earliest/Latest Times Activity ES EF LS LF Slack Activity ES EF LS LF Slack A * A * B * B * C C D D E E F * F * G * G * H H I * I * Example: EarthMover, Inc.

32 Slide © 2005 Thomson/South-Western Example: EarthMover, Inc. Critical Activities Critical Activities

33 Slide © 2005 Thomson/South-Western Ch. 10 – 7 A project involving the installation of a computer system comprises eight activities. The following table lists immediate predecessors and activity times (in weeks). Activity Immediate Predecessor Time ABCDEFGHABCDEFGH - A B,C D E B,C F,G a.Draw a project network. b.What are the critical activities? c.What is the expected project completion time?