Joint School District of Beloit Beloit City Council Meeting Monday, February 24, 2014
5 primary buildings ◦ Converse ◦ Robinson ◦ Hackett ◦ Todd ◦ Merrill The Swimming Pool
Cunningham Intermediate School Gaston Primary School Fitness Center McNeel Aldrich Memorial
Update as of January 29, 2014
North-East Exterior Front View North-West Exterior Front View Architect Renderings
West Exterior View South-West Exterior View Architect Renderings
South-East Exterior View North-East Exterior View Architect Renderings
Site Layout
Sidewalk 4-6 Entrance 7/8 Entrance Plaza Dumpster Enclosure Hard Surface Play Storage Building 16 x 16 Site Plan
First Floor First Floor= 70,242 SF Second Floor= 30,214 SF Total= 100,456 SF
Second Floor First Floor= 70,242 SF Second Floor= 30,214 SF Total= 100,456 SF
Site Clearing/Demolition: March/April 2014 Bid Date: April 17, 2014 Construction Start: April 30, 2014 Construction Complete: July 31, 2015
Tennis Courts Big Field between 6 th and 4 th Scoreboards New Storage for Football Propane Tank outside of Swimming Pool