A/E Services Construction Bonds. A/E Services Brooks Act - 1972 - State Adopted Principles - Represented in Procurement Code.

Slides:



Advertisements
Similar presentations
Contracts for Builders Ross Kinzler, Executive Director.
Advertisements

A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
ISTISNA’.
Fixed price contract: A contract that provides a price for each procurement item obtained under the contract.
Contract Analysis Codex FutureLaw Stanford Law School.
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
Utah Procurement Code Training
Bidding Requirements ACT 380. Objective Provide an overview of the bidding process, including documents included in the bidding requirements.
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
Gene Shawcroft, P.E. Central Utah Water Conservancy District April 29-30, 2013.
Surety Bond Claims State of Colorado 05/15/2013. State of Colorado Surety Bond Overview Construction Contract Surety Bonds  Bid – Guarantees bidder will.
WELCOME TO THE INDUSTRIAL COMMISSION SELF-INSURANCE SEMINAR.
Security of Payment workshop Andrew Robertson Important Disclaimer: The material contained in this publication is comment of a general nature only and.
Subcontracts 101 By Mitali Ravindrakumar USC Collaboration between Parties Perform Subcontractor Analysis Sponsor - Fund Project/Subcontr act Negotiate.
Foundations of Real Estate Management BOMA International ® Module 1: Real Estate Administration Contracting for Goods and Services ®
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Darren R. Krattli Eisenhower Carlson PLLC Mechanics’ and Materialmen’s Liens: Start to Finish RCW Main: (253) Direct: (253)
Marcy Mealy Procurement Specialist CDBG Program
Bobby Sullivan and Susan Matthews July 31, 2009 Subdivision Developer Defaults.
Time for a new standard - AS General Conditions of Contract
Patty Bartlett Logan County Treasurer / Public Trustee.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
PROCEDURES FOR SELECTING THE CONTRACTOR
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
Chapter 17 Construction Bonds Vanessa S. Werden
111 Con E 221 Review graded exams on Monday Review presentation guideline for term papers Finalize presentation schedule on Monday.
Performance of Contractor Agreements: Practical Issues Kyiv, September 2012 Kristina ARTEMENKO EU Project "Harmonisation of Competition and Public Procurement.
U.S. Small Business Administration
THE NEW MECHANICS LIEN LAW IN MISSOURI David Townsend President, CEO Agents National Title Insurance Copyright 2010 Agents National Title Insurance.
Design Build, Job Contracting, or Construction Manager at Risk In early 2000 the legislators added an alternate way to accelerate construction project.
Construction Contracts What You Need to Know March 19, 2015.
Reinsurance Supervision The US Perspective ASSAL XIV Annual Meeting Alessandro Iuppa, Superintendent Maine Bureau of Insurance, USA.
Changes To California’s Mechanic’s Lien Laws: Effective January 1, 2012 and July 1, 2012 Hanson Bridgett LLP.
Center of Islamic Finance COMSATS Institute of Information Technology Lahore Campus 1 Adopted from open source lecture of Meezan Bank. Customized for best.
IDENTIFYING THE STRENGTHS & WEAKNESSES OF YOUR CONSTUCTION PROJECT McCune Construction Services Group, L.C.C.
Commonwealth Self Bonding Program by the Department of General Services – Division of Engineering and Buildings Department of Treasury – Division of Risk.
Rabbanai T. Morgan Chief, Contingency Contracting 26 May 2005 Commercial Contract Financing.
LEASE POLICY The Governing Board authorized a new Lease Policy at its September Board meeting and deleted the old Lease Policy.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
CONSTRUCTION CONTRACTS DOCUEMENTS
Contract Bond Forms What to Look For and What Might be Missing Presented by Steve Nelson EVP & General Counsel SureTec Insurance Company 1.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Understanding Surety Concerns with the AIA A312 Payment Bond Form Presenter: [Insert Name]
Uniform Grant Guidance Roundtable Discussion: October 5, 2015 Procurement 1.
Office of Procurement Services.  Vendor Application Website: 
Introduction to Procurement for Public Housing Authorities Sealed Bids Unit 5.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
Small Purchase of Professional Service Providers Administrative Rule R
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 2 Construction Contracts.
HOW TO PROTECT YOUR INTEREST IN A SALE CONTRACT Focus on what you “get” when you sign!
A/E Services Construction Bonds. A/E Services Brooks Act State Adopted Principles - Represented in Procurement Code.
Building Capacity of SMEs for Participation in Public Procurement Draft Presentation for Training of Trainers June 2014.
MECHANICS LIENS: NEW CHANGES & OLD ISSUES Ryan Hiss, Lyman & Nielsen, LLC Brienne Berscheid, Chicago Title Insurance Company.
1 Consent to Subcontract Breakout Session # D12 Name: Rita Wells Daniel Johnson Anthony Simmons Date:July 12, 2011 Time:11:15 – 12:30.
Collateral is an asset that is pledged by a contractor to secure a surety bond. It is a form of asset that is readily convertible to cash, pledged for.
EQUIPMENT CONTRACT RUS FORM 395
Contracts A contract is an agreement between two or more parties which creates an obligation to do or not to do a particular thing. The document containing.
What Is Collateral? Collateral is an asset that is pledged by a contractor to secure a surety bond. It is a form of asset that is readily convertible to.
What Small and Emerging Contractors Need to Know Understanding the Basics of Contract Surety Bonds © Copyright 2016 NASBP.
Consent to Subcontract
MECHANICS LIENS: New Changes & Old Issues
Administration of a FIDIC Contract - Project Control
Understanding The Benefits Of Surety Bonds
What Small and Emerging Contractors Need to Know Understanding General Agreements of Indemnity © Copyright 2017 NASBP.
Contract Review and Processing
Commercial Contract Financing
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
Find the Problems with the Provisions May 11, 2016 Presented By:
Unique General Conditions of the Alabama Building Commission (ABC)
Presentation transcript:

A/E Services Construction Bonds

A/E Services Brooks Act State Adopted Principles - Represented in Procurement Code

A/E Services 63G-6A-1502 – Procurement of A/E Svces…. - Statement of Qualifications - Cost Not an Evaluation Factor - Negotiations with Selected Firm

A/E Services Requirements under $100,000 - Pre-Qualify Firms Pursuant to 63G-6a 403, 404 and Select and Evaluate Three Firms - Negotiate Price with Best Firm

A/E Services 63G-6A Evaluation Committee Selection Non–DFCM……..Refer to Rules From Appropriate Rule Making Authority

A/E Services 63G-6A-1505 Negotiations on Costs Based On…. - Estimated Value - Scope, Complexity & Professional Nature

A/E Services 63G-6A-1505 Negotiations Fail with Selected Firm - Terminate Discussions - Move to Next Selected Firm

A/E Services Rule R33-15 Evaluation Committee Selection - Req. For Statements Of Qualification - Evaluate/Negotiate/and Award or Move On

Construction Procurement Generally an IFB But Sometimes ……. - RFP or Two Step Appropriate

Construction DFCM General Clauses OR: DFCM Home Page / DFCM Forms / Reference Documents - # 9. General Conditions

Construction DFCM Clauses Incorporate by Reference Into IFB - Several Clauses Frequently Used

Construction – Field Conditions - Contractor Notifies A/E or PM on Inconsistencies/differences

Construction – Permits & Fees - Contractor Not Liable Unless Required in Supplemental Conditions

Construction – Delays - Part (2) Weather Related Delays Contractor to Plan for bad weather days Sometimes called “unusually severe”

Construction – Use of Site - Limits Staging Area - Protect Site & Work - Clean Up of Site – Associated Costs, Fines, Etc.

Construction 6.1 – Safety of Persons & Property - Employees, Materials, State Property - Safety Requirements – OSHA - Other Safety Issues / Emergencies - Hazardous Materials

Construction Article 7 – Modifications/Changes - Several Clauses Relative to Changes/Timing, Etc. - Change Orders Common – Usually Routine – Claim Filed? - Contractor Proceeds Diligently

Construction 10.1 – Insurance - Standard $1,000,000 / $3,000,000

Liquidated Damages LIQUIDATED DAMAGES - DFCM GENERAL CLAUSE IN GENERAL - Should the Contractor fail to complete the Work within the Contract Time, there shall be deducted from any amount due or that may become due the Contractor, the sum as stated in the Contractor's Agreement. Such sum is fixed and agreed upon by the DFCM and Contractor as liquidated damages due the DFCM by reason of the inconvenience and added costs of administration, engineering, supervision and other costs resulting from the Contractor's default, and not as a penalty. Actual damages related to delay can not be ascertained at the time of execution of the Contract. To the extent that the liquidated damages exceed any amounts that would otherwise be due the Contractor, the Contractor shall be liable for such excess to the DFCM. DFCM may seek enforcement of such obligation by legal action, and if such is necessary, shall recover the related costs and attorney fees. Notwithstanding any other provision of these General Conditions, the availability of liquidated damages to the DFCM shall not limit the DFCM's right to seek damages or other remedies available under law or equity to the extent such damages or remedies are not based upon delay. LEGAL REALITY… ….. (enforcement in courts) (mitigate damages)

BONDS Bid Bonds Payment Bonds Performance Bonds

Procurement Code Bid Bond – 63-6a-1102 Bid security in an amount equal to at least 5% of the amount of the bid shall be required for all competitive bidding for construction contracts Bid security shall be a bond provided by a surety company authorized to do business in this state, the equivalent in cash, or any other form satisfactory to the state. (AG’s Office has determined that alternate forms of bonding are not acceptable-- only a bid bond is acceptable)

Procurement Code When a bidder fails to comply with the requirement for bid security described in the invitation for bids, the bid shall be rejected unless, pursuant to rules of the applicable rulemaking authority, the issuing procurement unit determines that the failure to comply with the security requirements is nonsubstantial. After bid-closing, irrevocable - 60 days – except per 63G-6a-605 (erroneous bids, etc.) procurement office is not allowed to designate a specific insurance or surety company, producer, agent, or broker.

Procurement Code Performance / Payment Bonds A performance bond satisfactory to the procurement unit that is in an amount equal to 100% of the price specified in the contract and is executed by a surety company authorized to do business in the state or any other form satisfactory to the procurement unit A payment bond satisfactory to the procurement unit that is in an amount equal to 100% Again…….procurement office is not allowed to designate a specific insurance or surety company, producer, agent, or broker.

Procurement Code A person can make take claim action on a payment bond for any unpaid amount due to the person for labor, service, equipment, or material…..IF…. the person has not been paid in full within 90 days of work completion. (define labor)

Procurement Rules R – Bid Security General Acceptable bid security shall be limited to a bid bond in a form satisfactory to the State underwritten by a company licensed to issue bid bonds in this State; OR ??? - a cashier's, certified, or official check drawn by a federally insured financial institution; or cash. (AG Position)

Procurement Rules R – Bid Security: Non-substantial Failure to Comply If a bid does not comply with the security requirements of this Rule, the bid shall be rejected as nonresponsive except where the procurement officer determines otherwise (See Ree parts 1a, b, & c) Only one bid received, Low vs. next high bid within bond amount, Obvious mistake in bid changes bid requirement—48 hours to correct

Procurement Rules R Performance Bonds: General A performance bond is required for all construction contracts in excess of $50,000, in the amount of 100% of the contract price. Deliver within 14 days of notice to provide it. Failure = bid rejection & Bid bond enforced—next low bid awarded—same bonding requirement)

Procurement Rules R – Payment Bonds: General A payment bond is required for all construction contracts in excess of $50,000, in the amount of 100% of the contract price. The payment bond shall be delivered with performance bond – same timing requirements--same action if failure

Procurement Rules R – Bond Forms All bonding forms used must be those most recently adopted by the Board and on file with the Chief Procurement Officer (except bid bonds for projects under $1,000,000 if acceptable to the State)

Procurement Rules R & R Waiver of Bonding Requirements Waiver is possible under certain circumstances by The Chief Procurement Officer pursuant to R and R

Bonds – General Information Authorized Bonding Companies U.S. Department of the Treasury (Circular 570, Companies Holding Certificates of Authority and Acceptable Securities on Federal Bonds and as Acceptable Reinsuring Companies….(referred to as “Surety”). Per AG - Alternate forms of bonding no longer allowed. (Examples that used to be allowed: cash deposit, certified check or irrevocable letter of credit)

Bid Bond - General Must be 5% of Bid Amount Bid Bond must remain in effect up to 60 days Standard Notarize Signature Process Usually includes a Power of Attorney Form attached to the Bid Bond.

Bid Bond – Pertinent Language “..if the said principal does not execute a contract and give bond to be approved by the Obligee for the faithful performance thereof within ten (10) days after being notified in writing of such contract to the principal, then the sum of the amount stated above will be forfeited to the State of Utah as liquidated damages and not as a penalty; if the said principal shall execute a contract and give bond to be approved by the Obligee for the faithful performance thereof within ten (10) days after being notified in writing of such contract to the Principal, then this obligation shall be null and void.”

Bid Bond – State Action Collection on the bond is possible by the State as a result of: 1. Unauthorized or unapproved (by the State) backing out of bid after bid closing….or 2. Failure to obtain required performance and payment bonds..

Performance Bond – Pertinent Language ”…..the condition of this obligation is such that if the said Principal shall faithfully perform the Contract in accordance with the Contract Documents, including, but not limited to, the Plans, Specifications and conditions thereof, the one year performance warranty, and the terms of the Contract as said Contract may be subject to Modifications or changes, then this obligation shall be void; otherwise it shall remain in full force and effect. No right of action shall accrue on this bond to or for the use of any person or corporation other than the state named herein or the heirs, executors, administrators or successors of the Owner.”

Performance Bond – Pertinent Language – Continued The parties agree that the dispute provisions provided in the Contract Documents apply and shall constitute the sole dispute procedures of the parties. PROVIDED, HOWEVER, that this Bond is executed pursuant to the Provisions of Title 63, Chapter 56, Utah Code Annotated, 1953, as amended, and all liabilities on this Bond shall be determined in accordance with said provisions to the same extent as if it were copied at length herein.

Payment Bond – Pertinent Language Principal shall pay all claimants supplying labor or materials to Principal or Principal's Subcontractors in compliance with the provisions of Title 63, Chapter 56, of Utah Code Annotated, l953, as amended, and in the prosecution of the Work provided for in said Contract, then, this obligation shall be void; otherwise it shall remain in full force and effect.

Payment Bond – Pertinent Language - Continued PROVIDED, HOWEVER, that this Bond is executed pursuant to the provisions of Title 63, Chapter 56, Utah Code Annotated, 1953, as amended, and all liabilities on this Bond shall be determined in accordance with said provisions to the same extent as if it were copied at length herein..

Payment Bond – General State’s obligation is to provide bonding information to any subcontractors or material providers who indicate they have not been paid and ask for the information. There may always be exceptions, but….… The State does not withhold funds from the general contractor unless court ordered to do so, or if the bonding company requests it.

Payment Bond – General Generally, the State’s obligation to sub- contractors ends when payment bond has been secured and any potential claimant against the bond has been provided with bonding company information. To take other action on behalf of either the bonding company or the claimant would put the state at an unnecessary risk.

Bonding Company Action Payments by bonding companies are not automatic!

A/E – CONSTRUCTION - BONDS QUESTIONS?