District 2 System Preservation Projects for FY 14 and FY 15 Gregory B. Holsey - District Engineer Thomas S. Revelle - Assistant District Engineer – Project Development
Contract No. - XY Various Locations in Kent County Contract No. - XY Various Locations in Kent County Resurfacing Advertisement Date: November 1, 2013 Notice to Proceed: January 6, 2014 Approximate Hot Mix Asphalt Tonnage: 35,300 Tons. MD 291 from East of MD 213 to Morgnec Cutoff Road; MD 291 from MD 701 to Daisy Drive; MD 444 from End of SHA Maintenance to MD 444; MD 298 from MD 213 to MD 292 MD 291 MD 444
Contract No. - XY Contract No. - XY Various Locations in Queen Anne’s County Resurfacing Advertisement Date: November 1, 2013 Notice to Proceed: January 13, 2014 Approximate Hot Mix Asphalt Tonnage: 34,850 Tons MD 18V from MD 18B to Structure #17048; MD 300A from U.S. 301 to MD 19; MD 290 from MD 544 to MD 300; MD 404 from Talbot County Line to Caroline County Line; MD 662 from Talbot County Line to U.S. 50, MD 18C in Queenstown Town Limits MD 662MD 300A
Contract No. - AW Contract No. - AW MD 404 from West of MD 309 to Cemetery Road – Phase 1-B 4 Lane Divided Highway Construction Advertisement Date: November 29, 2013 Notice to Proceed: February 10, 2014 Approximate Hot Mix Asphalt Tonnage: 43,000 Tons
Contract No. - CE Existing Bridges on U.S. 1, U.S. 40, MD 222 and MD 272 Contract No. - CE Existing Bridges on U.S. 1, U.S. 40, MD 222 and MD 272 Clean/Paint Bridges Advertisement Date: November 29, 2013 Notice to Proceed: February 10, 2014 U.S. 1 over Branch of Octoraro Creek, U.S. 40 Over North East Creek, U.S. 40 Over Little North East Creek, U.S. 222 Over Octoraro Creek, MD 272 Over North East Creek U.S. 222U.S. 40
Contract No. - QA Contract No. - QA MD 835C from East of Cockey Lane Relocated to MD 18A Town of Stevensville Resurfacing and Safety Improvements Storm Drains, Sidewalk, Geometric Improvements Advertisement Date: November 5, 2013 Notice to Proceed: February 17, 2014 Approximate Hot Mix Asphalt Tonnage: 250 Tons Approximate Concrete Sidewalk Square Feet: 4,200 Square Feet Approximate Brick Sidewalk Square Feet: 1,600 Square Feet
Contract No. - XY Various Locations in Caroline County Contract No. - XY Various Locations in Caroline County Resurfacing Advertisement Date: November 5, 2013 Notice to Proceed: February 10, 2014 Approximate Hot Mix Asphalt Tonnage: 35,000 Tons MD 314 from East of Cranby Street to MD 480; MD 313 from Structure #5027 to MD 314 Spur; MD16 from MD 331 to MD 578; Campground Road from One Block East of MD 404 to One Block West of MD 404 MD 16MD 313
Contract No. - XY Contract No. - XY Various Locations in Cecil County Resurfacing Advertisement Date: November 5, 2013 Notice to Proceed: February 17, 2014 Approximate Hot Mix Asphalt Tonnage: 35,300 Tons U.S. 222 from MD 275 to Mill Street; MD 896 from the Delaware State Line to the Pennsylvania State Line; MD 274 from Post Road to Cecil Community College; MD 545 from MD 279 to Kirk Road; MD 285 from Lock Street to Lewis Street MD 274U.S. 222
Contract No. - AT U.S. 50 from 0.5 Miles West of MD 404 to 0.5 Miles East of MD 404 Contract No. - AT U.S. 50 from 0.5 Miles West of MD 404 to 0.5 Miles East of MD 404 Resurfacing and Safety Improvements Advertisement Date: December 3, 2013 Notice to Proceed: Notice to Proceed Date: March 17, 2014 Approximate Hot Mix Asphalt Tonnage: 6,000 Tons Approximate Concrete Pavement Square Yards: 700 Square Yards
Contract No. - QA Bridge #17030 Contract No. - QA Bridge #17030 MD 313 Over Chester River Bridge Deck Replacement Advertisement Date: December 10, 2013 Notice to Proceed: March 24, 2014
Contract No. - CE Contract No. - CE MD 272 in Cecil County Bridge #7036 over Amtrak Proposed Bridge Replacement Advertise Date: January 7, 2014 Notice to Proceed: April 21, 2014
Contract No. – XY Various Locations in Talbot County Resurfacing Contract No. – XY Various Locations in Talbot County Resurfacing Advertisement Date: January 7, 2014 Notice to Proceed: April 21, 2014 Approximate Hot Mix Asphalt Tonnage: 32,750 Tons MD 33 from Seymour Avenue to Pea Neck Road; MD 33 from Easton Corporate Limits to Washington Street; MD 334 from MD 322 to End of S.H.A. Maintenance; MD 33 from Athletics Field to Marks Lane; MD 309 from U.S. 50 to Ball Park MD 334MD 309
Contract No. - QA U.S. 50 from U.S. 301 to 0.5 Miles West of MD 404 Resurfacing and Safety Improvements Contract No. - QA U.S. 50 from U.S. 301 to 0.5 Miles West of MD 404 Resurfacing and Safety Improvements Advertisement Date: February 14, 2014 Notice to Proceed: May 19, 2014 Approximate Hot Mix Asphalt Tonnage: 36,000 Tons
Contract No. - TA MD 331 over Choptank River Bridge #20034 Bridge Replacement Contract No. - TA MD 331 over Choptank River Bridge #20034 Bridge Replacement Advertisement Date: March 4, 2014 Notice to Proceed: June 16, 2014
Contract No. - KE Contract No. - KE MD 213, MD 290, and MD 313A in Kent County Resurfacing and Safety Improvements Level 1 ADA improvements, signal reconstruction Advertisement Date: April 8, 2014 Notice to Proceed: July 21, 2014 Approximate Hot Mix Asphalt Tonnage: 3,000 Tons Approximate Square Feet of Concrete Sidewalk: 2,400 Square Feet
Contract Number – CE Contract Number – CE US 1 in Cecil County From MD 273A to Pennsylvania State Line Proposed Resurfacing and Safety Improvements Advertise Date: April 22, 2014 Notice to Proceed: August 8, 2014 Approximate Hot Mix Asphalt tonnage: 14,000 Tons
Contract Number – QA Contract Number – QA U.S. 301 at MD 304 Proposed Interchange Construction Advertise Date: June 3, 2014 Notice to Proceed: September 15, 2014