Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects June 2009.
Advertisements

Update on FCPS Construction/Renovation Projects July 2009.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT September 16 th, 2013 – October 25 th, 2013.
Update on FCPS Construction/Renovation Projects September 2009.
Update on FCPS Construction/Renovation Projects May 2009.
Tam Valley School Modernization - Phase 1 Summer 2011.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT Week of: August 19 th, 2013 – August 23 rd, 2013.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT Week of: August 5 th, 2013 – August 9 th, 2013.
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009.
Update on FCPS Construction/Renovation Projects April 2009.
With the passage of the May 2009 NLISD Bond Election, campuses made improvements and repairs. New flooring in the elementary schools, updated kitchen.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Newark CSD Phase II Capital Improvement Project Board of Education Report August 2013.
Kitchen New sandwich prep table. Kitchen New pizza prep table.
DG Inyorkern Weekly Project Summary 1/17/14. DG Inyokern 1/17/14: Percentage Overview Demolition: Pad Prep: 100% Finished and ceriified Footing & Foundation:
Wilson School Construction 2014 Tearing out the old courtyard to put in the new sewer line.
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract.
IWTP Facility. Holes Drilled for Detailed Blast Drilling and Blasting for final grade prior to construction in 2011.
October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
TECHNICAL ASSIGNMENT #1 – NATHAN BRASKEY SUNNYVALE PLAZA [Cooper Carry, Inc.]
HIGHLAND PARK BOND WORK The final results will be AMAZING!
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.
MSU/MCTC Law Enforcement and Criminal Justice Center March 10, 2010.
Dan Packer Construction Management Senior Thesis April 16, 2002
Architect Drawing of New Entrance. Location Location of Phase II Construction Project – Old tennis courts west of the existing building.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Update on FCPS Construction/Renovation Projects March 2009.
J&J CONTRACTORS’ MAJOR PHASE DRAWING GUIDE HAFB 1305 HVAC Repair Solicitation # MXRD /8/09 1. Chiller line-horizontal work 2 weeks (2 dn shift)
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. August 2007 Prepared by:
Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”
Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
F ACILITIES, P LANNING, AND C ONSTRUCTION December 14, 2015 – Monthly Construction Report.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
South Halls: Ewing-Cross Renovation AE Senior Thesis: Tech. 1 Quaid Spearing CM Option September 16, 2013.
Elevating the Quality of Life in the District. AFTER RENOVATION BEFORE RENOVATION.
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
WEST DES MOINES LIBRARY ADDITION Team North Final Presentation Team North The Ace Mentor Program career direction for students in architecture,
Estimating and Scheduling CEE 492
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
TRIGON, INC ARDMORE CITY SCHOOLS 2013 BOND ISSUE PROJECTS.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
White Pigeon Community Schools
Building Services Summer 2016 Update
Bond Oversight Committee
Bond Oversight Committee
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
School Improvement Bond Projects
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Construction Documents
Capital Improvements Presentation
Dr. Joseph Meloche Superintendent of Schools Mrs
Progress Report 11/10/11.
1 Semester Project Design A Multi Story Office Building
2018 Bond Review and Proposal
2007 Bond Issue Capital Improvement Program
Payment of the contractor: the cumulative value of work done
Presentation transcript:

Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date (1):$2, Current Phase:1 (On Schedule) Estimated Completion:19% August 2009

Cassidy Elementary – Renovation Rendering of Final Façade August 2009

Cassidy Elementary – Renovation Work Completed in Last 30 Days: Storm sewers installed on south side and across new front parking lot. Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed. Grading started at sidewalks and playground. Concrete retaining walls in place. Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed. Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete. Foundations for stage complete. Music Classroom addition foundation, 1 st floor slab, 2 nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going. Plumbing rough-ins have continued as masonry walls are installed. Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed. August 2009

Cassidy Elementary – Renovation Current Work Effort (August): Storm sewers will continue as site work allows. New 3” domestic water main service will complete. Site grading will complete around the playground. Sidewalk/paving work will complete at playground area. Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated. Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place. HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area. Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area. Electric conduit and rough-ins to continue. August 2009

Cassidy Elementary – Renovation New Admin. Addition 2 nd Fl. New Playground Retaining Walls August 2009 Interior Gym New Stage & Music Room Addition