Engineering Operations Outage Status: Post-run diagnostic calibrations have been completed and in-vessel work can start on PCHERS, FIDA, MPTS, and the.

Slides:



Advertisements
Similar presentations
REMOVE AND INSTALL THERMOSTAT AND TEST OPERATION CS4 A.1 D.6 P-5/6.
Advertisements

Plans for Diagnostic Removals, Storage, and Re-installations during NSTX Upgrade Outage B. Stratton NSTX Team Meeting 9/13/2011.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
EPICS Collaboration Meeting – Aix-en-Provence June 2010 Page 1 ITER welcomes EPICS WD Klotz ITER int. Organiztion That’s me.
August NSTX-U Team Meeting. Engineering Operations August 15, 2014 NSTX-U In-Vessel installations and calibrations have concluded, and activities have.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Fermilab Cavity Refurbishment Status J. Reid M. Slabaugh November 19, 2014 J. Reid 1.
New HV test specification for the LHC N. Catalan for the EI section.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Construction of Wendelstein 7-X Max-Planck-Institut für Plasmaphysik
Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U.
Machine Installations and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Operations Notes Updates Since Last Team Meeting Stefan Gerhardt NSTX Team Meeting B318 January 3 rd, 2013 NSTX-U Supported by Culham Sci Ctr York U Chubu.
ASIPP EAST Overview Of The EAST In Vessel Components Upgraded Presented by Damao Yao.
NSTX NSTX PAC-25 – Background info (Menard)February 18, NSTX FY Research Milestones (base and incremental ) Expt. Run Weeks: 1)Transport.
ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.
Machine Installation and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/ NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
NSTX NSTX Team Meeting –Masa Ono April 25, 2014 NSTX-U Team Meeting April 25, 2014 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo.
Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets.
Washington’s Water Use Efficiency Rule May Require Increased Coordination for Many Utilities Dan Sander, P.E. Senior Engineer.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
RF Operations: Commissioning the RF systems and antenna conditioning J. Hosea et al. NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima.
Engineering Operations OH water leak: Water leak is located ~ 4.5” into the upper OH lead. Leak 2 o’clock Cooling hole in. dia.
Beam Dump Upgrade Planning Keith Welch 2/5/13. Drivers for Upgrade Historical Problems – Hardware failures Helium system Windows, diffusers Dehumidifiers.
NSTX Effects of NTSX Upgrades on DiagnosticsFebruary 8, NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL Johns.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Engineering Operations FY08 Outage: In-Vessel Work: –BSE Vacuum Vessel Interfaces Completed –Liquid Lithium Divertor Tray trial fit-ups –HHFW Antennas.
1 NSTX Project Facility and Diagnostic Plan, 5-Year Plan Preparation and NSTX/NCSX Relationship Masa Ono NSTX PAC 21 st Meeting January , 2007 Supported.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NSTX Research Operation June 29, 2009 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
NSTX Team Meeting May 5, 2009 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics.
NSTX-U Run Planning Guidance for 2015 NSTX-U Research Forum 1 FY2015 (and 2016) research milestones will guide prioritization of eXperimental Proposal.
FY10 Ops Preparations: Extended vessel bake (to 3 weeks) Additional Physics Operators Spare LITER probes/fill systems fabricated & new staff Run day status/plans.
NSTX-Upgrade Magnetics And Related Diagnostics SPG NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu.
M. Ono NSTX FWP 2014 Budget Planning Meeting Apr. 15, 2012 Chapter 10. NSTX-U Facility Status and Proposed Upgrades Text, figures – mostly there except.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
1 PFC requirements  Basic requirements  Carbon based  Provisions for adding (interface design included in research prep budget)  NBI armor  Trim coil.
Engineering Operations Outage Status: Tile cleaning is complete Tentatively planning on 2 LITER operation. Design Review upcoming Shielding of HHFW/in-vessel.
Ans Pardons (with input from Jean-Marc Cravero) CERN CNGS Horn Experience (issues since NBI2010) Ans Pardons, CERN 1 NBI2012.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
NSTX NSTX Team Meeting –Masa Ono May 1, 2015 NSTX-U Team Meeting May 1, 2015 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
NSTX NSTX Team Meeting –Masa Ono August 14, 2015 Masa Ono February 5, 2016 NSTX-U Team Meeting.
Thomas Jefferson National Accelerator Facility Page 1 FNAL/JLab weekly meeting, April 23, 2014 Agenda  Path Forward  Status at FNAL  Status at JLab.
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
Research Operations Update Stefan Gerhardt NSTX-U Team Meeting B-318 December 4 th, 2014 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
NSTX NSTX Team Meeting –Masa Ono August 14, 2015 NSTX-U Team Meeting August 14, 2015 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
US Construction Project: SSs, PRY, Cavities and test program 1.
Research Operations Update S.P. Gerhardt August 2015 NSTX-U Team Meeting PPPL 8/14/2015 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
MRL CRG – Cleanaway Update
PARK EAST CONSTRUCTION
Presentation transcript:

Engineering Operations Outage Status: Post-run diagnostic calibrations have been completed and in-vessel work can start on PCHERS, FIDA, MPTS, and the new Bolometer. Surface analysis of lower divertor tiles is in progress and cleaning methods are being evaluated. Inspections of the HHFW antennas will determine if repairs are needed. The NBI group will replace all three ion sources and the TIV this outage. New bake-out system controls will be added to allow the three new NB sources to be conditioned during the vessel bake. Multi-stage firing controls will be added to the CHI Cap Bank.

Engineering Operations Outage Status: Diagnostic ground (Class 2) upgrades and add’l class 4 power circuits will be complete for this year’s run. In-vessel measurements are being made to install a liquid Lithium Divertor next year. Copper and insulation materials have been packaged and are ready to ship to ASIPP to fabricate the new OH coil. Studies to upgrade for sub-cooled operations continue.

Engineering Operations Outage Schedule: In-vessel construction activities will continue until mid-October before starting ~ 1 month of diagnostic calibrations for the upcoming run. The NB duct will be re-installed on November 20th for a late November pump-down and leak check. Twelve days of bake-out will be performed in early December. NB ion source conditioning will go on in parallel with the bake. Cooldown, leak checking, and add’l time for diagnostic calibrations will follow with plans to start the ISTP in the early part of January. Plasma operations is expected in the second half of January. An early start this year will give us the add’l time needed next year to install the new OH coil, and possibly to implement a liquid lithium divertor.