Twin Cities Minnesota Zone Meeting Xcel Energy October 27, 2004 St. Paul, MN.

Slides:



Advertisements
Similar presentations
Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
Advertisements

Cleco Transmission Planning Summit 2013
AN INTRODUCTION TO THE MIDWEST ISO By Bill Malcolm Manager-State Regulatory Affairs Pierre, South Dakota June 9, 2006.
Sistan & Balouchestan Electric Power Distribution Company
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
Cleco Transmission Planning Summit 2012
1 Local Area Planning Update to TRANSAC – December 16, 2014.
North Mankato Load Serving study Xcel Energy Great River Energy.
SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Eau Claire Area Study Northern MAPP Subregional Planning Group January 11, 2007 Daniel Kline.
Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission Study Presentation to National Wind Coordinating Committee June 22, 2005 W Grivna, PE.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Xcel Energy Projects From 2008 Reliability Assessment.
Midwest Energy, Inc. Transmission Planning and Expansion
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
Transmission planning in Vermont Past, present and future Docket 7081 workshop By Dean LaForest 9/19/05.
Potential Transmission Construction Scheduling In Southern Minnesota--- Fall Spring 2006 Xcel Energy has posted Significant Transmission construction.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Rocky Mountain Power Sub Transmission Five Year Study Findings and Kick Off Attachment K Meeting September 10, 2015.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
0 CapX /1/2015 CapX 2020 Transmission Plan: Ensuring Reliable Electricity.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
1 Transmission Line Projects in Maryland – an Overview Sandra S. Patty PPRP - Manager, Transmission Projects PPRAC Meeting Country Inn & Suites, Annapolis,
Lyndonville Electric Department Feasibility Analysis Review December 2,
NSP System. NSP Supply Plans: Generation and Transmission Betsy Engelking Betsy Engelking Director, Resource Planning Director, Resource Planning Xcel.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
Southwest Renewable Energy Transmission Conference May 21, 2010 This report contains transmission planning data that may be conceptual in nature and is.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
1 Entergy Transmission Planning Summit New Orleans, LA July 10, 2003 Generation and Transmission Development in the Southeastern United States.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
PJM© Market Efficiency RTEP Proposal Window PJM TEAC 1/9/2014 – Market Efficiency Presentation.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies) 
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Freeport Area Master Plan Project -
2016 RTP Update November, 2016 RPG Meeting.
Excelsior Energy’s Mesaba Energy Project
Local Area Planning Update to TRANSAC – June 29, 2017
Excelsior Energy’s Mesaba Energy Project
DEC System Voltage Planning - June 2018
Excelsior Energy’s Mesaba Energy Project
Big Stone II Study Update
Presentation transcript:

Twin Cities Minnesota Zone Meeting Xcel Energy October 27, 2004 St. Paul, MN

Overview of Presentation Xcel Energy will present: – Aldrich to St Louis Park 115 kV line – Eden Prairie to Edina 115 kV line – Eden Prairie - Minnetonka Area – Carver County - Waconia Area – Chisago to Apple River Project – High Bridge to Rogers Lake 115 kV line – Blue Lake generation outlet –

– Koch to Inver Hills 115 kV line – Prairie Island to Red Rock 345 kV circuit #2 – Oakdale to Tanners Lake 115 kV line – Champlin to Champlin Tap to Crooked Lake 115 kV – Twin Cities 345/115 kV transformer capacity Overview of Presentation

Aldrich-St Louis Park 115 kV

Aldrich-St Louis Park 115 kV Line Need: –Under some summer peak conditions, the line may overload –Worst case outage of the 345 kV double circuit carrying the Parkers Lake-Dickinson line and the Parkers Lake Elm Creek line; Solution: –Re-conductor the line by summer 2006 to enable it to carry more power

Edina-Eden Prairie 115 kV Line

Need: –Under some summer peak conditions, a one mile section of this line may overload –Outage of the double circuit carrying the Parkers Lake-Cedar Lake and Parkers Lake-Bassett Creek 115 kV lines Proposed Solution: –Upgrade capacity of 1 mile section of line –Final decision expected early 2005

Eden Prairie- Minnetonka Transmission System Excelsior- Westgate 69 kV reconductor 2006 Westgate 80 MVAR capacitor 2008

Eden Prairie-Minnetonka Area Needs: –Outage of Scott County-Chaska 69 kV line overloads Excelsior-Westgate 69 kV line in 2006 –Outage of Westgate-Eden Prairie 115 kV double circuit line results in low voltage in 2008 –Outage of Scott County-Chaska 69 kV line overloads the reconductored Excelsior-Westgate 69 kV line in 2011

Eden Prairie – Minnetonka Area Short-term upgrades: –Reconductor Excelsior-Deephaven-Westgate 69 kV line and Westgate 115 kV capacitor –Expected in-service of 2006 (line) and 2008 (capacitor) Long-term upgrade: –Scott Co - Westgate 69 kV rebuild to 115 kV (approximately 2011) –Will be reviewed again in upcoming twin cities long range studies

Westgate to Scott County 115 kV line option Westgate to Scott County 69 kV line rebuild to 115 kV (2011)

Carver Co - Waconia Area Needs: –During summer peak load conditions, the Glencoe-Young America 69 kV line may overload by 2008 – outage of future McLeod-Glencoe 115 kV line

Carver Co – Waconia Area Long-term upgrade options for 2008: –Rebuild Glencoe-Carver Co 69 kV line to 115 kV –Rebuild Glencoe to West Waconia 69 kV line and reconfigure 69 kV system to 115 kV –Expected to complete review studies in Spring 2005

Chisago – Apple River Project Needs: –Outage of Apple River 69 kV source may result in overload of Arden Hills-Birch 69 kV line –Outage of Apple River 69 kV source may result in low voltage at Shafer, Scandia, and Sand Lake –Outage of Arden Hills 69 kV source may result in overload of Apple River-Garfield 69 kV line –Using operating procedures to defer upgrades into the later 2000’s.

Chisago – Apple River Project Options examined: –Chisago-Lawrence Creek 115 kV line and Lawrence Creek-Apple River 161 kV line. Recommended plan –Chisago-Apple River 69 kV line rebuild –Reconfigure 69 kV system and add reactive support –Distributed generation is cost prohibited Update: Project approved in Wisconsin. Certificate Of Need to be filed in Minnesota late this fall

Chisago Co-Lawrence Creek 115 kV line Lawrence Creek-Apple River 161 kV line New Lawrence Creek substation (2006)

Rebuild Chisago-Apple River 69 kV line New Lawrence Creek substation (2006)

High Bridge-Rogers Lake 115 kV Line

Need: –This has the potential to overload under certain operating conditions – Operating procedure: generation redispatch (being reviewed annually) New Factor: – High Bridge and Riverside generation are scheduled to be upgraded and converted from coal to gas/steam combined plants as part of the Metropolitan emission reduction program (MERP)in – High Bridge to Rogers Lake 115 kV line may potentially be aggravated by the MERP projects

High Bridge-Rogers Lake 115kV Line Status: – MISO is currently performing transmission service request studies for the High Bridge and Riverside generation upgrades

Blue Lake Generation Increase Project Need: Generation increase of about 395 MW at Xcel Energy’s Blue Lake Substation in Shakopee Expected in-service date of June 2005 Requires additional transmission outlet Solution: Interconnecting to the existing McLeod to Black Dog 230 kV was the recommended alternative Reconductor of 8 miles of Blue Lake to Black Dog 115 kV line.

Blue Lake generation increase project

Koch to Inver Hills 115 kV Need: Under summer peak conditions, this 2 mile line may overload. Outage of Black Dog to Riverwood 115 kV line Solution: Upgrade Inver Hills to Koch Refinery 115 kV along with substation equipment at Inver Hills and Koch Refinery substations in 2006 Final decision expected early 2005

Koch to Inver Hills 115 kV

Prairie Island to Red Rock 345 kV circuit #2 Uprate Need: One of the two parallel 345 kV lines build to an older standard Under some summer peak load conditions, this line may have insufficient ground clearance Outage of the double circuit from Blue Lake to Prairie Island and parallel Prairie Island to Red Rock 345 kV line. Solution: Increase the line clearance Final decision expected early 2005

Oakdale to Tanners Lake 115 kV Need: Under some Summer peak load conditions, the line may overload Outage of Red Rock to Woodbury 115 kV line Recommendation: Upgrade 5 mile Oakdale to Tanners Lake 115 kV line in 2005 or Final decision expected in early 2005

Oakdale to Tanners Lake 115 kV

Champlin to Champlin Tap 115 kV Need: Under some Summer peak load conditions, the line may overload Outage of the 345 kV double circuit Elm Creek to Parkers Lake line and the Sherburne County to Coon Creek 345 kV line Recommendation: Upgrade capacity of 2.4 miles line in 2005 or 2006 Expect final decision in early 2005

Champlin to Champlin Tap 115 kV

Champlin Tap to Crooked Lake 115 kV Need: Under some Summer peak load conditions, the line may overload Outage of Coon Creek to Parkwood 115 kV Recommendation: Upgrade capacity of 2.4 miles line in 2005 or 2006 Expect final decision in early 2005

Champlin Tap to Crooked Lake 115 kV

Twin Cities 345/115 kV Trans- formers

Twin Cities 345/115 kV Transformers Needs Identified: –Under some summer peak conditions Eden Prairie 345/115 kV may overload for parallel transformer outage Parkers Lake 345/115 kV may overload for parallel transformer outage Red Rock 345/115 kV may overload for parallel transformer outage May be aggravated by reduced Twin Cities metro 115 kV generation levels. Twin Cities 10 year planning study expected to be initiated during 2005.

Any Questions/ Input?