FIDIC MDB Conference Brussels Putting Your Money Where Your Mouth Is OR Practising What Your Preach The Funding (or not) of DABs by International Banks.

Slides:



Advertisements
Similar presentations
1 COURT OF ARBITRATION FOR SPORT by Felix Majani University of Tillburg, Spring Semester 2010.
Advertisements

ALTERNATIVE METHODS OF DISPUTE RESOLUTION (ADR)
Contracts – important issues
+ African Legal Support Facility Negotiations of natural resource contracts : Role of ALSF 2013 African Legal Support Facility Stephen Karangizi Director,
The role of the Parish Clerk Local Determination of Complaints.
© PHJ Chapman 2006 DISPUTE RESOLUTION BOARD FOUNDATION 6 th INTERNATIONAL CONFERENCE 6/7 th May 2006 Budapest Dispute Boards – A new force to be reckoned.
The ICC DISPUTE BOARD RULES DRBF 6th Annual International Conference Programme Budapest 6-7 May 2006 Presentation by Katherine González Arrocha Senior.
Research and Innovation Summary of MS questions on the Commission's proposal for DG Research & Innovation Research and Innovation Rules for Participation.
Pennsylvania Council of Mediators Resolving Disputes Through Mediation © PA Council of Mediators –
Last Topic - National Security Measures taken to ensure national security include Pakistan National Security Council (PNSC) Elements of National Security.
The legislative framework for public procurement: implications for the 2010 ARV tender Jonathan Berger Senior Researcher AIDS Law Project Friday, February.
EVALUATION OF DISPUTE RESOLUTION METHODS. Strengths of Mediation  Strengths 1) Mediation is often less expensive. Mediation avoids the costs of a trial,
Unlawful Internet Gambling Enforcement Act Final Rule Joseph Baressi June 3, 2009.
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
OAG Office of the Auditor-General Promoting Accountability in the Public Sector Using Audit to Oversee Public Procurement Edward Ouko Auditor-General Kenya.
Module five: Session Two M5S21. Training objective To review the various financing options available to road contractors M5S22.
“Lessons Learnt” workshop on 18 th June 2015, Sofia Project Implementation Support Service Agreement (PISSA) TA BG BSF S1 – Procurement & FIDIC.
ZHRC/HTI Financial Management Training
Performance of Contractor Agreements: Practical Issues Kyiv, September 2012 Kristina ARTEMENKO EU Project "Harmonisation of Competition and Public Procurement.
CURRENT PROPOSALS FOR FURTHER INTRODUCTION OF DISPUTE BOARDS WITHIN THE CONSTRUCTION INDUSTRY IN ROMANIA.
DRBF 6th annual International Conference 6-7 May Budapest, Hungary Ladies and Gentlemen, dear Guests, First of all, I would like to thank the organizers.
The Employment Act 2008 – A Critical Overview Dispute Resolution & Tribunal Procedures: Overview of the New Procedures IER Conference 2009 _______________________.
HARNESSING INFORMAL CROSS BORDER COMMERCIAL DISPUTE RESOLUTION MECHANISMS FOR ECONOMIC DEVELOPMENT IN WEST AFRICA Presented by Oluwafemi A. LADAPO (Chartered.
WTO FORUM: ARTICLE 25 OF THE DSU Christian Albanesi Managing Counsel ICC International Court of Arbitration.
Background of PPP Negotiation
AMENDED LAWS FOR UTILITY COORDINATION 2009 AASHTO R/W & Utilities Subcommittee Conference April 22 nd.
Trends in dispute resolution in Africa
21 September 2010Social Dialogue European level1 Situation and current problems of Social Dialogue in the Private Security Sector from the European point.
The Private Finance Initiative n Advantages * Benefits of the PFI The major appeal of the PFI for the government is that the cost of the hospital does.
Private sector’s experience on public procurement practices in Rwanda Presented by: Eng. KAZAWADI Papias Managing Director, Star Construction Company Ltd.
1 Smart Public and Private Procurement Lukáš Klee for BCC in CR Procurement in the construction sector and the use of FIDIC contracts British Chamber of.
Investment Funds Conference “Collective Investment Funds in the Qatar Financial Centre – Confidence and Opportunity” November 26-27, 2007 Michael Webb.
Date: 16 April 2010 Adapting FIDIC Standard Forms for Local Conditions and Regulations TCDPAP Annual Conference - '‘New Approaches and Solutions for Consultancy.
“ ALL TOGETHER NOW: INNOVATIVE CONTRACT MANAGEMENT WITH DISPUTE BOARDS ” PRESENTERS: “ ALL TOGETHER NOW: INNOVATIVE CONTRACT MANAGEMENT WITH DISPUTE BOARDS.
FIDIC MDB Conference Brussels June 2012 © European Bank for Reconstruction and Development 2010 | EBRD Procurement considerations when financing.
ACC Europe ADR Forum Shopping: What are the options for dispute resolution outside litigation?
Third Party Alternative Dispute Resolution. Alternative Dispute Resolution (ADR)?  It involves the application of theories, procedures, and skills designed.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) April, 2008 Tegucigalpa, Honduras Filip Drapak.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.1 Steps in the Licensing Process Geoff Vaughan University.
CONSTRUCTION ADMINISTRATION Claims and Disputes Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate Program.
1 Chapter 33 International business Copyright © Nelson Australia Pty Ltd 2003.
Dispute Prevention The Dispute Resolution Adviser (DRA) System Colin J Wall Global Mediation Services Ltd Prague June 2013.
Special Railways Phase III Proposed approach to regulatory changes Jakarta 16 May 2011.
LSylvester1 INTRODUCTION TO NEGOTIATED RULEMAKING FEDERAL MEDIATION AND CONCILIATION SERVICE.
ALTERNATIVE METHODS OF DISPUTE RESOLUTION (ADR). WHY IS ADR NEEDED? Courts expensive Courts time-consuming Courts traumatic Public hearings bring unwelcome.
1 DISPUTE SETTLEMENT THROUGH ADJUDICATION N D Sharma.
Change Orders. CO Proposals Initiated by owner or GC –Owner requests estimate for work proposed –GC CO results from changed site condition or response.
Employment Act 2008 IER Conference 2009 _______________________.
ADR within the MAP - Alternative or Supplement to Arbitration? Dr. Arno Gildemeister.
P.R.I.M.E. Finance Panel of Recognized International Market Experts in Finance The role of experts in complex financial cases: DIFC Court case study (Al.
THIRD PARTIES. Negotiation would appear to be the best way to settle a dispute Parties control process Flexible Places responsibility to resolve solely.
The institutional system of public procurement in Hungary Dr. András Nagy Public Procurement Council Hungary.
CESA Conference 2014 Draft Resolutions. Procurement 1.Distribute CESA position paper to members and invite comment 2.Work with clients on improving procurement.
Public Procurement Principles and Applications Basic Level: Trainer’s Manual Inter – American Development Bank Chapter 4: Procurement of Works December.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
BIMILACI 2007 Best Practice Procurement of Engineering Services Washington, D.C. May , 2007 Gregs Thomopulos, P.E., FACEC Executive Committee Member,
REPUBLIC OF ALBANIA PUBLIC PROCUREMENT AGENCY Eighth Regional Public Procurement Forum May, 22-25, 2012 Tirana
January 2016 Role and Function of the FMCS. Statutory Mission 2 Created in 1947 as an Independent agency under Taft-Hartley Act.
Law LA1:Dispute Resolution THE CIVIL JUSTICE SYSTEM DISPUTE RESOLUTION.
Alternate Dispute Resolution - ADR ADR Most people think of legal disputes being resolved through the courts; consulting a solicitor and sometimes also.
An introduction to the IPPC Dispute Avoidance and Settlement System IPPC Secretariat Regional IPPC Workshop 2015.
Charles University – Law Faculty October 2012 © Peter Kolker 2012 Class III
Procurement and Contract Management Training
INTERNATIONAL FAMILY MEDIATION - Central Contact Points
Introduction to FIDIC - Manuals
Gordon L. Jaynes A DAM GOOD THING Gordon L. Jaynes Copyright 2008.
Tim Ahern Consultancy Ltd. tim. Tel;
Robert Plumb Scheme Liaison Manager 15 January 2015
What is a Dispute Board? A Dispute Board is composed of 1 or 3 neutral individuals who help the Parties avoid disputes or resolve disputes. If necessary,
Presentation transcript:

FIDIC MDB Conference Brussels Putting Your Money Where Your Mouth Is OR Practising What Your Preach The Funding (or not) of DABs by International Banks Murray Armes 25 June 2012 ©2012 Murray Armes

DISPUTE AVOIDANCE FIDIC Contracts are unique Provision for dispute avoidance The Dispute Board is the vehicle for dispute avoidance Dispute avoidance is worthwhile Disputes are costly in money, time and reputations MDB Contract provides for a Standing Board The MDB Contract promotes dispute avoidance ©2012 Murray Armes

WHY USE A DAB? DB costs 0.05%-0.26% of the construction costs About 99% of disputes referred are resolved in <90 days, average cost about 0.02% of the value of the dispute 98% of referred disputes end with the DB Of the 2% remaining, half are subsequently upheld Of the 1% of decisions upset by arbitration/courts, most due to procedural irregularity, not the substance Plus savings in management time, legal costs and reputation ©2012 Murray Armes

WHY ARE DABs SOMETIMES NOT USED? Previous adverse decisions Forum in which Contractor disputes can be dealt with Lack of education/training Unrealistically optimistic expectations for no disputes Another layer of dispute resolution Cost Lack of funding ©2012 Murray Armes

FUNDING THE DAB Development Banks fund projects in developing countries Borrower may not have access to other funding Borrower may not have access to foreign currency Borrower may be unable to pay for a DAB……. ….unless the funds are available from the bank Cost of the DAB could be included in the funding ©2012 Murray Armes

FUNDING POLICY Banks encourage use of DABs (MDB Contract) But there is no consistent funding policy JICA funds DBs and encourages others to do so (JICA Dispute Board Manual 2012) ADB is keen to have more training (DRBF Training in Africa) Many banks do not provide funding for training or for the formation of the DAB Some banks will not fund “litigation” (EU IPA Implementing Rules Article 34, 3(d)) The EU instead promotes mediation (EU Statutory Instrument 2011 No 1133, The Cross-Border Mediation (EU Directive) Regulations 2011) ©2012 Murray Armes

REACTIVE vs PROACTIVE AVOIDANCE Mediation takes place after a dispute has crystallised and parties have taken up positions Mediation is reactive The MDB Contract allows the DAB to avoid disputes The DAB process is proactive The DAB deals with issues before they become disputes Dispute avoidance is very cost effective ©2012 Murray Armes

CONSEQUENCES OF NOT FUNDING THE DB - 1 (1)Where a “standing” Board is required, the parties delay establishing the Board until after a dispute has arisen which they are unable to resolve by negotiation. The intended dispute prevention role of the Board is lost; (2)A “standing” Board is established timeously but to “save money” the Board is allowed to visit only once per year, proactive dispute avoidance is diminshed; (3)Board members are selected by price competition with little or no evaluation of other facets of a Board member’s suitability for the particular project leading possibly to a poor quality board and at worst a dysfunctional board; (4)A single board member is appointed for a complex job. The benefits of having a board of several members with varied experience are lost; ©2012 Murray Armes

CONSEQUENCES OF NOT FUNDING THE DB - 2 (1)In an effort to “save money” an “ad hoc” Board is agreed even though its use on the type of project involved is contrary to FIDIC guidance, the opportunities for dispute avoidance are lost; (2)To “save money” the party receiving the financing seldom (if at all) appears at Site during the Board Site visits, the opportunities for dispute avoidance are diminished or at worst lost; (3)Provisions regarding implementation of Board decisions are not developed in a way which will avoid future difficulties of enforcement under the law applicable to the contract; (4) Lacking the financing to pay any sums awarded by a Board, all decisions favourable to the Contractor are not honoured and are referred to arbitration in order to postpone any actual payment for as long as possible. ©2012 Murray Armes

CONSEQUENCES OF NOT TRAINING Borrower does not understand the role of the DB Borrower does not understand how the DB is to be used Borrower does not understand the dispute avoidance role Borrower unable to guide tenderers Borrower unable to promote advantages (better tenders) Funders can benefit from training… and to help educate the Borrowers ©2012 Murray Armes

THE ROLE OF THE DAB - 1 FIDIC Procedural Rules allows DB to take steps to avoid disputes by: (1) Monitoring the project (2) Regular site visits (3) Meetings with the parties (4) Reviews of issues (5) Assistance in resolving issues (6) Informal opinions Use of “mediation” skills Facilitating solutions None of this is “litigation”….. ….it is project management! ©2012 Murray Armes

THE ROLE OF THE DAB - 2 DB role traditionally carried out by the Engineer The Engineer has traditionally been financed The DB takes on the decision making role of the engineer But only after applying PM procedures to avoid disputes Only if avoidance is not possible is a dispute referred ©2012 Murray Armes

THE ROLE OF THE DAB - 3 Majority of DB roles are PM procedures If a dispute is referred role changes DB Decision is required for access to arbitration The DAB is a portal between Project Management and the first steps to arbitration ©2012 Murray Armes

AN APPROACH TO FUNDING Training to be funded DAB Retainer costs to be funded DAB site visit costs to be funded DAB informal opinions to be funded ….none of this is “litigation”! Banks to provide guidelines on how to estimate DB costs (JICA Dispute Board Manual 2012) ©2012 Murray Armes

THE FUTURE - 1 Funding for adjudication procedure? The JICA DB Manual guidance on estimating DB costs More DABs to be established Pool of trained, experienced DB members Dispute Avoidance = LESS WASTED COST + BETTER TENDERS + MORE SUCCESSFUL PROJECTS DABs are mandatory in the MDB Contract Banks use the MDB Contract Value of DABs is recognised but not all banks will fund them……. ©2012 Murray Armes

THE FUTURE BUT WHY NOT? ©2012 Murray Armes