1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review.

Slides:



Advertisements
Similar presentations
Replacement of the Queens Approach Bronx-Whitestone Bridge
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
Finally! – A Process that Looks at Environmental Risk Early J. S. Irving Environmental Compliance Idaho National Laboratory.
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Chapter 14 Pricing General Expenses. Objectives Upon completion of this chapter, you will be able to: –Define general expenses –Use a checklist to identify.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Project Startup Hmwk Due 10/11/ # 1,3,7,8 8.9 #1 9.7 #1,3,4,5, #1,2,3,4,10.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
Company LOGO C o n s t r u c t i o n R e p o r t P r o f e s s i o n a l C o n s t r u c t i o n M a n a g e m e n t 2006 Prepared by:
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Greenfield District Utility/RR Engineer, INDOT
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Thomas C. Nehring, P.E. Lead Electrical Engineer CFAC Review November 9-10, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities.
M. Scharfenstein - ES&H Coordinator 8 June 2009
PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Discussion Topics Construction Contract Administration Lessons Learned Other Construction Issues Questions? / Comments (Anytime)
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities LEED-ESH-Facility Utilization May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities NSLS-II PAC Review.
Module 7: Construction Phase
Introduction to Construction General Permit Inspections.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities & Beam Stability Marty Fallier Director for Conventional Facilities NSLS-II Beam Stability Workshop.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
 Coordinating construction related training  Following and gathering info for construction related performance measures  Follow Contract Modifications.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
VERMONT YANKEE Transitioning into SAFSTOR ​SEPTEMBER 2, 2015 Paul Paradis Director Decommissioning.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
Environmental Restoration Projects Methods for Safety Culture Realization November 30, 2007.
Foundations of Technology.  To familiarize students with the function, applications, and requirements of construction management.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Status Update Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Steve Sawch Asst. Director, Construction Management NSLS-II CF Construction Preparations May 8, 2008.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Procurements Thomas C. Nehring, PE Lead Electrical Engineer Conventional Facilities Advisory Committee - Review.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
Regulatory Streamlining Task Force Update Discussion Item December 6, 2011 Board of County Commissioners.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
Managing Quality with Quality Through the Construction Management Leadership Manual Presented by: Aleksandr Sergek, PE, PMP Allison Justiniano, LEED AP.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
Restructuring of the Finnish Infrastructure Administration Draft
Second Street Closure for Construction of B21 1/16/16 – 1/31/16.
The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C.
Region’s Core Services 202/17/2014 Integrity ∙ Excellence ∙ Respect Provide leadership, administrative support, procurement and budgetary and financial.
Central Houston, Inc. Houston Downtown Management District 909 Fanin, Suite 1650 Houston, Texas / Operations
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
A New Paradigm for Utility Coordination Kenny Franklin VP of SUE Development Blood Hound.
Page Headline Project Management Cost & Schedule Review Rob Michnoff.
Sources of Energy ELECTRICAL MECHANICAL PNEUMATIC FLUID AND GASES
Management Breakout: MREFC Budget Summary Victor L
Meeting of the LCLS Facilities Advisory Committee
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
Conventional & Experimental Facilities Dept.
M. Scharfenstein - ES&H Coordinator 14 May 2009
A Paradigm for Utility Coordination
Department Of Energy Review Linac Coherent Light Source Project
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review March 10 –11, 2009

2 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Outline Site Preparation Purpose Existing Site Prior BNL Work Site Preparation Scope Lessons Learned Path Forward

3 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Purpose Site Preparation was included as an early procurement (authorized pre-CD-3) to: Provide an activity that reduced schedule risk to the Ring Building by: –Reducing potential for unknown utilities or site conditions delaying construction start –Reduce GC schedule risk during early construction –Be mobilized to correct any deficiencies left over from previous activity at the site (leftover facilities or environmental liabilities) It provided a number of other benefits as well

4 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation - Existing Site Bldg 100 Demolished Bldg 87 Demolished Bldg 210 Demolished Bldg 481 Demolished Bldg 211 Demolished Ring Bldg Footprint Construction Area Perimeter Existing Buildings to be removed prior to construction Bldg 209 Demolished

5 BROOKHAVEN SCIENCE ASSOCIATES Prior Work by BNL On-going BNL program removed excess facilities/structures Relocated Warehouse Facilities Demolished Existing Facilities and Slabs/Foundations Prepared Recycling Area and recycled concrete foundations Remove Rail Road tracks and ties Performed clean up and removal of oil-water separators and related sanitary piping

6 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Scope Site Preparation Scope/Construction Packages Clear and Grub Trees Abandon Existing Site Utilities/Relocate Utilities Abandon Monitoring Wells/Relocate Wells Verify no environmental liabilities Provide Utilities for Construction (power and communication)

7 BROOKHAVEN SCIENCE ASSOCIATES Site Prep Status All base scope work completed -2/17/09 running under budget Some minor punchlist / closeout items remain Added some items to scope Enlarged recharge basin & stockpiled structural fill due to seasonal environmental permit constraint Added maintenance of erosion control until Ring Bldg Contractor mobilizes Added clean-up of miscellaneous debris No evidence of environmental liabilities Ready for Ring building GC

8 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation – Site Clearing View of Cleared Site From NSLS I

9 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation – Site Clearing Tree Clearing Along Grove Street

10 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation – Electrical

11 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Summary –Site access control requirements –NSLS-II CM Staff increased knowledge of BNL systems, procedures, personnel and points of contact –Understanding of requirements for shutdowns, notifications, permits and utility tie-ins –Utility mark-outs and surveys will assist Ring Building utility installation –Improved coordination of field inspectors and safety engineers in oversight of contractor performance

12 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Better understanding of site access control requirements –Repeated unauthorized incursions of area by Lab personnel -Despite Signs, Roadblocks and Web & Postings –Additional time & effort spent: -Chasing Unauthorized Personnel from Area, -Maintaining Signs & Barricades –On-site fauna destroyed construction fencing in path to food, habitats –Need for well managed “permanent fence” instead of temporary construction fence

13 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned NSLS-II CM Team new to BNL –Different Culture –“Outside world” experience Site Preparation work facilitated: –Knowledge / Understanding of BNL/DOE expectations and requirements –Enhanced familiarity with BNL systems, procedures, personnel and points of contact

14 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Lessons Learned –U nderstanding of requirements for shutdowns, notifications, permits and utility tie-ins Determine Timeframe required for coordination with BNL Depts. Requirements for off-hour work due to maintenance of operations, personnel availability.

15 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Lessons Learned –Utility mark-outs and surveys will assist Ring Building Utility installation: Facilitated planning for temporary utilities, as well as familiarity with existing and surrounding site utilities, infrastructure; Exposed unmarked structures, utilities, and identified “known- unknown utilities”.

16 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Lessons Learned –Improved coordination of field inspectors and safety engineers in oversight of contractor performance: Good Planning & Project Oversight by CF & ESH Teams, Collaborative Approach With Contractors Mitigated Weather Impacts & Potential Impacts due to Scope Changes, No Impact to Vehicular & Pedestrian Traffic.

17 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Lessons Learned and experience brought –From “Outside Staff”: New Technologies, Systems for Administering, managing projects; Implementation of Primavera Contract Manager, “Slight” Modification of BNL Procedures to incorporate experiences Experience with CM scheduling and estimating methods Experience with claims prevention and mitigation

18 BROOKHAVEN SCIENCE ASSOCIATES Path Forward Employ Lessons Learned on Site Preparation Start Permitting Process Early, Recommend Site Access Control Measures to Ring Building Contractor Continue to Coordinate with BNL Site Operations to preclude delays, Keep current with BNL Procedures / Systems Partner with Ring Building GC to expedite mobilization and communication, to facilitate efficient resolution of issues as they will inevitably arise.