MUSURUMILLI PROJECT 15 km 35.4 km Project cost : 207.00 cr TUNNEL MAIN CANAL 2.7 KM RESERVOIR HEAD SLUICE 2.7 mt X 1.6 mt LEFT EARTH DAM NON OVER FLOW DAM RIGHT EARTH DAM SPILL WAY 86.5 mt DYKE 138 mt SEETHAPALLI VAGU EBD VAGU PICKUP WEIR 15 km 35.4 km HEADREGULATOR EPC Package Works under progress Project cost : 207.00 cr Ayacut : 22643 ac
MUSURUMILLI PROJECT 1 PROJECT PROFILE : Across Seethapallivagu 2 Administrative Sanction : G. O. Ms. No. 204, I & CAD, Dt: 31-12-2004 for Rs. 207.00 Crores 3 No. of EPC Packages 2 Nos 4 Agreement value of 2 packages 118.72 Crs. 5 Budget provision for 2006-07 Rs.33.00 Crs. 6 Expenditure of the project 2004 – 05 Rs. 11.88 Crs. 2005 – 06 Rs. 21.59 Crs. Cum. Exp. Rs. 33.47 Crs 8 Ayacut New ayacut 22,643 acres 9 Land Acquisition Required 3633 acres Acquired 855 acres 10 Forest Land 0.85 hectares Govt. of AP have accorded permission vide G.O.Ms.No.119, Dt.31-10-05 for diversion of forest land
MUSURUMILLI PROJECT 11 Mob. Advance (Rs. in Crores) Paid Recovered 2004-05 : 5.85 -- 2005-06 5.35 2.22 Total 11.20 2.22