1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - tests on prototypes - pipe production by Lamina - gluing exercises - time schedule - conclusions.

Slides:



Advertisements
Similar presentations
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Advertisements

2/9/2004DC status - BVR1 1.Mechanics 2.Foil 3.Frame and Print Anode Inner cathode Hood 4.Pressure control + He bag + target 5.Electronic 6.Schedule Status.
Status Update on Mechanical Prototype in Rome November 6,
R.Valbuena NBI March 2002 CNGS Decay Pipe Entrance Window Structural and Thermal Analysis A.Benechet, P.Cupial, R.Valbuena CERN-EST-ME.
Christine KOURKOUMELIS University of Athens ATLAS Muon Chamber construction in Greece and alignment studies for H  ZZ  4μ decay Como, 8/10/03.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
Operational prototype work at CERN Status report MM Gen. Meeting, 06/11/2013 J. Wotschack1.
HFT Geometry Considerations F.Videbæk BNL. Introduction This presentation is meant to be a living document, updated as more and better information becomes.
Status of the Polarized 3He Target
Theodore Todorov Pixel mechanics november 8th Inner detector upgrade / IBL Activities on cooling LAPP LAPP team Jacky Ballansat, Patrick.
IBL Mock Up IBL Mock Up MANUFACTURING 2011/04/29 François-Xavier NUIRY Maxence CURDY Andrea CATINACCIO CERN PH/DT/PO 1.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
Aluminum bellows for experiments
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Vacuum tests on scintillating fibres. Table of content The Aim of the vacuum tests on the scintillating fibre plane Equipments used in the vacuum tests.
ENGINEERING DESIGN AND FABRICATION OF PETS V. Soldatov¹, D. Gudkov¹, I. Syratchev², A. Samoshkin¹, G. Riddone², A. Olyunin¹, S. Atieh² 1 – JINR, Dubna,
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - prototypes validation and pipe production - microflanges and fixation system - the intervention.
Vacuum / cryo links Mechanical design issues Jo van den Brand, Martin Doets Nikhef Cascina, January 21,
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
1 Advanced Endplate - mechanics: Development of a Low-Material TPC Endplate for ILD Dan Peterson Laboratory for Elementary-Particle Physics, Cornell University.
Spasimir Balev /CERN/ mrad 3 LKr simulation: – very slow, so only events with interesting topology are fully simulated: –  + with.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
First results of an aging test of a full scale MWPC prototype for the LHCb muon system Workshop on “Aging Phenomena in Gaseous Detectors”, October 2-5.
1 CLAS12/Central Tracker review. Saclay 12/09 Stéphan AUNE Central Tracker review Micromegas central & forward tracker  R&D and prototypes  CAD implantation.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
1 Fulvio TESSAROTTO the new RICH beam pipe the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation.
Mechanical Status of EUDET Module Marc Anduze – 05/04/07.
Production of Forward RPC Gaps CMS Forward RPC EDR (10/10/2002 – 11/10/2002) Seong Jong Hong KODEL, Korea University.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
Alain Hervé, ILD Workshop, Seoul 17 February 2009, 4365-ILD-T-Coil-Developments.ppt Possible Coil Developments ILD Workshop - SEOUL - 17 February 2009.
JCOV, 25 OCT 2001Thermal screens in ATLAS Inner Detector J.Godlewski EP/ATI  ATLAS Inner Detector layout  Specifications for thermal screens  ANSYS.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
1 IBF in aligned, misaligned and FLOWER THGEMs The IBF problem Standard THGEM configuration COBRA and extra electrode Misaligned holes FLOWER THGEM solution.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
THE VACUUM BOX FOR COMPASS CRYOSTAT MUNICH 23/10/2007 G. GIRAUDO I.N.F.N. TORINO 1.MECHANICS – OVERWIEV 2.WINDOWS 3.INTEGRATION WITH HODOSCOPE.
14-Dec-15S.Movchan Straw manufacturing and QC1 Straw manufacturing procedure and QC tape and straw parameters specification conditions of straw production:
9 September 2004The Straw Tube Chamber1 The CDC Curtis A. Meyer Carnegie Mellon University Physics Requirements and Specifications Prototype Construction.
Resistive protections Rui de Oliveira 09/12/15
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
Zaragoza, 5 Julyl Construction of and experience with a 2.4 x 1 m² micromegas chambers Givi Sekhniaidze On behalf of the Micromegas community.
1 Fulvio TESSAROTTO CERN, 13/11/ COMPASS THGEM meeting Construction of the large size Hybrid Prototype The bulk Micromegas technology Examples of.
1 Fulvio TESSAROTTO GDD meeting, CERN, 01/10/2008 Trieste THGEM news New THGEM test in the COMPASS hall New THGEM test in the COMPASS hall Preparation.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Chamber mechanics Chamber mechanics Production in China Peking University Group – 20 Aug
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
Practical aspects of small aperture quadrupoles Dr Ben Leigh Tesla Engineering Ltd.
MVD COOLING STATUS-PAST AND UPDATES PIXEL COOLING PROJECT: -STUDIES and TEST on MATERIALS (Carbon Foam) -THERMAL FEM ANALYSES and TEST on DISKS and STAVES.
Pierre Delebecque Cooling – upgrade 2012 May 31 st 1 Inner detector upgrade / IBL Activities on cooling LAPP LAPP team Jacky Ballansat, Patrick.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
NA 62 – straw detector Content Detector Specifications Chamber design Straw design and specifications Calculations and measurements Prototyping Plans Straw.
Vacuum System P. Chiggiato TE-VSC
Alignment of the CMS Tracker
Update on Pavia MM mechanical prototype
Ti/SS transitions A.Basti INFN-PISA*
MVD Mechanics update EXTERNAL FRAME: NEW DESIGN
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Quality Control in Straw Production
C.Clerc ILD session, ALCPG /03/2010
Tracker Outer Barrel COOLING Antti Onnela, CERN.
Integration issues at IHEP
Far Detector Activities Late 2017 – Early 2018
Pierre-Alexandre Thonet
WG4 – Progress report R. Santoro and A. Tauro.
Challenges for FCC-ee MDI mechanical design
Chapter 5 Power Estimation in Extrusion and Wire-rod Drawing
Presentation transcript:

1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - tests on prototypes - pipe production by Lamina - gluing exercises - time schedule - conclusions COMPASS TB meeting, CERN, 10/11/2011 Fulvio Tessarotto

2 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Activity on prototypes - We received from Lamina 4 “non aluminized” pipe pieces: - diam. = 100 mm, L = 1.3 m, tot. thickness ~ 180 μm - 4 layers of 36 μm thick Mylar wound and glued with S100 bonding agent - One was cut to measure the material properties and perform gluing tests - inner diam. = , good compatibility with Araldite 2011, … -The second one has been equipped with aluminum end-cups to perform: - pressure tests (cylinder only for overpressure > 6 mbar) - deformation tests - He leak tests - Progress was possible because we solved problems of: - location (we equipped a room dedicated to these tests in Trieste) - technical manpower (two technicians are now helping on this project) - budget (INFN accepted to support the new RICH pipe)

3 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The prototypes without Al coating

4 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The Al flanges for this test

5 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The gluing for this test

6 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The result

7 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The first He leak test

8 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Temperature and pressure recording

9 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

10 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Simple He leak measurement - Volume = 10 l, fluxed with He, overpressure = 10 mbar, input closed. - Internal overpressure monitored for several hours: - External pressure, tempereature, humidity recorded too. - The overpressure evolves with T and P - Once corrected for temperature and pressure the observed leak is ~ 0.3 mbar/h or less. This corresponds to ~ 3 ml/h leak PRELIMINARY CONCLUSION: MYLAR AND GLUE ARE VALIDATED A stainless steel pipe with 240 mm radius and 2 m length, with flanges and gas connections has been bought and will host the higher accuracy He leak measurements and the other tests.

11 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 03/02/2011 at 25 º C and for 1 bar pressure difference, a 25 μm thick Mylar foil with a surface of 645 cm 2 leaks “typically” 150 cc/day  1 m 2 will leak ~0.1 l/h From the datasheet of the DuPont Teijin Mylar polyester film (the measurements have been performed using a 25 μm thick Mylar foil) Our validation figure is 10 ml/h Which includes a safety factor of 4 with respect To the maximum allowed leak rate of 1l/day For the prototype which has a surface of 0.4 m 2 and no coating we would expect a leak of ~ 40 ml/h divided by a “thickness factor”

12 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 For water vapor, the increase from 25 μm to 144 μm of the mylar thickness corresponds to a decrease of a factor ~8 in the transmission rate If the factor is the same for He, we would expect ~ 5 ml/h leak. We see ~3 ml/h expected leak: tickness factor

13 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 End-caps and gluing studies

14 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 microflange

15 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 microflange

16 Fulvio TESSAROTTO production of the pipes by Lamina The base material, coated by Sheldahl, has been checked by Lamina: - measured thickness = 27 μm, - surface resistivity = 0.5 Ω / □ (The amount of material is sufficient for 10 pipes) 4 pipes are being produced this week: 100 mm diameter, 1800 mm long pipes - 4 layers of Mylar, 25 μm thick, with 200 nm Al coating - spiral winding and gluing via 5 μm thick cross-linking polyester - 2 pieces will have an extra layer of Mylar, 36 μm thick (no Al coating) (total thickness ~170 μm) - 2 pieces without the 36 μm extra layer (total thickness ~130 μm Mylar)

17 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 The base material is the same as:

18 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Technical data

19 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Engineering drawings from Draw CodeMINMAX I.D99,7100,30 W.T0,1000,130 O.L1800,01810,0 Confidential Property of: Lamina Dielectrics Ltd, Daux Rd, Billingshurst, RH14 9SJ Tel: +44(0) Fax: +44(0) CUSTOMER:INFN PROJECT: Drawn by:PMH Approved by:DG Material: Polyester non shrink film thickness mm coated with 2,000 Angstroms of Al All dimensions in mm: Tolerances Linear:Angular: X+/- 0.5mm+/ X.X+/- 0.1mm X.XX+/- 0.05mm Unless otherwise stated on drawing DEBURR AND REMOVE ALL SHARP EDGES UNLESS STATED OTHERWISE Notes: Bond agent S Layers of film wound at half pitch all Aluminium surfaces to point to the inner bore of the tube TITLE: 100 mm internal diameter detector Drawing No.: Issue:1Date:

20 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Pictures of the pipe:

21 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Pictures of the pipe:

22 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Pictures of the pipe:

23 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Summary of default choices: Issue default choice Removal of presently used pipe Cutting and extracting it Material for the thin pipe 4 layer aluminized Mylar, < 0.8 ‰ X Geometry 2 pipes 100 mm diam, 1600 mm long Gas He, flowing at few l/h, 20 mbar overpr. End caps PET or microflange: still to be defined Fixation system Rings + wires: still to be defined

24 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Time schedule Pipe prototype production and testsNovember RICH beam pipe production: December Validation tests: January Installation: February Contingency in case of problems: March RICH operation tests with new pipeAprile

25 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011 Conclusions: The thin RICH pipe project is progressing, and problems about procurement, logistics, budget and manpower are being solved. The uncoated prototype allowed to test stiffness, gluing, He tightness. Technical solutions are being tested for end-caps and fixation system. Real RICH pipe prototypes are being produced. They will be tested in the incoming weeks. The present time schedule is compatible with installation in Feb. - March 2012

26 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 05/09/2011 Material budget actual pipe material budget: (0.15 mm / 17.6 mm)8.523 ‰ X 0 goal for the material budget of the new pipe:10% actual =0.852 ‰ X 0 4 layers of 25 μm thick Mylar : (0.1 mm / 287 mm) ‰ X 0 4 layers of 200 nm thick Al coating: (0.8 μm / 89 mm)0.009 ‰ X 0 1 layer of 36 μm thick Mylar: (36 μm / 287 mm) ‰ X 0 4 layers of 5 μm thick Mylar glue: (20 μm / 287 mm) ‰ X estimated total material budget for orthogonal crossing:0.552 ‰ X 0 (with respect to the goal we have a margin of 50% with the present design) The contribution from end caps, fixation rings, gas connections will be relevant For a 5 mrad particle (thickness * 200)  X 0 from the pipe, 5 x 2 mm thick nylon  (10 mm / 367 mm) = X 0 from the support rings

27 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 05/09/2011 We need Accurate description of the mechanical properties of the pipe Estimate of the mechanical stresses applied to the RICH pipe Preliminary definition of the support – fixation system Computing the stresses and the deformations of the pipe (help needed!) Define the acceptable figures for the deformations (are 2 mm o.k.?) Building a testing device for the validation of the prototypes To measure the effect and validate the prototypes and the fixation system scheme