AB/ATB-EA ML, le 30/03/071 MERIT INSTALLATION
AB/ATB-EA ML, le 30/03/072 MERIT INSTALLATION Total supported weight Solenoid: 5500 kg (12000 lbs) Hg System with 23liter Hg: 1800 kg (4000 lbs) Baseplate: 450 kg (1000 lbs) Maximum width of 1.3m (51") to meet CERN facility constraints
AB/ATB-EA ML, le 30/03/073 MERIT INSTALLATION Layout
AB/ATB-EA ML, le 30/03/074 MERIT INSTALLATION Cranes and shaft…
AB/ATB-EA ML, le 30/03/075 MERIT INSTALLATION Solenoid handling with “yellow” cross-bar
AB/ATB-EA ML, le 30/03/076 MERIT INSTALLATION Mercury loop
AB/ATB-EA ML, le 30/03/077 MERIT INSTALLATION Mercury loop handling
AB/ATB-EA ML, le 30/03/078 MERIT INSTALLATION Placing solenoid on the baseplate 1. Baseplate on wedge 2. Solenoid on baseplate 3. Baseplate towed up slope with tractor “VOLK” 4. Wedge removed, traverse down TT2
AB/ATB-EA ML, le 30/03/079 MERIT INSTALLATION Handling with “VOLK” (testing with a dummy in TT2)
AB/ATB-EA ML, le 30/03/0710 MERIT INSTALLATION TT2 to TT2A
AB/ATB-EA ML, le 30/03/0711 MERIT INSTALLATION Same handling procedure for mercury loop…
AB/ATB-EA ML, le 30/03/0712 MERIT INSTALLATION Transport Hg SystemRemove RollersTransport Baseplate Remove Rollers, Level MagnetRoll Hg System into MagnetAdd Rollers
AB/ATB-EA ML, le 30/03/0713 MERIT INSTALLATION Roll System into Beam LineRemove Rollers Elevate & Tilt