March 24th 2010MICE CM26 - Riverside1 MOM Report m. apollonio – Imperial College.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

Summary of MICE 4/4/2008 shift during the ISIS machine-physics period Goals for 04 Apr08 MICE shift: 1. Radiation survey in MICE Hall with target operating,
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MICE Electronics Upgrade P J Smith (University of Sheffield) J Leaver (Imperial College) 17 th June 2009.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference April 22, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Online Reconstruction Update Linda R. Coney UCR Mar 25, 2010.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Computing Panel Discussion Continued Marco Apollonio, Linda Coney, Mike Courthold, Malcolm Ellis, Jean-Sebastien Graulich, Pierrick Hanlet, Henry Nebrensky.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Luminosity Monitor Commissioning MICE Collaboration Meeting March 2010 Paul Soler, David Forrest Danielle MacLennan.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM report Mico Meeting 8/3/2010. DS is down: – beamline highly penalised  all detectors suffer – calibration at low rate only – problem is too high.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Target Online Software J. Leaver 01/12/ /06/2015Imperial College 2 Target Controller Software Software for Stage 1 upgrade nearing completion –Hardware.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 4, 2011.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
MICE CM25 Nov 2009Jean-Sebastien GraulichSlide 1 Online Summary o Detector DAQ o Controls And Monitoring o Online Data Base o Bottom Lines Jean-Sebastien.
MICE CM26 March '10Jean-Sebastien GraulichSlide 1 Detector DAQ Issues o Achievements Since CM25 o DAQ System Upgrade o Luminosity Monitors o Sequels of.
CM26 March 2010Jean-Sebastien GraulichSlide 1 Online Summary o The heplnw17 case o DAQ o CAM o Online Reconstruction o Data Base o Data Storage Jean-Sebastien.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
MICE VC Aug '10J.S. GraulichSlide 1 MOM report o Achievements Since CM27 o Daily Operations o Run Plans o Summary Jean-Sebastien Graulich, Geneva.
Project manager report paul drumm CM16 October 2006.
1 MICE Running L. Coney – UCR MPB – 31 Oct Coney - MPB - 31 Oct 2012Outline Current Running Current Running Shift personnel training Shift personnel.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
Control & Monitoring System Update Contributors: Brian Martlew - Daresbury Laboratory - STFC James Leaver - Imperial College Pierrick Hanlet - Fermilab.
MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8, 2010.
MICE CM25 Nov 2009Jean-Sebastien GraulichSlide 1 Detector DAQ Issues o Achievements Since CM24 o Trigger o Event Building o Online Software o Front End.
Configuration Database Antony Wilson MICE CM February 2011 RAL 1.
Software Status  Last Software Workshop u Held at Fermilab just before Christmas. u Completed reconstruction testing: s MICE trackers and KEK tracker.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
Online Reconstruction 1M.Ellis - CM th October 2008.
MICE Run Plan Sept/Oct 2009 m. apollonio – IC MACHINE PHYSICS USERs RUN NO SHIFT A B C D E.
MICE CM January 2009Jean-Sébastien GraulichSlide 1 Detector DAQ Issues o Achievements Since CM23 o Detector DAQ o Trigger o Online Software o Front End.
MICE VC MOM Report, 25 th February 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - Machine Physics and User Runs - Suggestions.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
Linda R. Coney – 5 November 2009 Online Reconstruction Linda R. Coney 5 November 2009.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
MICE CM28 Oct 2010Jean-Sebastien GraulichSlide 1 Detector DAQ o Achievements Since CM27 o DAQ Upgrade o CAM/DAQ integration o Online Software o Trigger.
Controls & Monitoring Status Update J. Leaver 05/11/2009.
VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
MICE CM February 08Jean-Sébastien GraulichSlide 1 Report on DAQ & CAM o Detector DAQ Status Hardware Trigger Software o Controls and Monitoring (CAM) o.
1 Configuration Database David Forrest University of Glasgow RAL :: 31 May 2009.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
M. apollonio 7/7/2010CM27 - RAL11 Beam-Line Analysis …
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
MICE Computing and Software
Controls & Monitoring in MICE
MOM Report + RUN PLAN m. apollonio – Imperial College
Presentation transcript:

March 24th 2010MICE CM26 - Riverside1 MOM Report m. apollonio – Imperial College

March 24th 2010MICE CM26 - Riverside2 ApollonioOctober 17November 2 CecchetNovember 2December 1 GametNovember 29December 11 HanletDecember 10December 18 Kyberd/RogersDecember 17December 24 SmithJanuary 4February 1 HartJanuary 31March 1 ApollonioFebruary 28March 29Current MOM SolerMarch 28April 24 MOMs since CM25 … CM25 talk

Summary March 24th 2010MICE CM26 - Riverside3 February to Now - BeamLine and Decay Solenoid - DAQ / OnLine - Control & Monitoring - Luminosity Monitor - Target - Running Practice - Network and Access to Data - DATA quality - Conclusions

March 24th 2010MICE CM26 - Riverside4 TGT Q Q Q D DKSOL D Q Q Q Q Q Q TOF0, BPM1, TOF KL CKOV BL AVAILABILITY >0 criticality readiness Beamline … a simple system? 21 elements, some of which critical to transport/study a beam e.g.: no Q1 no beam no TOF0 = no (e,P) study when a critical element is in a RED status the BL is declared unavailable in fact it does not mean we cannot run it BUT it is a limping line... high: needed to run the line medium: desirable but not jeopardizing the DT, unless in special cases low: desirable but acceptable if not present ON-flawless: no real problem with the system ON-regular: generally OK with some remarks OFF: system unavailable due to serious issue DK sol OFF – N2 contamination BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions HV issues on TOF0 unit (channel minicom) temperature issue on BPM-large

March 24th 2010MICE CM26 - Riverside5 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions At CM25 we had a great news: the BL was completed with DK solenoid finally operational 2010 did not bring good luck … DK Solenoid suffered after Linde service work in January … to be clear: the problem is NOT in the SOLENOID, rather in the cooling system - Large concentration of N2 found in the DS cold box - search for leaks - trials to reach <10 ppm level of impurities all unsuccesful - cooling impossible - culprit finally found in a charcoal trap used to filter N2/H2O - it is believed Linde intervention determined that more recent (Matt’s communication) - attempts to bake the absorber failed - probably due to not achieving the required flow rate by using boil-off gas from a N2 dewar - pack of N2 order and arriving (Tue) - Linde expert arriving on site (Tue) - hope this could eradicate the problem

March 24th 2010MICE CM26 - Riverside6 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions A long story short: BL w.o. DS for ~3 months. This poses severe limitations to our run plans Any characterization of the BL (emittance, momentum) postponed Optics different and rate reduced We tried to get the most of it by running calibrations and testing the proton absorber

BL - performance March 24th 2010MICE CM26 - Riverside7 feb/march run period BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions

March 24th 2010MICE CM26 - Riverside8 For the DAQ: A mirror system with upgraded OS and DATE software version has been tested successfully. The migration is scheduled for the next shut down. It should release the limitation on the number of particle triggers per spill. Detailed documentation on the installation procedure for DAQ PC has been produced. Software repository has been installed in the online cluster. BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions

March 24th 2010MICE CM26 - Riverside9 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions - Significant upgrade of the CAM computing infrastructure: 1) reorganized infrastructure to final configuration - computers & monitors -- Have installed 2 additional Operator Interface PCs, a second general purpose EPICS server PC, a backup for the critical 'EPICS client' server and a general purpose NAS drive. All Operator Interface PC monitors have also been upgraded. 2) All regular CAM PCs have been moved to the Rack Room. 3) Operating Systems and Desktop environments of all PCs have been Standardised. 4) One single version of channel archiver -- All Channel Archiver duties have now been officially transferred to the 'EPICS client' server PC. A new web server enables local retrieval of data via the EPICS Java Archive Viewer. This server will be moved to the PPD web services PC (when available), to allow off-site access 5) All CAM software is now managed via the Bazaar Version Control System. Central repositories are hosted on the backup 'EPICS client' server. 6)A Google Docs account has been set up to act as a repository for CAM-related information, facilitating collaboration between members of the Online Group. 7) Soft IOCs for monitoring CKOV/ magnet water temp/ beamstop -- one water leak detection became evident after leak in trench -- MICE hall temperatures

March 24th 2010MICE CM26 - Riverside10 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions - The hardware and firmware for Stage 1 of the Target Controller electronics upgrade are complete. The EPICS software is in development and should be finished by the end of March. We expect to carry out a soak test of the new system in R78 during May. MOM’s naïve question: - will this control system provide an automatic version of the Target Integrity Test ?

March 24th 2010MICE CM26 - Riverside11 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions Documentation available (MICO web page)

March 24th 2010MICE CM26 - Riverside12 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions - Target works well - as of today ~ pulses - all TIT passed - for progress on T2/T3 see relevant talk(s) - Only one remark: - when running at MS delays < 3s we notice the tgt counter misses every second count - a time lag between dip/beep and count is built up - it recovers if MS delay > 3s, otherwise it causes the system to miss a count - ball to experts … - HOWEVER: running at 5s delay = 0.2 Hz is a no way

March 24th 2010MICE CM26 - Riverside13 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions Since NOVEMBER 2009 we agreed with ISIS on a procedure to request a RUN A form is filled in specifying the kind of run needed and it is sent to the MOM: The MOM sends the document to A. Stevens (ISIS) and gets permission to RUN. The DO is informed. The good practice is to hand in the request one week in advance.

March 24th 2010MICE CM26 - Riverside14 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions Some flexibilty from the MOM is expected, however a good practice from requesters is appreciated There is a clear flaw here: - If a required run is cancelled - there is not a unique recipe out the MOM should try to repeat that run ASAP. Sometimes this can take months … info is not passed to the next MOM - I suggest a list of pending runs keep tracks of requests... I expect this practice to improve with a more established system

March 24th 2010MICE CM26 - Riverside15 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions Hi All The results of the 2Vs activation run show that there was a slight increase in activation in straight 7. With this in mind we have agreed to set the new beam loss limit for MICE operations at 2Vs for two 8 hour shifts per week and any further shifts at the 1 Vs level. I enclose an documents with the last two surveys and analysis. Regards Dean Adams

March 24th 2010MICE CM26 - Riverside16 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions MOM BLOCShifter perfect shift - the trinity MOM / BLOC / Shifter seems a good combination - needless to say the perfect number of persons in the MICE LCR is 3

March 24th 2010MICE CM26 - Riverside17 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions Summary … of the Run Summary dategoal# target pulses triggerpolaritynotes 7/2/2010Lumi-mon commissioning ~ /2/2010On Line monitoring test ~ /2/2010TOF2 calibration~ /2/2010OnLine reconstruction~ /3/2010Test run500Test run after interruption 5/3/2010Test run1000“ 10/3/2010TOF / KL calib /3/2010TOF / KL calib /3/2010Proton Absorber Test /3/2010TOF calib …0 !ISIS down for 10 hrs ~30000

March 24th 2010MICE CM26 - Riverside18 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions RUN 1525 – NO p-absorber (1000 pulses)

19 RUN 1520 – 10cm p-absorber (780 pulses) BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions

March 24th 2010MICE CM26 - Riverside20 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions GOOD - We know how to run - (MOM/BLOC/Shifter) - LumiMon installed - Proton Absorber tested - Slew Rate for MPUs imminent - DAQ running - Data Quality (started) - OnLine Mon running BAD - DS status: anything else behind the corner? - Network/Data: analysis for commissiong data not facilitated by nw and data saving structures - Data Quality … need feedback from experts - LogBook: when it fails we can even wait a day before it’s back … - Need a better communication between parties We have learnt a lot, we keep learning and spread “knowledge” (new MOMs) With it the awareness of the growing complexity of the system: it looks more and more fragile and prone to errors … Personal concern for a near future scenario

March 24th 2010MICE CM26 - Riverside21 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions

March 24th 2010MICE CM26 - Riverside22 BL /DS DAQ/OL CAM Luminosity Monitor Target Running Practice Network/DATA Conclusions    Thanks to … a lot of people expecially the ones who helped subbing me during this MOM time (Willie, Ken, Pierrick …) As usual I wish the best for the next to come, Paul.